Planning application
Land At St Austell Street St Austell Street Summercourt Cornwall
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Western Power Distribution have a statutory duty to provide connections to the electricity network and in order to do this it will be necessary to re-inforce the existing network by installing a new pole mounted transformer. It is intended that two poles in an "H" Pole configuration will be stood and a transformer erected. It will be connected to both the existing HV and LV network with underground cables withon private land. Attached plan reference S3847017v2 .
As published by the council, reference PA22/01290
Application record
- Reference
- PA22/01290
- Type
- Overhead Electricity Lines
- Status
- Decided
- Decision
- No objections (OHL/OHE/HG apps)
- Received
- 8 Feb 2022
- Validated
- 8 Feb 2022
- Decided
- 2 Mar 2022
- Ward
- St Dennis And St Enoder
- Parish
- St. Enoder
- Decision by
- Peer Sign Off
- Postcode
- TR8 5DR
Timeline
Dates from the published record
-
8 Feb 2022
Received by Cornwall
-
2 Mar 2022
Decision issued: No objections (OHL/OHE/HG apps)
-
16 Aug 2026
Added to PlanIndex
Documents
Plans, drawings, consultee responses and the officer's report
6 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Trade members open them from here.
Open the documentsWhat this grant of permission means
Cornwall granted permission on 2 March 2022, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About less common application types
This application sits outside the common categories, and the council record linked on this page sets out the specific procedure that applies. More in our guide to planning application types.
Nearby applications
Within 500 metres
-
Western House St Austell Street Summercourt TR8 5DR
Relocation of existing Cabins and additional cabins
Granted Full applications 6 docs -
Andy Loos Fair Park School Road Newquay Summercourt TR8 5EA
95% historically approved · decision due ~16 Sep
Proposed change of use and extension to the existing toilet block to an office
Awaiting decision Full applications Extension 10 docs -
Land South West Of Ivybank Farm School Road Summercourt Newquay TR8 5EA
Application for Permission in Principle for the proposed erection of up to 4 dwellings (minimum of 4, maximum of 4)
Granted Outline 7 docsSeveral homes
Other less common application types
In Cornwall
-
PA26/04973 Granted
Truthan Manor Truthan St Erme Truro Cornwall TR4 9BB
Overhead Electricity Lines application to add a 3rd wire to an existing 11kv overhead line
-
PA26/05516 Decided
Little Trethellan Trethellan Lanner Redruth Cornwall TR16 6BP
Notification of change of use under Class R from agricultural building to a flexible commercial use consisting of storage or distribution (Class B8) and offices (Class E)
-
PA26/04833 Granted
Shelton Farm Delabole Cornwall PL33 9DA
-Erect new terminal pole at 43LC4 add a back stay to support OHL and install new underground cable pole termination -Install new HV underground cable from 43LC4 to new H-Pole at 43LC5. -Install new H-pole at 43LC5 new position as per plan and installed new HV and LV earth wires as required. Reconnect existing low voltage network via new underground cables as shown on attached plan -Install new HV cable from new poles at 43LC5 to 43LC9 with associated earth wires as necessary. -Install new terminal pole at 43LC9 and backstay to support OHL and install new underground cable pole termination -Dismantle all redundant equipment between 43LC4 and 43LC9 as shown highlighted blue on plan. Existing underground cable to be disconnected from network, made safe and abandoned in situ
-
PA26/05569 Awaiting decision
Lower Tolcarne Farm St Allen Truro Cornwall TR4 9QX
Overhead Electricity Lines to add a 3rd wire to an existing 11kv overhead line
-
PA26/02843 Granted
Dubbers Restoration Storage And Mixing Area Land East Of Karslake China Clay Works Currian Vale Nanpean Cornwall PL26 7XS
Use of land for the receipt and mixing of a number of waste productions and 'compost like outputs' (previously composted material) to form a blended material which is added as a soil substitute used in land restoration purposes in the China Clay area at Dubbers Tip Complex