Planning application
Telecommunication Mast Hobart Crescent Dover Kent
Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.
Proposal
Notice under of the Electronic Communications Code (Conditions and Restrictions) Regulations 2003 (as amended) for the removal of 6 existing antennas to be replaced with 9 proposed antennas
As published by the council, reference 26/00808
Application record
- Reference
- 26/00808
- Status
- Awaiting decision
- Received
- 9 Sep 2026
- Validated
- 10 Sep 2026
- Ward
- Buckland
- Parish
- DOVER
Site history
Applications at this address on the Dover register
This site has had 2 applications since 2026: 1 approved, 0 refused.
-
26/00129 Granted
Telecommunication Mast Hobart Crescent Dover Kent
Regulation 5 (The Electronic Communications Code (Conditions and restrictions) (Amendment) Regulations 2017) notification for the installation of a a new 10kVA genny on new concrete base. Earth pit to be installed. Power duct to be installed from source to genny. AMF panel to be installed on existing support pole PSU cabinet to be retained. Proposed double wide access gate to be installed and ancillary upgrades thereto
Timeline
Dates from the published record
-
9 Sep 2026
Received by Dover
-
9 Sep 2026
Added to PlanIndex
-
10 Sep 2026
Validated
Checked as complete and ready for consideration.
-
Decision
Awaiting decision
Decision expected by 5 November 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Dover took a median of 55 days over the applications it decided in the last year.
Documents
Plans, drawings, consultee responses and the officer's report
3 documents on file for this application
- SITE PLAN
- PROPOSED ELEVATION
- COVER LETTER
Trade members open them from here.
Open the documentsWhat happens while it is decided
This application is with Dover for determination, against a statutory target of eight weeks. Over the last year Dover's median decision took 55 days. More in our guide to how long planning decisions take.
About this record
The published feed does not state which type of application this is; the register entry on Dover's portal will say. Our guide explains the common types.