Land To The South Of Murrells End Hartpury Gloucestershire

Refused Forest of Dean P0271/22/FUL Full Application

Refused. Only the applicant can appeal, within the statutory time limit, and a revised scheme can be submitted instead.

Proposal

Installation and operation of a renewable energy generating station comprising ground-mounted photovoltaic solar arrays together with inverter units, substation, site access, internal access tracks, security measures, access gates, other ancillary infrastructure and landscaping and biodiversity enhancements.

As published by the council, reference P0271/22/FUL

Application record

Reference
P0271/22/FUL
Type
Full Application
Status
Refused
Decision
Refused
Received
25 Feb 2022
Validated
1 Jun 2022
Decided
14 Mar 2023
Ward
Hartpury & Redmarley
Parish
Hartpury
Decision by
Committee Decision
Postcode
GL19 3DF

Timeline

Dates from the published record

  1. 25 Feb 2022

    Received by Forest of Dean

  2. 1 Jun 2022

    Validated

    Checked as complete and ready for consideration.

  3. 14 Mar 2023

    Decision issued: Refused

  4. 2 Aug 2026

    Added to PlanIndex

Cases linked to this one on the register

  • Appeal: AP0027/23/REF (Appeal Dismissed)

Who's behind it

Company information only, from the register and Companies House

RPS Group plc Agent

125 applications on PlanIndex · across 50 councils · 80% granted

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Elgin Energy EsCo Ltd Applicant

6 applications on PlanIndex · across 4 councils

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Documents

Plans, drawings, consultee responses and the officer's report

201 documents on file for this application

  • APPEAL DISMISSED Appeal Decision · 15 Jul 2024
  • NATURAL ENGLAND - ANNEX A Consultee Comment · 08 May 2024
  • RUDFORD AND HIGHLEADON PARISH COUNCIL Consultee Comment · 20 Dec 2023
  • WOLFSON Public Comment · 20 Dec 2023
  • ORRITT -27.11.2023 Public Comment · 20 Dec 2023
  • STATEMENT OF CASE Council`s Case · 19 Dec 2023
  • STATEMENT OF CASE - APPENDIX 12 Council`s Case · 19 Dec 2023
  • STATEMENT OF CASE - APPENDIX 11 Council`s Case · 19 Dec 2023
  • STATEMENT OF CASE - APPENDIX 10 Council`s Case · 19 Dec 2023
  • STATEMENT OF CASE - APPENDIX 9 LAYOUT PLAN Council`s Case · 19 Dec 2023
  • STATEMENT OF CASE - APPENDIX 9 LOCATION PLAN Council`s Case · 19 Dec 2023
  • STATEMENT OF CASE - APPENDIX 8 Council`s Case · 19 Dec 2023
  • STATEMENT OF CASE - APPENDIX 7 LANDSCAPE STATEMENT Council`s Case · 19 Dec 2023
  • STATEMENT OF CASE - APPENDIX 7 LANDSCAPE STATEMENT APPENDIX CT-1 Council`s Case · 19 Dec 2023
  • STATEMENT OF CASE - APPENDIX 7 LANDSCAPE STATEMENT APPENDIX CT-2 Council`s Case · 19 Dec 2023
  • STATEMENT OF CASE - APPENDIX 5 SCREENING OPINION Council`s Case · 19 Dec 2023
  • STATEMENT OF CASE - APPENDIX 4 PRE-APP REPORT Council`s Case · 19 Dec 2023
  • STATEMENT OF CASE - APPENDIX 4 OFFICER RESPONSE Council`s Case · 19 Dec 2023
  • STATEMENT OF CASE - APPENDIX 4 FURTHER OFFICER RESPONSE Council`s Case · 19 Dec 2023
  • STATEMENT OF CASE - APPENDIX 3 SITE MAP Council`s Case · 19 Dec 2023
  • STATEMENT OF CASE - APPENDIX 2 Council`s Case · 19 Dec 2023
  • STATEMENT OF CASE - APPENDIX 1 CORRESPONDENCE Council`s Case · 19 Dec 2023
  • STATEMENT OF CASE - APPENDIX 1 CORRESPONDENCE Council`s Case · 19 Dec 2023
  • STATEMENT OF CASE - APPENDIX 1 CORRESPONDENCE Council`s Case · 19 Dec 2023
  • STATEMENT OF CASE - APPENDIX 1 CORRESPONDENCE Council`s Case · 19 Dec 2023
  • STATEMENT OF CASE - APPENDIX 1 AREAS OF NO DIG PLAN Council`s Case · 19 Dec 2023
  • STATEMENT OF CASE - APPENDIX 15 Council`s Case · 19 Dec 2023
  • STATEMENT OF CASE - APPENDIX 14 Council`s Case · 19 Dec 2023
  • STATEMENT OF CASE - APPENDIX 13 Council`s Case · 19 Dec 2023
  • STATEMENT OF CASE - APPENDIX 9 DECISION NOTICE Council`s Case · 19 Dec 2023
  • STATEMENT OF CASE - APPENDIX 7 LANDSCAPE STATEMENT APPENDIX CT-3 Council`s Case · 19 Dec 2023
  • STATEMENT OF CASE - APPENDIX 7 LANDSCAPE STATEMENT APPENDIX CT-4 Council`s Case · 19 Dec 2023
  • STATEMENT OF CASE - APPENDIX 6 Council`s Case · 19 Dec 2023
  • STATEMENT OF CASE - APPENDIX 5 SCREENING DETERMINATION Council`s Case · 19 Dec 2023
  • STATEMENT OF CASE - APPENDIX 4 CONSULTEE COMMENTS Council`s Case · 19 Dec 2023
  • STATEMENT OF CASE - APPENDIX 4 CONSULTEE PHOTOGRAPHS Council`s Case · 19 Dec 2023
  • STATEMENT OF CASE - APPENDIX 3 SITE MAP Council`s Case · 19 Dec 2023
  • STATEMENT OF CASE - APPENDIX 3 AERIAL MAP Council`s Case · 19 Dec 2023
  • AREAS OF 'NO-DIG' INSTALLATION Drawing · 18 Dec 2023
  • ECOLOGICAL ADDENDUM 2023 ? FINAL REPORT Appellants Case · 21 Nov 2023
  • HEARING QUESTIONNAIRE Questionnaire · 10 Nov 2023
  • STATEMENT OF CASE - APPENDIX 5 APPEAL DECISION Appellants Case · 03 Nov 2023
  • STATEMENT OF CASE - APPENDIX 5 APPEAL DECISION Appellants Case · 03 Nov 2023
  • STATEMENT OF CASE - APPENDIX 10 Appellants Case · 03 Nov 2023
  • STATEMENT OF CASE Appellants Case · 03 Nov 2023
  • STATEMENT OF CASE - APPENDIX 2 Appellants Case · 03 Nov 2023
  • STATEMENT OF CASE - APPENDIX 3 Appellants Case · 03 Nov 2023
  • STATEMENT OF CASE - APPENDIX 6 Appellants Case · 03 Nov 2023
  • STATEMENT OF CASE - APPENDIX 7 Appellants Case · 03 Nov 2023
  • STATEMENT OF CASE - APPENDIX 8 Appellants Case · 03 Nov 2023
  • STATEMENT OF CASE - APPENDIX 9 Appellants Case · 03 Nov 2023
  • STATEMENT OF CASE - APPENDIX 12 Appellants Case · 03 Nov 2023
  • STATEMENT OF CASE - APPENDIX 4 Appellants Case · 03 Nov 2023
  • STATEMENT OF CASE - APPENDIX 5 APPEAL DECISION Appellants Case · 03 Nov 2023
  • STATEMENT OF CASE - APPENDIX 5 DECISION NOTICE Appellants Case · 03 Nov 2023
  • STATEMENT OF CASE - APPENDIX 5 CORRESPONDENCE Appellants Case · 03 Nov 2023
  • STATEMENT OF CASE - APPENDIX 1 Appellants Case · 03 Nov 2023
  • STATEMENT OF CASE - APPENDIX 11 Appellants Case · 03 Nov 2023
  • STATEMENT OF CASE - APPENDIX 13 Appellants Case · 03 Nov 2023
  • STATEMENT OF CASE - APPENDIX 4 PHOTOGRAPH Appellants Case · 03 Nov 2023
  • STATEMENT OF CASE - APPENDIX 4 PHOTOGRAPH Appellants Case · 03 Nov 2023
  • GEOPHYSICAL SURVEY REPORT Appellants Case · 02 Nov 2023
  • SITE LAYOUT PLAN Appellants Case · 02 Nov 2023
  • SUBSTATION PLANS Appellants Case · 02 Nov 2023
  • DEVELOPMENT MANAGEMENT COMMITTEE 14.03.2023 Committee schedule extract · 14 Aug 2023
  • LETTER- TO SECRETARY OF STATE RE: DECISION Correspondence · 16 Mar 2023
  • EIA REGULATION STATEMENT Correspondence · 15 Mar 2023
  • SITE INSPECTION PANEL NOTES Correspondence · 08 Mar 2023
  • HISTORIC ENGLAND Consultee Comment · 24 Feb 2023
  • GCC HIGHWAYS Consultee Comment · 21 Feb 2023
  • HARTPURY PARISH COUNCIL Consultee Comment · 20 Feb 2023
  • SUSTAINABILITY - ECOLOGY Consultee Comment · 15 Feb 2023
  • ENVIRONMENT AGENCY Consultee Comment · 13 Feb 2023
  • ENVIRONMENT AGENCY REQUESTS AN EXTENSION OF TIME TO RESPOND Correspondence · 09 Feb 2023
  • HISTORIC ENGLAND Consultee Comment · 26 Jan 2023
  • RUDFORD AND HIGHLEADON PARISH COUNCIL Consultee Comment · 25 Jan 2023
  • RUDFORD AND HIGHLEADON PARISH COUNCIL Consultee Comment · 24 Jan 2023
  • HISTORIC ENGLAND Consultee Comment · 23 Jan 2023
  • RUDFORD AND HIGHLEADON PARISH COUNCIL Consultee Comment · 18 Jan 2023
  • PARISH COUNCIL CONFIRMATION OF EXTENSION OF TIME TO RESPOND Correspondence · 17 Jan 2023
  • REVISED DRAWING- SITE LAYOUT Drawing · 12 Jan 2023
  • ADDITIONAL LETTER- RESPONSE TO COUNCILS ECOLOGIST Correspondence · 12 Jan 2023
  • ADDITIONAL ECOLOGICAL ADDENDUM Report · 12 Jan 2023
  • ADDITIONAL NOISE LEVELS DAY Report · 12 Jan 2023
  • ADDITIONAL ECOLOGICAL APPRAISAL Report · 12 Jan 2023
  • ADDITIONAL NOISE LEVELS NIGHT Report · 12 Jan 2023
  • ADDITIONAL HERITAGE RESPONSE Report · 12 Jan 2023
  • OFFICER/AGENT EMAIL Correspondence · 12 Jan 2023
  • AGENT LETTER- RE: CONSULTATION RESPONSES (RESPONSE) Correspondence · 12 Jan 2023
  • ADDITIONAL ARCHAEOLOGY WRITTEN SCHEME OF INVESTIGATION Report · 12 Jan 2023
  • ADDITIONAL NOISE LEVELS 5 ? 7AM Report · 12 Jan 2023
  • AGREEMENT TO EXTENSION OF TIME Correspondence · 16 Dec 2022
  • CPRE Consultee Comment · 15 Sep 2022
  • NATURAL ENGLAND Consultee Comment · 12 Sep 2022
  • APPLICATION SUMMARY Correspondence · 01 Sep 2022
  • AGREEMENT TO EXTENSION OF TIME Correspondence · 31 Aug 2022
  • CORRESPONDENCE RE: E-MAIL TO AGENT Correspondence · 22 Aug 2022
  • SUSTAINABILITY APPRORIATE ASSESSMENT Consultee Comment · 22 Aug 2022
  • SUSTAINABILITY LIKELY SIGNIFICANT EFFECTS Consultee Comment · 22 Aug 2022
  • SUSTAINABILITY ECOLOGY Consultee Comment · 22 Aug 2022
  • OFFICER REQUEST FOR EXTENSION OF TIME Correspondence · 17 Aug 2022
  • LANDSCAPE OFFICER Consultee Comment · 15 Aug 2022
  • HISTORIC ENGLAND Consultee Comment · 11 Aug 2022
  • ENVIRONMENT AGENCY Consultee Comment · 10 Aug 2022
  • NATURAL ENGLAND Consultee Comment · 05 Aug 2022
  • HARTPURY PARISH COUNCIL Consultee Comment · 29 Jul 2022
  • PARISH COUNCIL Consultee Comment · 26 Jul 2022
  • CONSERVATION ADVISOR Consultee Comment · 25 Jul 2022
  • COUNTY ARCHAEOLOGIST Consultee Comment · 13 Jul 2022
  • SUSTAINABILITY GCN Consultee Comment · 13 Jul 2022
  • GCC MINERALS AND WASTE Consultee Comment · 07 Jul 2022
  • LOCAL PLANS Consultee Comment · 28 Jun 2022
  • GCC PUBLIC RIGHTS OF WAY (PROW) Consultee Comment · 28 Jun 2022
  • LAND DRAINAGE OFFICER Consultee Comment · 24 Jun 2022
  • CORRESPONDENCE OFFICER/AGENT Correspondence · 22 Jun 2022
  • GCC LEAD LOCAL FLOOOD AUTHORITY Consultee Comment · 21 Jun 2022
  • SUSTAINABILITY TREES Consultee Comment · 21 Jun 2022
  • PARISH COUNCIL EXTENSION OF TIME AGREEMENT TO RESPOND Correspondence · 21 Jun 2022
  • AGREEMENT TO PARISH COUNCIL EXTENSION OF TIME Correspondence · 20 Jun 2022
  • ENVIRONMENTAL STATEMENT CHAPTERS - MURRELLS END CHAPTER 5 LANDSCAPE Report · 20 Jun 2022
  • FIGURE 1.1 MURRELLS END SITE LOCATION PLAN Drawing · 20 Jun 2022
  • FIGURE 5.1_DESIGNATIONS Drawing · 20 Jun 2022
  • FIGURE 5.4A_ZTV & VIEWPOINTS Drawing · 20 Jun 2022
  • FIGURE 5.4B_LCA+ZTV Drawing · 20 Jun 2022
  • FIGURE 5.27 TO 5.32 PHOTOMONTAGES_4268-0007-01 R Drawing · 20 Jun 2022
  • FIGURE 5.33_LANDSCAPE PROPOSALS Drawing · 20 Jun 2022
  • FIGURE 7.2 NON.DESIGNATED ASSETS Drawing · 20 Jun 2022
  • FIGURE 7.6 LIDAR SLRM Drawing · 20 Jun 2022
  • FIGURE 7.10 HLC Drawing · 20 Jun 2022
  • FIGURE 7.9 GEOPHYS Drawing · 20 Jun 2022
  • APPENDIX 1.2 STATEMENT OF EXPERTISE Report · 20 Jun 2022
  • APPENDIX 2.1 MURRELLS END - CONSTRUCTION TRAFFIC MANAGEMENT PLAN Report · 20 Jun 2022
  • APPENDIX 4.1 CUMULATIVE ASSESSMENT 2022 Report · 20 Jun 2022
  • APPENDIX 5.2 MURRELLS END - GLINT AND GLARE Report · 20 Jun 2022
  • APPENDIX 7.2 HISTORIC ENV GAZETTEER Report · 20 Jun 2022
  • APPENDIX 8.3 NOISE REPORT Report · 20 Jun 2022
  • APPENDIX 8.4 AGRICULTURAL LAND CLASSFICATION Report · 20 Jun 2022
  • VOL 3 CONTENTS Report · 20 Jun 2022
  • ENVIRONMENTAL STATEMENT CHAPTERS - MURRELLS END CHAPTER 1 INTRODUCTION Report · 20 Jun 2022
  • ENVIRONMENTAL STATEMENT CHAPTERS - MURRELLS END CHAPTER 2 PROJECT DESCRIPTION Report · 20 Jun 2022
  • ENVIRONMENTAL STATEMENT CHAPTERS -MURRELLS END CHAPTER 3 NEEDS AND ALTERNATIVES Report · 20 Jun 2022
  • ENVIRONMENTAL STATEMENT CHAPTERS -MURRELLS END CHAPTER 4 EIA METHODOLOGY Report · 20 Jun 2022
  • ENVIRONMENTAL STATEMENT CHAPTERS -MURRELLS END CHAPTER 6 BIODIVERSITY Report · 20 Jun 2022
  • ENVIRONMENTAL STATEMENT CHAPTERS - MURRELLS END CHAPTER 7 HISTORIC ENV Report · 20 Jun 2022
  • ENVIRONMENTAL STATEMENT CHAPTERS - MURRELLS END CHAPTER 8 OTHER ENV EFFECTS Report · 20 Jun 2022
  • ENVIRONMENTAL STATEMENT CHAPTERS -VOL 1 CONTENTS AND GLOSSARY Report · 20 Jun 2022
  • APPENDIX 6.3 MURRELLS END BNG ASSESSMENT_DRAFT_220524 Report · 20 Jun 2022
  • APPENDIX 8.2 FLOOD RISK ASSESSMENT Report · 20 Jun 2022
  • FIGURE 5.2_LCA Drawing · 20 Jun 2022
  • FIGURE 5.3_TOPOGRAPHY Drawing · 20 Jun 2022
  • FIGURE 5.5 TO 5.26 PANORAMAS_4268-0001-07 R Drawing · 20 Jun 2022
  • APPENDIX 1.1 REQUIREMENTS OF EIA LEGISLATION Report · 20 Jun 2022
  • APPENDIX 5.1 LANDSCAPE PLANNING POLICY Report · 20 Jun 2022
  • APPENDIX 6.1 ECOLOGICAL ASSESSMENT Report · 20 Jun 2022
  • ENVIRONMENTAL STATEMENT - NON TECHNICAL SUMMARY Report · 20 Jun 2022
  • FIGURE 2.1 JPW1643-002REVC_D220218_(MURRELLS FARM SOLAR PLANNING RED LINE). Drawing · 20 Jun 2022
  • FIGURE 2.2 JPW1643-001REVJ_D220222_(MURRELLS FARM SOLAR LAYOUT DESIGN) Drawing · 20 Jun 2022
  • FIGURE 7.1 DESIGNATED ASSETS Drawing · 20 Jun 2022
  • FIGURE 7.3 1811 OSD Drawing · 20 Jun 2022
  • FIGURE 7.4 1883 OS Drawing · 20 Jun 2022
  • FIGURE 7.5 1903 OS Drawing · 20 Jun 2022
  • FIGURE 7.7 GEOPHYS Drawing · 20 Jun 2022
  • FIGURE 7.8 GEOPHYS Drawing · 20 Jun 2022
  • VOL 2 CONTENTS ENVIRONMENTAL STATEMENT Report · 20 Jun 2022
  • APPENDIX 2.2 COCP Report · 20 Jun 2022
  • APPENDIX 6.2 ECOLOGICAL ADDENDUM Report · 20 Jun 2022
  • APPENDIX 7.1 HISTORIC ENV PLANNING POLICY Report · 20 Jun 2022
  • APPENDIX 8.1 TRANSPORT STATEMENT Report · 20 Jun 2022
  • WALES AND WEST UTILITIES RESPONSE WITH MAP Correspondence · 16 Jun 2022
  • WESTERN POWER DISTRIBUTION RESPONSE Correspondence · 16 Jun 2022
  • NATIONAL GRID RESPONSE Correspondence · 16 Jun 2022
  • WALES AND WEST UTILITIES RESPONSE Correspondence · 16 Jun 2022
  • WESTERN POWER DISTRIBUTION WITH MAP Correspondence · 16 Jun 2022
  • WESTERN POWER DISTRIBUTION CHARGING STRUCTURE Correspondence · 16 Jun 2022
  • ENATIONAL GRID LINE SEARCH ENQUIRY RESPONSE Correspondence · 16 Jun 2022
  • GIGACLEAR RESPONSE Correspondence · 16 Jun 2022
  • EMAIL WESTERN POWER DISTRIBUTION Correspondence · 16 Jun 2022
  • ENVIRONMENT AGENCY CHECKLIST Environment Agency Checklist · 13 Jun 2022
  • D&A Report · 12 Apr 2022
  • TRANSPORT STATEMENT Report · 12 Apr 2022
  • CONSRUCTION TRAFFIC MANAGEMENT PLAN Report · 06 Apr 2022
  • GEOPHYSICAL SURVEY Report · 06 Apr 2022
  • GLINT AND GLARE STUDY Report · 06 Apr 2022
  • FLOOD RISK ASSESSMENT Report · 06 Apr 2022
  • NOISE REPORT Report · 06 Apr 2022
  • TRANSPORT STATEMENT Report · 06 Apr 2022
  • ARBORICULTURAL IMPACT ASSESSMENT Report · 06 Apr 2022
  • AGRICULTURAL LAND CLASSIFICATION Report · 06 Apr 2022
  • THE LOCATION PLAN Drawing · 25 Feb 2022
  • SITE PLAN - CONCEPT SOLAR DESIGN Drawing · 25 Feb 2022
  • REPORT - 6 PAGES - WESTERN POWER Drawing · 25 Feb 2022
  • TYPICAL PANEL - PLANNING DETAILS Drawing · 25 Feb 2022
  • FENCE AND GATE DETAILS Drawing · 25 Feb 2022
  • ACCESS ROAD Drawing · 25 Feb 2022
  • TYPICAL INVERTER Drawing · 25 Feb 2022
  • TEMPORARY CONSTRUCTION COMPOUND Drawing · 25 Feb 2022
  • CCTV DETAILS Drawing · 25 Feb 2022
  • CABLE TRENCH DETAIL Drawing · 25 Feb 2022
  • 8 DRAWINGS - TOPOGRAPHICIAL SURVEY Drawing · 25 Feb 2022
  • COVERING LETTER Agent letter · 25 Feb 2022
  • DESIGN AND ACCESS STATEMENT Report · 25 Feb 2022

Watch members (£5 a month) open the document list from here.

Open the documents

What this refusal means

Forest of Dean refused this application for the reasons on the decision notice; only the applicant can appeal, and refused schemes often return in revised form. More in our guide to what happens after a planning decision.

About full applications

A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.

In Forest of Dean

  • P1090/26/FUL Awaiting decision

    SPP Pumps Ltd Crucible Close Coleford Gloucestershire GL16 8RE

    Erection of a semi permanent building providing 342m² of undercover storage for engines and metal fabrications currently stored externally within the existing yard.

    Received 8 Oct, published by the council 13 Oct 2026 Full applications
  • P0902/26/FUL Granted

    Sunnyside Crow Ash Road Berry Hill Coleford Gloucestershire GL16 7RB

    Demolition of existing kitchen extension and erection of two storey side extension with single storey wrapping round rear of the property.

    Received 3 Aug, published by the council 11 Aug 2026 Full applications
  • P0800/26/FUL Granted

    Dennel Hill Farmhouse Tidenham Chase Chepstow NP16 7JN

    Erection of rear 1.5 storey extension with balcony and first floor extension with balcony to allow for extended first floor level with associated internal alterations and works. Demolition of existing rear conservatory.

    Received 7 Jul, published by the council 20 Aug 2026 Full applications
  • P0682/26/FUL Granted

    7 Woodgate Road Mile End Coleford Gloucestershire GL16 7QE

    Proposed Vehicular Access and Parking and associated works

    Received 10 Jun, published by the council 27 Jul 2026 Full applications
  • P0213/26/FUL Granted

    Land At 34 Worrall Hill Gloucestershire GL17 9QE

    Erection of a self-build dwelling and associated works

    Received 23 Feb, published by the council 27 Jul 2026 Full applications