Planning application

Locquiers Farm Plump Hill Mitcheldean Gloucestershire GL17 0HQ

Granted Forest of Dean P0693/26/NONMAT

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Non-material amendment to P0980/21/FUL to allow for amendments to dimension of transformer housing.

As published by the council, reference P0693/26/NONMAT

Application record

Reference
P0693/26/NONMAT
Status
Consent
Decision
Granted Permission
Received
12 Jun 2026
Validated
12 Jun 2026
Decided
26 Jun 2026
Ward
Mitcheldean, Ruardean & Drybrook
Parish
Drybrook
Decision by
Delegated Decision
Postcode
GL17 0HQ

Site history

Applications at this address on the Forest of Dean register

This site has had 3 applications since 2020: 2 approved, 0 refused.

  • P1003/25/FUL Granted

    Locquiers Farm Plump Hill Mitcheldean Gloucestershire GL17 0HQ

    Variation of condition 02 (approved plans) of planning permission P0980/21/FUL to allow for alterations to substations and solar panels.

    Decided 23 Oct 2025 Full applications
  • P0970/21/EIA Decided

    Locquiers Farm Plump Hill Mitcheldean Gloucestershire GL17 0HQ

    Decided 23 Feb 2021 Outline

Timeline

Dates from the published record

  1. 12 Jun 2026

    Received by Forest of Dean

  2. 26 Jun 2026

    Decision issued: Granted Permission

  3. 27 Jul 2026

    Added to PlanIndex

Cases linked to this one on the register

  • Application: P0980/21/FUL (Consent)

Documents

Plans, drawings, consultee responses and the officer's report

4 documents on file for this application

  • APPLICATION FORM Application Form · 12 Jun 2026
  • DETAIL DRAWING Drawing · 12 Jun 2026
  • TYPICAL SUBSTATION HOUSINGS DETAIL Drawing · 12 Jun 2026
  • COVERING LETTER Agent letter · 12 Jun 2026

Trade members open them from here.

Open the documents

What this grant of permission means

Forest of Dean granted permission on 26 June 2026, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About this record

The published feed does not state which type of application this is; the register entry on Forest of Dean's portal will say. Our guide explains the common types.