Planning application
Devonport House and Cooper Building, 66-68 King William Walk, Greenwich, SE10 9JW
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
An application submitted under Section 96a of the Town & Country Planning Act 1990 for a non-mate...
As published by the council, reference 26/2762/NM
Application record
- Reference
- 26/2762/NM
- Status
- Decided
- Decision
- Granted As published: Approve
- Received
- 22 Sep 2026
- Decided
- 28 Sep 2026
- Postcode
- SE10 9JW
Site history
Applications at this address on the Greenwich register
This site has had 26 applications since 2025: 22 approved, 0 refused.
-
26/1747/SD Granted
Devonport House and Cooper Building, 66-68 King William Walk, Greenwich SE10 9JW
Submission of details pursuant to the partial discharge of Condition 11 (Fire Safety Strategy) in...
-
26/1585/SD Decided
Devonport House and Cooper Building, 66-68 King William Walk, Greenwich, SE10 9JW
Submission of details pursuant to the partial discharge of condition 34 (Green / Brown Roofs) in ...
-
26/1313/SD Awaiting decision
Devonport House and Cooper Building, 66-68 King William Walk, Greenwich, SE10 9JW
Submission of details pursuant to discharge condition 9 (Piling) and to partially discharge condition 15, part D (Archaeology) in relation to Planning Permission 24/3426/F dated 26/11/2025.
-
26/0982/SD Withdrawn
Devonport House and Cooper Building, 66-68 King William Walk, Greenwich, SE10 9JW
Submission of details pursuant to part discharge condition 9 (Piling) solely in relation to Area C in relation to Planning Permission 24/3426/F dated 26/11/2025.
-
26/0983/SD Granted
Devonport House and Cooper Building, 66-68 King William Walk, Greenwich, SE10 9JW
Submission of details pursuant to discharge Condition 23 (Digital Connectivity) in relation to Planning Permission 24/3426/F dated 26/11/2025.
-
26/0676/SD Granted
Devonport House and Cooper Building, 66-68 King William Walk, Greenwich, SE10 9JW
Submission of details pursuant to discharge part D of Condition 15 (Archaeology) solely in relation to the proposed Art Wall Building in relation to Planning Permission 24/3426/F dated 26/11/2025
-
26/0494/I106 Granted
Devonport House and Cooper Building, 66-68 King William Walk, Greenwich, SE10 9JW
Submission of details pursuant to Schedule 3, Part 1, Paragraph 1.1.1 (BNG Monitoring Contribution), Schedule 3, Part 1, Paragraph 1.1.2 (First Carbon Offsetting Contribution), Schedule 3, Part 3, Paragraph 3.1 (Monitoring Costs) associated with the S106 Agreement relating to ref.24/3426/F and 24/3427/L
-
26/0262/SD Granted
Devonport House and Cooper Building, 66-68 King William Walk, Greenwich, SE10 9JW
Submission of details pursuant to the discharge of Condition 17 (Materials and Details - Art Wall...
-
25/4053/NM Granted
Devonport House and Cooper Building, 66-68 King William Walk, Greenwich, SE10 9JW
An application submitted under Section 96a of the Town & Country Planning Act 1990 for a non-material amendment in connection with planning consent (24/3426/F) dated 26/11/2025 to allow: Entrance design changes, Facade material amendments, Internal layout changes and Alterations to the Art wall/substation building, tree species and gutter details. Amendments to conditions 2 (approved plans) and 34 (green / brown roofs) noting the amendments brought forwards by this application.
-
25/4038/SD Granted
Devonport House and Cooper Building, 66-68 King William Walk, Greenwich, SE10 9JW
Submission of details pursuant to discharge Condition 9 (Piling and Foundations) in relation to Planning Permission 24/3426/F dated 26/11/2025.
Timeline
Dates from the published record
-
22 Sep 2026
Received by Greenwich
-
28 Sep 2026
Decision issued: Approve
-
28 Sep 2026
Added to PlanIndex
-
28 Sep 2026
Status changed to Decided
Previously Registered.
What this grant of permission means
Greenwich granted permission on 28 September 2026, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About this record
The published feed does not state which type of application this is; the register entry on Greenwich's portal will say. Our guide explains the common types.
Nearby applications
Within 0.3 miles
-
Devonport House and Cooper Building, 66-68 King William Walk, Greenwich, SE10 9JW
84% historically approved · decision due ~21 Jul
Submission of details pursuant to the partial discharge of condition 34 (Green / Brown Roofs) in ...
Decided 8 docs -
Devonport House and Cooper Building, 66-68 King William Walk, Greenwich, London SE10 9JW
84% historically approved · decision due ~21 Oct
Submission of details pursuant to discharge Condition 14 (Drainage Strategy) in relation to Plann...
Awaiting decision 4 docs -
Devonport House and Cooper Building, 66-68 King William Walk. Greenwich, London SE10 9JW
84% historically approved · decision due ~20 Aug
Submission of details pursuant to discharge of Condition 16 (Boundary Gates) in relation to Plann...
Decided 4 docs -
Devonport House and Cooper Building, 66-68 King William Walk, Greenwich, London SE10 9JW
84% historically approved · decision due ~17 Aug
Submission of details pursuant to discharge Condition 26, part A (Cycle Parking) in relation to P...
Decided 4 docs -
Devonport House and Cooper Building, 66-68 King William Walk, Greenwich, SE10 9JW
Submission of details pursuant to the discharge of Condition 17 (Materials and Details - Art Wall...
Granted 9 docs -
Devonport House and Cooper Building, 66-68 King William Walk, Greenwich, London SE10 9JW
Submission of details pursuant to the partial discharge of condition 24 (Secure by Design) in rel...
Granted 11 docs