Planning application
LA10/2026/0069/NMC
150M SOUTH OF 5 KILLYPADDY ROAD, LISNASKEA, BT92
Proposal
Non-material change to application LA10/2021/1013/F for proposed changes to western terraces from 7+7 units within each block to 8+6 units along with re-alignment of proposed car parking to rear of apartment block
As published by the council, reference LA10/2026/0069/NMC
Timeline
Dates from the published record
-
26 Jan 2026
Received by Fermanagh and Omagh
-
2 Feb 2026
Validated
Checked as complete and ready for consideration.
-
12 Feb 2026
Decision issued: Granted
-
29 Jul 2026
Added to PlanIndex
What a grant of permission means
The process from here
Permission has been granted, usually subject to conditions listed on the decision notice, some of which must be discharged before work starts. The decision notice on the council portal sets out exactly what was approved.
Work must normally begin within three years of the decision or the permission lapses. Neighbours cannot appeal a grant; challenging one means judicial review of how the decision was made, within tight time limits.
About amendments applications
How this application type works
An amendment application changes a permission that already exists. Non-material amendments cover small adjustments with no wider effect, while minor material amendments, usually made by varying a condition, allow modest design changes without a fresh application. Anything beyond that needs a new permission, so the scope here is deliberately narrow.
Nearby applications
Within 500 metres
-
LA10/2026/0469/DC Decided
150m S of 5 Killypaddy Road, Barnhill, Lisnaskea, BT92 0HD
Discharge of condition 1 (PSD) of planning approval LA10/2021/1013/F (housing development).
-
LA10/2026/0676/DC Awaiting decision
75 Main Street and nos. 1 & 3 Water Street, Lisnaskea
Discharge of condition 2 (archaeological programme of works) of planning approval LA10/2026/0324/F (community building).
-
LA10/2026/0344/DCA Granted
75 Main Street, and no.s 1 & 3 Water Street, Lisnaskea, BT92 0JD
Demolition of former supermarket, associated storage buildings and semi-detached dwellings
-
LA10/2026/0324/F Granted
75 Main Street and Nos. 1 & 3 Water Street, Lisnaskea
Demolition of existing buildings and erection of proposed mixed-use building to provide community group facilities, offices, cafe & ancillary spaces. Men's & Ladies' Shed facility, 4 No. emergency single occupancy apartments, 4No. self-catering overnight accommodation units, plus dedicated family services building incorporating a creche for 0-3yrs old
-
LA10/2025/1193/F Granted
Mcgarry Dental Design 101 Main Street, Lisnaskea, BT92 0JD
proposed change of use from Class C1 residential to Class D1 community and cultural use, there are no proposed alterations to the building.
-
LA10/2026/0013/F Granted
175 Main Street, Lisnaskea, BT92 0JE
Redevelopment of the existing former public house to form a ground-floor pharmacy, with ancillary spaces and 4no. apartments above.
Other amendments applications
In Fermanagh and Omagh
-
LA10/2026/0680/NMC Awaiting decision
Omagh Academy, Strule Shared Education Campus, Gortin Road, Omagh
Non Material Change comprising: incorporation of louvres; amendments to parapet heights; relocation and reduction to curtain walling/glazing; amendments to floor to floor heights; revision of cladding colours; minor reconfiguration of internal areas; and provision of roof access ladders to Omagh Academy approved under LA10/2016/0711/RM.
-
LA10/2026/0682/NMC Awaiting decision
Shared Sports Centre, Strule Shared Education Campus, Gortin Road, Omagh
Non Material Change to comprising: amendments to parapets; removal of roof terrace; provision of additional fire exit doors; amendments to door and window sizes and locations; incorporation of louvres; minor reconfiguration of internal areas; provision of roof access ladders; reconfiguration and amendment to mechanical and electrical plant; and amendments to external materials to the Shared Sports Centre building approved under LA10/2016/0711/RM.
-
LA10/2026/0678/NMC Awaiting decision
Christian Brothers Grammar School, Strule Shared Education Campus, Gortin Road, Omagh
Non Material Change comprising: incorporation of louvres; reconfiguration of window sizes, openings and locations; reconfiguration of areas for future roof PV panelling; reconfiguration of roof plant; amendments to parapet heights; minor reconfiguration of internal areas and provision of roof access ladders to Christian Brothers Grammar School approved under LA10/2016/0711/RM.
-
LA10/2026/0685/NMC Awaiting decision
Sacred Heart College, Strule Shared Education Campus, Gortin Road, Omagh
Non Material Change comprising: incorporation of louvres; relocation, reduction and amendments to windows; provision of new door; amendments to parapet and floor to floor heights; reduction in amount of brickwork; reconfiguration and amendment to mechanical and electrical plant; minor reconfiguration of internal areas; and provision of roof access ladders. to Sacred Heart College approved under LA10/2016/0711/RM.
-
LA10/2026/0683/NMC Awaiting decision
Shared Education Centre, Strule Shared Education Campus, Gortin Road, Omagh
Non Material Change comprising: minor reconfiguration of internal areas; amendments to door sizes; amendment to window size and locations; amendment to parapets to provide guarding for roof access and maintenance; reconfiguration and amendment to mechanical and electrical (‘M&E’) plant; provision of additional fire exit doors; incorporation of louvres; amendments to curtain walling; rationalisation of secant wall alignment; amendment to floor to floor heights; reconfiguration of southern entrance; reconfiguration of Dance Drama Lecture and school meals area (‘SMA’) access; reconfiguration of bridge link; and provision of plant and ducting enclosures. to the Shared Education Centre approved under LA10/2016/0711/RM.