Planning application
Castle An Dinas Link Area St Columb
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Overhead Electricity Lines application to install a third wire on existing infrastructure
As published by the council, reference PA21/01400
Application record
- Reference
- PA21/01400
- Type
- Overhead Electricity Lines
- Status
- Decided
- Decision
- Granted As published: No objections (OHL/OHE/HG apps)
- Received
- 10 Feb 2021
- Validated
- 10 Feb 2021
- Decided
- 29 Mar 2021
- Ward
- St Columb Major
- Parish
- St. Columb Major
- Decision by
- Peer Sign Off
Timeline
Dates from the published record
-
10 Feb 2021
Received by Cornwall
-
29 Mar 2021
Decision issued: No objections (OHL/OHE/HG apps)
-
27 Sep 2026
Added to PlanIndex
Documents
Plans, drawings, consultee responses and the officer's report
1 document on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat this grant of permission means
Cornwall granted permission on 29 March 2021, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About less common application types
This application sits outside the common categories, and the council record linked on this page sets out the specific procedure that applies. More in our guide to planning application types.
Other less common application types
In Cornwall
-
PA26/06662 Awaiting decision
Street Record St Ervan Wadebridge Cornwall
Upgrade and relocate existing 100kVa Transformer with a 315kVa unit. Install new 11.5m and 10.5m Stout poles to replace existing 11.5m Medium pole to house new transformer and associated equipment. A new back stay will be installed to support the overhead lines. Replace and relocate an existing 10.5m Medium pole with a 10m Medium pole. Pole to be relocated to edge of land title boundary due to access restrictions. Upgrade 192m of existing 25 Hard Drawn Copper overhead high voltage line to 3 phase by installing a third conductor along highlighted route. This reinforcement work is being carried out to improve network carrying capacity and reliability for customers in the Penrose area
-
PA26/06624 Awaiting decision
Higher Beeny Beeny Boscastle Cornwall PL35 0HL
Overhead Electricity Lines to install 3rd wire for approximately 130 metres from pole 43LWA4 to 43LWA4B. Replace poles 43LWA4A and 43LWA4B on a like for like basis. Upgrade pole mounted transformer to a new 100kVA unit and replace all associated secondary wiring at pole 43LWA4B.
-
PA26/06625 Awaiting decision
Gwendreath Ruan Minor Helston Cornwall TR12 7LZ
Overhead Electricity Lines to upgrade an existing two wire 11kV line to a three wire 11kV overhead line along with additional support poles / equipment to facilitate an upgrade to three phase in the Gwendreath, Ruan Minor area. In addition to the overhead equipment we will also be installing a section of underground cable.
-
PA26/06587 Awaiting decision
Plusha Launceston Cornwall PL15 7QT
National Grid proposed to install a 3rd wire on existing poles between 45LCHB1-5. The overall distance of the 3rd wire works is 340 metres. Pole 45LCHB3 is planned to be replaced on a like for like basis and a new pole mounted transformer will be added. No other poles are planned to be replaced, however, if nearer the time of the works the poles are found to require replacement the additional poles will be replaced as part of this scheme as well. All pole replacement work would be completed on a like for like basis
-
PA26/05569 Granted
Lower Tolcarne Farm St Allen Truro Cornwall TR4 9QX
Overhead Electricity Lines to add a 3rd wire to an existing 11kv overhead line