Planning application
Land South Of Gretna 400KV Substation (Known As Gretna Green Battery Energy Storage System)
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
CONSULTATION FROM SCOTTISH MINISTERS REGARDING AN APPLICATION MADE UNDER SECTION 36 OF THE ELECTRICITY ACT 1989 FOR BATTERY ENERGY STORAGE SYSTEM WITH A STORAGE CAPACITY OF UP TO 456 MEGAWATTS
As published by the council, reference 24/1531/S36
Application record
- Reference
- 24/1531/S36
- Type
- Section 36 Consultation
- Status
- Decided
- Decision
- Granted As published: Raise No Objections
- Received
- 17 Jul 2024
- Validated
- 17 Jul 2024
- Decided
- 1 Nov 2024
- Ward
- Annandale East And Eskdale
- Decision by
- Planning Applications Committee
Timeline
Dates from the published record
-
17 Jul 2024
Received by Dumfries and Galloway
-
1 Nov 2024
Decision issued: Raise No Objections
-
15 Nov 2026
Added to PlanIndex
Documents
13 documents on file for this application
A planning file usually holds the application form, the consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWorking a patch? Trade sends you every new job in your area each morning. 14 days free.
What this grant of permission means
Dumfries and Galloway granted permission on 1 November 2024, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About outline applications
An outline application tests the principle of developing a site, holding back details such as appearance and landscaping as reserved matters for later approval. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
Land East Of Gretna Substation 3km To The North Of Gretna
PROPOSED GRID STABILITY FACILITY COMPRISING FORMATION OF AN ELECTRICAL TRANSMISSION INFRASTRUCTURE COMPOUND CONTAINING TRANSFORMERS, CABLES AND INFRASTRUCTURE, THE ERECTION OF MAIN PLANT ROOM BUILDING, FORMATION OF NEW ACCESS, ANCILLARY CAR PARKING, DRAINAGE, BOUNDARY TREATMENT AND LANDSCAPING AT VARIANCE WITH CONDITION 4 OF PLANNING PERMISSION 20/2071/FUL CONDITION RELATION TO AIL DELIVERIES TO ENABLE AIL DELIVERIES WITHOUT THE NEED FOR A TEST RUN AND TO PROVIDE SUFFICIENT TECHNICAL EVIDENCE TO BE SUBMITTED AND APPROVED IN WRITING INSTEAD
Granted 13 docs -
Land To South Of Gretna Substation Gretna
EXTENSION TO ELECTRICITY SUBSTATION INCLUDING INSTALLATION OF ONE 33KV 60 MVAR AIR CORE SHUNT REACTOR, ERECTION OF 3 METRE HIGH BOUNDARY FENCE AND ASSOCIATED LANDSCAPING WORKS
Granted Full applications Extension 27 docsSmall domestic
Other outline applications
In Dumfries and Galloway
-
26/2070/UTL Awaiting decision
Low Spango Bank Crawick Sanquhar DG4 6HB
REMOVAL AND REPLACEMENT OF TRANSMISSION CABINET, INSTALLATION OF 2 ANTENNAS, 1 GPS AND ASSOCIATED EQUIPMENT
-
26/2071/UTL Granted
Fingland Hill Dalry Castle Douglas DG7 3UG
REMOVAL AND REPLACEMENT OF TELECOMMUNICATIONS CABINET, INSTALLATION OF 3 ANTENNAS, 1 GPS AND ASSOCIATED EQUIPMENT
-
26/2060/UTL Granted
Near Glencarse A714 Wigtown DG8 9TF
INSTALLATION OF 1NO. TELECOMMUNICATIONS POLE
-
26/2058/UTL Granted
Side Of Anthony House Kippford Village Hall Quarry Road Kippford DG5 4PB
INSTALLATION OF 1NO. TELECOMMUNICATIONS POLE
-
26/2059/UTL Granted
Side Of 1 Meadow Park Kirkcowan Newton Stewart DG8 0HF
ERECTION OF A TELECOMMUNICATIONS POLE