Skip to content
PlanIndex Get alerts
Menu

Planning application

Kerley Paddock Kerley Chacewater Truro Cornwall TR4 8JY

Granted Cornwall PA25/07225 Overhead Electricity Lines

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

To add a third 11kv overhead wire to an existing line and erect one wooden pole to create a H pole to support a larger pole mounted transformer.

As published by the council, reference PA25/07225

Application record

Reference
PA25/07225
Type
Overhead Electricity Lines
Status
Awaiting decision
Decision
Granted As published: No Objection
Received
23 Sep 2025
Validated
23 Sep 2025
Decided
29 Oct 2025
Ward
Threemilestone And Chacewater
Parish
Chacewater
Decision by
Self Sign Off (Area Team)
Postcode
TR4 8JY

Timeline

Dates from the published record

  1. 23 Sep 2025

    Received by Cornwall

  2. 29 Oct 2025

    Decision issued: No Objection

  3. 21 Jul 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

4 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Watch members (£5 a month) open the document list from here.

Open the documents

What this grant of permission means

Cornwall granted permission on 29 October 2025, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About less common application types

This application sits outside the common categories, and the council record linked on this page sets out the specific procedure that applies. More in our guide to planning application types.

Nearby applications

Within 0.3 miles

  • 18 Trevithick Road Chacewater Truro Cornwall TR4 8JT

    PA21/04375 Submitted 21 Apr 2021 350 yards away

    Energy efficiency improvements to property including external wall and loft insulation, replacement doors and windows and installation of PV array and removal of chimney

    Granted Full applications Windows or glazing 21 docs
  • Street Record Cross Roads Chacewater Cornwall

    PA25/09261 Submitted 9 Dec 2025 450 yards away

    Undertake work that is considered to be exempted from the Electricity Act 1989 by falling within the Overhead Lines (Exemption) (England and Wales) Regulations 2009

    Decided 4 docs
  • 25 Boscawen Road Chacewater Truro Cornwall TR4 8JS

    PA26/02640 Submitted 20 Apr 2026 0.3 miles away

    Works to Tree(s) within a Conservation Area (TCA) Ash. Prune away from both Nos. 25 and 26 by 3m to suitable growth points and remove major deadwood.

    Granted Trees 4 docs
  • 12 Kerley Vale Chacewater Truro Cornwall TR4 8JN

    PA25/09585 Submitted 7 Jan 2026 0.3 miles away

    Proposed Single Storey Extension

    Granted Full applications Extension 11 docs
    Small domestic
  • Land South West Of 16 Chacewater Hill Chacewater Hill Chacewater TR4 8QB

    PA25/06713 Submitted 22 Sep 2025 0.3 miles away

    Technical Details Consent for the construction of 2 dwellings, following Permission in Principle approval PA23/08469 dated 19.12.2023

    Refused Full applications 31 docs
    Several homes
  • 13 Roseland Crescent Chacewater TR4 8JW

    PA22/01430 Submitted 21 Feb 2022 0.3 miles away

    Formation of annexe accommodation from existing garage and existing bedroom above for use in connection with 13 Roseland Crescent.

    Granted Full applications 8 docs

In Cornwall

  • PA26/06662 Awaiting decision

    Street Record St Ervan Wadebridge Cornwall

    Upgrade and relocate existing 100kVa Transformer with a 315kVa unit. Install new 11.5m and 10.5m Stout poles to replace existing 11.5m Medium pole to house new transformer and associated equipment. A new back stay will be installed to support the overhead lines. Replace and relocate an existing 10.5m Medium pole with a 10m Medium pole. Pole to be relocated to edge of land title boundary due to access restrictions. Upgrade 192m of existing 25 Hard Drawn Copper overhead high voltage line to 3 phase by installing a third conductor along highlighted route. This reinforcement work is being carried out to improve network carrying capacity and reliability for customers in the Penrose area

    Received 23 Sep, published by the council 30 Sep 2026 Other
  • PA26/06624 Awaiting decision

    Higher Beeny Beeny Boscastle Cornwall PL35 0HL

    Overhead Electricity Lines to install 3rd wire for approximately 130 metres from pole 43LWA4 to 43LWA4B. Replace poles 43LWA4A and 43LWA4B on a like for like basis. Upgrade pole mounted transformer to a new 100kVA unit and replace all associated secondary wiring at pole 43LWA4B.

    Received 23 Sep, published by the council 30 Sep 2026 Other
  • PA26/06625 Awaiting decision

    Gwendreath Ruan Minor Helston Cornwall TR12 7LZ

    Overhead Electricity Lines to upgrade an existing two wire 11kV line to a three wire 11kV overhead line along with additional support poles / equipment to facilitate an upgrade to three phase in the Gwendreath, Ruan Minor area. In addition to the overhead equipment we will also be installing a section of underground cable.

    Received 23 Sep, published by the council 30 Sep 2026 Other
  • PA26/06587 Awaiting decision

    Plusha Launceston Cornwall PL15 7QT

    National Grid proposed to install a 3rd wire on existing poles between 45LCHB1-5. The overall distance of the 3rd wire works is 340 metres. Pole 45LCHB3 is planned to be replaced on a like for like basis and a new pole mounted transformer will be added. No other poles are planned to be replaced, however, if nearer the time of the works the poles are found to require replacement the additional poles will be replaced as part of this scheme as well. All pole replacement work would be completed on a like for like basis

    Received 22 Sep, published by the council 30 Sep 2026 Other
  • PA26/05569 Granted

    Lower Tolcarne Farm St Allen Truro Cornwall TR4 9QX

    Overhead Electricity Lines to add a 3rd wire to an existing 11kv overhead line

    Received 10 Aug, published by the council 24 Aug 2026 Other