Granted City of London 24/00974/CLOPD Certificate of Lawfulness (Proposed)

Works: Demolition

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Certificate of Lawful Development (proposed) for demolition of a pre-cast concrete plant room structure at roof level of the existing 123 Houndsditch building, as consented by the approved development works under planning permission dated 01.02.2022 (ref: 21/00622/FULEIA).

As published by the council, reference 24/00974/CLOPD

Application record

Reference
24/00974/CLOPD
Type
Certificate of Lawfulness (Proposed)
Status
Decided
Decision
Granted As published: Grant Certificate of Lawful Development
Received
9 Sep 2024
Validated
9 Sep 2024
Decided
31 Oct 2024
Ward
Aldgate
Decision by
Delegated Decision
Postcode
EC3A 7BU

Site history

Applications at this address on the City of London register

This site has had 2 applications since 2024: 2 approved, 0 refused.

  • 24/01314/CLEUD Granted

    Dovetail Building 115 - 123 Houndsditch London EC3A 7BU

    Certificate of Lawful Development (existing) for confirmation that works carried out on site constitute a material operation for the purposes of s.56(4) of the Town and Country Planning Act 1990 (as amended), pursuant to condition 1 (time limit) of planning permission dated 01.02.2022 (ref: 21/00622/FULEIA).

    Decided 21 Feb 2025 Lawful development

Timeline

Dates from the published record

  1. 9 Sep 2024

    Received by City of London

  2. 31 Oct 2024

    Decision issued: Grant Certificate of Lawful Development

  3. 25 Jul 2026

    Added to PlanIndex

Who's behind it

Company information only, from the register and Companies House

DP9 Ltd Agent

Active · incorporated 2004

2,658 applications on PlanIndex · across 36 councils · 98% granted

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Documents

Plans, drawings, consultee responses and the officer's report

11 documents on file for this application

  • PHASE 1 DEMOLITION PLAN ROOF LEVE Drawing · 09 Sep 2024
  • EXISTING ELEVATION CUTLER STREET NORTH Drawing · 09 Sep 2024
  • PHASE 1 PROPOSED PLAN ROOF LEVEL Drawing · 09 Sep 2024
  • APPLICATION FORM REDACTED Application Form · 09 Sep 2024
  • STATEMENT IN SUPPORT OF CLOPUD Other · 09 Sep 2024
  • METHOD STATEMENT Other · 09 Sep 2024
  • LOCATION PLAN Site Plan · 09 Sep 2024
  • IMAGE OF ROOF PLANT Photograph · 09 Sep 2024
  • COVER LETTER Cover Letter · 09 Sep 2024
  • PHASE 1 PROPOSED ELEVATION CUTLER STREET NORTH Drawing · 09 Sep 2024
  • PHASE 1 DEMOLITION ELEVATION CUTLER STREET NORTH Drawing · 09 Sep 2024

Watch members (£5 a month) open the document list from here.

Open the documents

What this grant of permission means

City of London granted permission on 31 October 2024, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About lawful development applications

A lawful development certificate is a legal determination that existing or proposed works do not need planning permission; the merits of the scheme are not considered. More in our guide to planning application types.

Nearby applications

Within 0.3 miles

  • 115 - 123 Houndsditch London EC3A 7BU

    26/01146/NMA Submitted 10 Aug 2026 50 yards away

    100% historically approved · decision due ~5 Oct

    Non-material amendment under Section 96A of the Town and Country Planning Act 1990 (as amended) for amendments to Condition 78 (Floorspace) and Condition 79 (Approved Plans) to accommodate design changes to the pedestrian and cycle entrances and associated envelope and layout changes, of planning permission dated 19.08.2025 (ref: 25/00276/FULEIA).

    Awaiting decision Amendments 19 docs
  • Cutlers Court 115 Houndsditch London

    23/00149/MDC Submitted 9 Feb 2023 50 yards away

    Submission of Pre-Demolition Audit pursuant to condition 2 of planning permission 21/00622/FULEIA dated 1st February 2022.

    Granted Conditions Demolition 5 docs
  • 115 - 123 Houndsditch London EC3A 7BU

    23/01056/MDC Submitted 25 Sep 2023 50 yards away

    Submission of a Whole Life Cycle Carbon assessment pursuant to condition 9 of planning permission 21/00622/FULEIA dated 01/02/2022.

    Granted Conditions 7 docs
  • 115 - 123 Houndsditch London EC3A 7BU

    26/01216/MDC Submitted 26 Aug 2026 50 yards away

    100% historically approved · decision due ~21 Oct

    Submission of Pre-Commencement Whole-Life Cycle Carbon Assessment (WLCA) Note pursuant to discharge of condition 9 of planning permission 25/00276/FULEIA dated 19.08.2025.

    Awaiting decision Conditions 3 docs
  • 115 - 123 Houndsditch London EC3A 7BU

    22/01129/PODC Submitted 22 Nov 2022 50 yards away

    Submission of the Utility Connection Requirements and Draft Programme pursuant to Schedule 3 Paragraph 13.1 of the Section 106 Agreement dated 01 February 2022 (Planning Application Reference 21/00622/FULEIA).

    Granted 8 docs
  • 115 - 123 Houndsditch London EC3A 7BU

    25/01142/MDC Submitted 20 Aug 2025 50 yards away

    Submission of Climate Change Resilience Sustainability Statement (CCRSS) pursuant to Condition 13 of planning permission dated 19.08.2025 (ref: 25/00276/FULEIA).

    Granted Conditions 4 docs

In City of London

  • 26/01295/CLEUD Granted

    Boundary House 7 - 17 Jewry Street London EC3N 2EX

    Application for Lawful Development Certificate (Existing) seeking confirmation that demolition works undertaken constitute implementation of planning permission 21/00826/FULMAJ dated 21 December 2023.

    Received 17 Sep, published by the council 24 Sep 2026 Lawful development
  • 26/01557/LDC Awaiting decision

    Central Criminal Court Old Bailey London EC4M 7EH

    Submission of details of the sanitaryware and samples of exposed pipework and associated fixings pursuant to condition 2 of planning permission 26/00935/LBC dated 24.08.2026.

    Received 30 Oct, published by the council 6 Nov 2026 Lawful development
  • 26/01530/LDC Awaiting decision

    Library Barbican Arts And Conference Centre Silk Street London EC2Y 8DS

    Submission of Method Statement pursuant to condition 5 of planning permission 25/01774/LBC dated 18.08.2026.

    Received 27 Oct, published by the council 6 Nov 2026 Lawful development
  • 26/01527/LDC Awaiting decision

    Library Barbican Arts And Conference Centre Silk Street London EC2Y 8DS

    Submission of Method Statement for the Protection of Historic Fabric During Works pursuant to condition 4 of planning permission 25/01774/LBC dated 18.08.2026.

    Received 27 Oct, published by the council 6 Nov 2026 Lawful development
  • 26/01528/LDC Awaiting decision

    Library Barbican Arts And Conference Centre Silk Street London EC2Y 8DS

    Submission of Method Statement pursuant to condition 7 of planning permission 25/01774/LBC dated 18.08.2026.

    Received 27 Oct, published by the council 6 Nov 2026 Lawful development