Power Station At Artillery Way Discovery Park Sandwich Kent

Granted Dover CON/23/01446/A Conditions

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Discharge of condition 3 (external colour of units), condition 4 (pre-com fire management plan), condition 8 (pre-com CEMP) pursuant to application 23/01446 Installation of a battery energy storage system (BESS) and associated infrastructure

As published by the council, reference CON/23/01446/A

Application record

Reference
CON/23/01446/A
Type
Conditions
Status
Decided
Decision
Condition Approved
Received
25 Sep 2025
Validated
26 Sep 2025
Decided
11 Nov 2025
Ward
Sandwich
Parish
SANDWICH
Decision by
Delegated

Site history

Applications at this address on the Dover register

This site has had 3 applications since 2025: 3 approved, 0 refused.

  • CON/24/00844/B Granted

    Power Station At Artillery Way Discovery Park Sandwich Kent

    Discharge of condition 5 (ecological management plan), condition 7 (lighting strategy), condition 8 (biodiversity plan), condition 9 (Landscape and Ecological Management Plan) pursuant to application 24/00844 Change of use of land for the storage of logs (as biomass fuel)

    Decided 7 Apr 2026 Conditions
  • CON/24/00844/A Granted

    Power Station At Artillery Way Discovery Park Sandwich Kent

    Discharge of condition 4 (flood mitigation) pursuant to application 24/00844 Change of use of land for the storage of logs (as biomass fuel)

    Decided 20 Jan 2026 Conditions

Timeline

Dates from the published record

  1. 25 Sep 2025

    Received by Dover

  2. 26 Sep 2025

    Validated

    Checked as complete and ready for consideration.

  3. 11 Nov 2025

    Decision issued: Condition Approved

  4. 26 Jul 2026

    Added to PlanIndex

Who's behind it

Company information only, from the register and Companies House

Agent on file, registered in Warrington

3 applications on PlanIndex

Trade members see who it is, their full track record, and every application they have filed.

See who's behind it

Documents

Plans, drawings, consultee responses and the officer's report

13 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Trade members open them from here.

Open the documents

What this grant of permission means

Dover granted permission on 11 November 2025, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About condition discharge and variation applications

This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.

In Dover

  • CON/25/00248/C Withdrawn

    Longships Cauldham Lane Capel Le Ferne CT18 7HG

    Discharge of condition 16 (badger survey), condition 17 (Bat mitigation), condition 18 (Mitigation measures), condition 19 (CEMP), condition 20 (LEMP) pursuant to application 25/00248 Erection of 9 dwellings (custom build) with access, landscaping and associated works

    23 Dec 2025 Conditions
  • CON/25/00649/A Granted

    Richborough Energy Park (Part Of Former Richborough Power Station) Ramsgate Road Sandwich CT13 9NL

    Discharge of condition 7 (Lighting design strategy) pursuant to application 25/00649 - Variation of condition 2 (approved drawings) and 11 (SUDS) on planning permission 22/00705 as amended by 24/00258 (Installation of an electrical battery storage facility including the installation of UKPN connection area and equipment, ground raising, landscaping and associated works) to vary room sizes, the layout of access, increase of size of SUDS basin, removal of secondary security fencing and secondary water tanks, and to update drainage strategy report

    16 Apr 2026 Conditions
  • CON/24/00920/E Granted

    Land South Of Cauldham Lane Capel-Le-Ferne CT18 7HG

    Discharge of condition 25 (lighting strategy) pursuant to application 24/00920 - Variation of condition 4 (approved plans) of planning permission 23/00401 (Outline application for the erection of up to 16 dwellings (with all matters reserved except access)) to replace approved document 19064-H-03 P1 - Proposed Offsite Works, with 19064-H-04 P1 - Offsite Works

    21 Jul 2026 Conditions
  • CON/25/00649/B Granted

    Richborough Energy Park (Part Of Former Richborough Power Station) Ramsgate Road Sandwich CT13 9NL

    Discharge of condition 8 (Landscaping scheme) and 9 (Hard & soft landscaping) pursuant to application 25/00649 - Variation of condition 2 (approved drawings) and 11 (SUDS) on planning permission 22/00705 as amended by 24/00258 (Installation of an electrical battery storage facility including the installation of UKPN connection area and equipment, ground raising, landscaping and associated works) to vary room sizes, the layout of access, increase of size of SUDS basin, removal of secondary security fencing and secondary water tanks, and to update drainage strategy report

    16 Apr 2026 Conditions
  • CON/24/00293/I Granted

    Car Park Woolcomber Street Dover Kent CT16 1QF

    Discharge of condition 4 (materials) pursuant to application 24/00293 Erection of a drive thru restaurant, car parking, car charging bays, substation, landscaping and associated works, including Customer Order Displays (COD) and a height restrictor

    10 Nov 2025 Conditions