Skip to content
PlanIndex Get alerts
Menu

Planning application

Fell Wind Farm Grid Connection

Awaiting decision Dumfries and Galloway 26/1193/CSG SG Scoping/Screening/Gatecheck

Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.

Proposal

CONSULTATION REQUEST FROM SCOTTISH GOVERNMENT IN RELATION TO SCOPING OPINION UNDER THE TOWN AND COUNTRY PLANNING (ENVIRONMENTAL IMPACT ASSESSMENT) (SCOTLAND) REGULATIONS 2017 FOR A PROPOSED 33KV GRID CONNECTION TO CONNECT THE CONSENTED FELL WIND FARM TO THE ELECTRICITY GRID NETWORK

As published by the council, reference 26/1193/CSG

Application record

Reference
26/1193/CSG
Type
SG Scoping/Screening/Gatecheck
Status
Assessment Stage
Received
7 Jul 2026
Validated
7 Jul 2026
Ward
Dee And Glenkens
Parish
Balmaclellan Community Council

Timeline

Dates from the published record

  1. 7 Jul 2026

    Received by Dumfries and Galloway

  2. 29 Jul 2026

    Added to PlanIndex

  3. Decision

    Awaiting decision

    Decision expected by 1 September 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    Dumfries and Galloway took a median of 47 days over the applications it decided in the last year.

Documents

Plans, drawings, consultee responses and the officer's report

6 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Trade members open them from here.

Open the documents

What happens while it is decided

This application is with Dumfries and Galloway for determination, against a statutory target of eight weeks. Over the last year Dumfries and Galloway decided outline applications in a median of 1 days. More in our guide to how long planning decisions take.

About outline applications

An outline application tests the principle of developing a site, holding back details such as appearance and landscaping as reserved matters for later approval. More in our guide to planning application types.

In Dumfries and Galloway

  • 26/1552/UTL Granted

    Stoneykirk DG9 9BT

    INSTALLATION OF 8NO. TELECOMMUNICATIONS POLES

    3 Sep 2026 Outline
  • 26/1540/UTL Granted

    Outside Of Glendale Gillbrae Road Dumfries DG1 4EJ

    INSTALLATION OF 1NO. TELECOMMUNICATIONS POLE

    2 Sep 2026 Outline
  • 26/1548/UTL Awaiting decision

    1 Lochfield Carlisle Road Annan DG12 6QX

    INSTALLATION OF 1NO. TELECOMMUNICATIONS POLE

    2 Sep 2026 Outline
  • 26/0650/PIP Granted

    Damson Lodge Barholm Wood Creetown DG8 7EN

    ERECTION OF DWELLINGHOUSE AND INSTALLATION OF SEPTIC TANK AND SOAKAWAY

    20 Apr 2026 Outline
  • 26/1508/UTL Granted

    Near To 22 St Conal's Square And Main Street Kirkconnel DG4 6PH

    ERECTION OF 4 TELECOMMUNICATION POLES

    26 Aug 2026 Outline