Development Site 2 Aldermanbury Square London

Granted City of London 25/01766/MDC

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Submission of confirmation that either: all water network upgrades required to accommodate the additional flows to serve the development have been completed or a development and infrastructure phasing plan has been agreed with Thames Water to allow development to be occupied (with all occupation taking place in accordance with the agreed housing and infrastructure phasing plan) pursuant to condition 50 of planning permission 21/00116/FULMAJ dated 29/09/2021.

As published by the council, reference 25/01766/MDC

Application record

Reference
25/01766/MDC
Status
Decided
Decision
Granted As published: Approved
Received
15 Dec 2025
Validated
15 Dec 2025
Decided
30 Oct 2026
Ward
Bassishaw
Decision by
Delegated

Site history

Applications at this address on the City of London register

This site has had 7 applications since 2025: 6 approved, 0 refused.

  • 26/01450/MDC Awaiting decision

    Development Site 2 Aldermanbury Square London

    Submission of details of Whole Life Cycle Carbon Assessment and GLA Whole Life Cycle Carbon Assessment Template pursuant to condition 32 of Planning Permission 21/00116/FULMAJ dated 29.09.2021.

    Submitted 13 Oct 2026
  • 26/00972/PODC Granted

    Development Site 2 Aldermanbury Square London

    Submission of the Carbon Offset Assessment pursuant to Schedule 3 Paragraph 9 of the Section 106 Agreement dated 29 September 2021 (Planning Application Reference 21/00116/FULMAJ).

    Decided 14 Aug 2026
  • 26/00481/MDC Granted

    Development Site 2 Aldermanbury Square London

    Submission of a post-completion Circular Economy report pursuant to condition 36 of planning permission 21/00116/FULMAJ dated 29.09.2021.

    Decided 15 Oct 2026
  • 26/00226/PODC Granted

    Development Site 2 Aldermanbury Square London

    Submission of a Revised Affordable Workspace Plan pursuant to Schedule 3 Paragraph 16.1 of the Section 106 Agreement dated 29 September 2021 (Planning Application Reference 21/00116/FULMAJ).

    Decided 6 Mar 2026
  • 25/01767/MDC Granted

    Development Site 2 Aldermanbury Square London

    Submission of details of plant noise, installation and maintenance pursuant to condition 30 of planning permission 21/00116/FULMAJ dated 29/09/2021.

    Decided 15 Jan 2026 Conditions
  • 25/01711/NMA Granted

    Development Site 2 Aldermanbury Square London

    Application under section 96a of the Town and Country Planning Act 1990 (as amended) to planning permission ref. 21/00116/FULMAJ dated 29.09.2021 to amend condition 55 (approved plans) to allow for the following revisions to the development: (i) installation of sliding doors and alterations to spandrel panels at level 12; (ii) reconfiguration of the ground floor toilet arrangement; (iii) alteration of the ground floor façade to enable access to a UKPN grille; amendment of the wording of condition 41 (delivery vehicles) to enable flexibility on delivery and collection vehicle access arrangements and insertion of a new condition relating to the servicing of the retail unit.

    Decided 26 Feb 2026 Amendments

Timeline

Dates from the published record

  1. 15 Dec 2025

    Received by City of London

  2. 24 Jul 2026

    Added to PlanIndex

  3. 30 Oct 2026

    Decision issued: Approved

  4. 30 Oct 2026

    Status changed to Decided

    Previously Under Consideration.

Cases linked to this one on the register

  • Application: 21/00116/FULMAJ (Decided)

Documents

Plans, drawings, consultee responses and the officer's report

19 documents on file for this application

  • COMMENTS - THAMES WATER Consultee Comment · 27 Jul 2026
  • THAMES WATER POINT OF ENTRY PLAN Drawing · 13 Jul 2026
  • THAMES WATER CONFIRMATION OF INCOMING WATER MAINS COMPLETION Correspondence In · 13 Jul 2026
  • NEW WATER CONNECTION QUOTE Other · 13 Jul 2026
  • CLEAN WATER CAPACITY REPORT Accompanying report · 13 Jul 2026
  • CONFIRMATION OF INCOMING WATER MAINS COMPLETION Correspondence Out · 13 Jul 2026
  • TECHNICAL NOTE Correspondence In · 13 Jul 2026
  • COMMENTS - THAMES WATER Consultee Comment · 11 Feb 2026
  • COMMENTS - THAMES WATER Consultee Comment · 11 Feb 2026
  • CLEAN WATER CAPACITY REPORT Accompanying report · 03 Feb 2026
  • SITE PLAN Drawing · 02 Feb 2026
  • NEW WATER CONNECTION QUOTE Accompanying report · 02 Feb 2026
  • GUIDE WATER CONNECTION Accompanying report · 02 Feb 2026
  • APPLICATIONFORMREDACTED Application Form · 15 Dec 2025
  • QUOTATION DS6090020 Drawing · 15 Dec 2025
  • 2AS THAMES WATER DESIGN POE DS6090020 Other · 15 Dec 2025
  • 2AS THAMES WATER CONFIRMATION OF INCOMING WATER MAINS COMPLETION 290625 Other · 15 Dec 2025
  • 2AS THAMES WATER CONFIRMATION OF INCOMING WATER MAINS COMPLETION - 150725 Other · 15 Dec 2025
  • CONDITION 50 COVER LETTER Cover Letter · 15 Dec 2025

Watch members (£5 a month) open the document list from here.

Open the documents

What this grant of permission means

City of London granted permission on 30 October 2026, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About this record

The published feed does not state which type of application this is; the register entry on City of London's portal will say. Our guide explains the common types.