Lorg Wind Farm Grid Connection (Formerly Known As Lorg And Longburn) Near Carsphairn

Granted Dumfries and Galloway 25/2174/S37 Section 37 Consultation

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

CONSULTATION REGARDING AN APPLICATION MADE UNDER SECTION 37 OF THE ELECTRICITY ACT 1989 FOR PROPOSED 17.5KM 132kv TRIDENT WOOD POLE OVERHEAD LINE FROM LORG WIND FARM TO THE PROPOSED HOLM HILL SUBSTATION (AMENDED DESCRIPTION)

As published by the council, reference 25/2174/S37

Application record

Reference
25/2174/S37
Type
Section 37 Consultation
Status
Decided
Decision
Raise No Objections
Received
27 Nov 2025
Validated
27 Nov 2025
Decided
18 Mar 2026
Ward
Dee And Glenkens
Parish
Carsphairn Community Council
Decision by
Planning Applications Committee

Timeline

Dates from the published record

  1. 27 Nov 2025

    Received by Dumfries and Galloway

  2. 18 Mar 2026

    Decision issued: Raise No Objections

  3. 29 Jul 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

7 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Trade members open them from here.

Open the documents

What this grant of permission means

Dumfries and Galloway granted permission on 18 March 2026, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About outline applications

An outline application tests the principle of developing a site, holding back details such as appearance and landscaping as reserved matters for later approval. More in our guide to planning application types.

In Dumfries and Galloway

  • 26/1574/UTL Granted

    Rear Of 28 Barkerland Avenue Dumfries DG1 4HR

    INSTALLATION OF 1NO. TELECOMMUNICATION POLE

    4 Sep 2026 Outline
  • 26/1573/UTL Granted

    OS 11 Glebe Place Annan DG12 6DQ

    INSTALLATION OF 2NO. TELECOMMUNICATION POLES

    4 Sep 2026 Outline
  • 26/1564/UTL Granted

    18 Queen Elizabeth Drive Castle Douglas DG7 1HH

    INSTALLATION OF 1NO. TELECOMMUNICATIONS POLE

    4 Sep 2026 Outline
  • 26/1552/UTL Granted

    Stoneykirk DG9 9BT

    INSTALLATION OF 8NO. TELECOMMUNICATIONS POLES

    3 Sep 2026 Outline
  • 26/1548/UTL Granted

    1 Lochfield Carlisle Road Annan DG12 6QX

    INSTALLATION OF 1NO. TELECOMMUNICATIONS POLE

    2 Sep 2026 Outline