Skip to content
PlanIndex Get alerts
Menu

Planning application

Land At Badgeworth Road Cheltenham Gloucestershire

Status unknown Cheltenham 26/00184/FUL Full Planning Permission

Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.

Proposal

100% affordable housing scheme of 97 dwellings with associated access, landscaping and associated works.

As published by the council, reference 26/00184/FUL

Application record

Reference
26/00184/FUL
Type
Full Planning Permission
Received
4 Feb 2026
Validated
5 Feb 2026
Ward
Benhall/The Reddings/Fiddlers Green
Decision by
Delegated Decision

Timeline

Dates from the published record

  1. 4 Feb 2026

    Received by Cheltenham

  2. 5 Feb 2026

    Validated

    Checked as complete and ready for consideration.

  3. 27 Jul 2026

    Added to PlanIndex

  4. Decision

    Awaiting decision

    Decision expected by 2 April 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    Cheltenham took a median of 44 days over the applications it decided in the last year.

Cases linked to this one on the register

  • Buildingcontrol: C26/00756/IN (Received)

Who's behind it

Company information only, from the register and Companies House

Evans Jones Ltd Agent, registered in Cheltenham

Active · incorporated 2006 · Cheltenham

149 applications on PlanIndex · across 13 councils · 93% granted

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Documents

Plans, drawings, consultee responses and the officer's report

211 documents on file for this application

  • Sunny brae badgeworth rd bng issues Public Comment · 08 Sep 2026
  • Sunny brae badgeworth rd habitat degredation Public Comment · 08 Sep 2026
  • Sunny brae badgeworth rdsummary of why the field contains omhpdl Public Comment · 08 Sep 2026
  • Sunny brae badgeworth rd ground survey evidance that the field meets omhpdl crit Public Comment · 08 Sep 2026
  • Ecological technical note Other · 04 Sep 2026
  • Gcc minerals & waste response Consultee Comment · 25 Aug 2026
  • Sunny brae, badgeworth road Public Comment · 19 Aug 2026
  • Sunny brae, badgeworth road Public Comment · 19 Aug 2026
  • Designing out crime officer response Consultee Comment · 18 Aug 2026
  • Housing enabling comments Consultee Comment · 13 Aug 2026
  • Copy of natural england response Consultee Comment · 11 Aug 2026
  • Llfa response Consultee Comment · 11 Aug 2026
  • Revised flood risk assessment part 1 Report · 10 Aug 2026
  • Revised flood risk assessment part 2 Report · 10 Aug 2026
  • Revised flood risk assessment part 3 Report · 10 Aug 2026
  • Gcc education & libraries response Consultee Comment · 10 Aug 2026
  • Gcc education & libraries response Consultee Comment · 10 Aug 2026
  • Gcc libraries assessment Consultee Comment · 10 Aug 2026
  • Sunny brae, badgeworth road Public Comment · 05 Aug 2026
  • Sunny brae, badgeworth road Public Comment · 05 Aug 2026
  • Sunny brae badgeworth road cheltenham gl51 6sj Public Comment · 04 Aug 2026
  • Gloucestershire airport Consultee Comment · 03 Aug 2026
  • Gloucestershire wildlife trust Consultee Comment · 03 Aug 2026
  • Sunny brae, badgeworth road gl51 6sj Public Comment · 30 Jul 2026
  • 1 Site Notice · 28 Jul 2026
  • 2 Site Notice · 28 Jul 2026
  • Revised 1b ma/b floor plans & elevation Revised Drawing · 24 Jul 2026
  • Revised 1b ma/b floor plans & elevations Revised Drawing · 24 Jul 2026
  • Revised walton floor plans & elevations Revised Drawing · 24 Jul 2026
  • Revised walton floor plans & elevations Revised Drawing · 24 Jul 2026
  • Revised taunton floor plans & elevations Revised Drawing · 24 Jul 2026
  • Revised taunton floor plans and elevations Revised Drawing · 24 Jul 2026
  • Revised taunton floor plans & elevations Revised Drawing · 24 Jul 2026
  • Revised taunton floor plans & elevations Revised Drawing · 24 Jul 2026
  • Revised oakham floor plans and elevations Revised Drawing · 24 Jul 2026
  • Revised oakham floor plans and elevations Revised Drawing · 24 Jul 2026
  • Revised oakham floor plans and elevations Revised Drawing · 24 Jul 2026
  • Revised maidstone floor and elevations Revised Drawing · 24 Jul 2026
  • Revised maidstone floor plans and elevations Revised Drawing · 24 Jul 2026
  • Revised maidstone floor plans and elevations Revised Drawing · 24 Jul 2026
  • Revised maidstone floor plans and elevations Revised Drawing · 24 Jul 2026
  • Revised maidstone floor plans and elevations Revised Drawing · 24 Jul 2026
  • Revised maidstone floor plans and elevations Revised Drawing · 24 Jul 2026
  • Revised maidstone floor plans & elevations Revised Drawing · 24 Jul 2026
  • Revised maidstone floor plans & elevations Revised Drawing · 24 Jul 2026
  • Revised hertford floor plans and elevations Revised Drawing · 24 Jul 2026
  • Revised hertford floor plans and elevations Revised Drawing · 24 Jul 2026
  • Revised hertford floor plans and elevations Revised Drawing · 24 Jul 2026
  • Revised hertford floor plans and elevations Revised Drawing · 24 Jul 2026
  • Revised hampton v2 floor plans and elevations Revised Drawing · 24 Jul 2026
  • Revised hampton v2 floor plans and elevations Revised Drawing · 24 Jul 2026
  • Revised hampton v2 floor plans and elevations Revised Drawing · 24 Jul 2026
  • Revised bedford floor plans and elevations Revised Drawing · 24 Jul 2026
  • Revised bedford floor plans and elevations Revised Drawing · 24 Jul 2026
  • Revised bedford floor plans and elevations Revised Drawing · 24 Jul 2026
  • Response from national highways Consultee Comment · 24 Jul 2026
  • Revised 1bma/b & bedford floor plans & elevations Revised Drawing · 23 Jul 2026
  • Revised 1bma&b & hertford floor plans and elevations Revised Drawing · 23 Jul 2026
  • Revised 5b8p floor plans & elevations Revised Drawing · 23 Jul 2026
  • Revised substation floor plans and elevations Revised Drawing · 23 Jul 2026
  • Revised site location plan OS Extract · 23 Jul 2026
  • Revised planning layout rev a Revised Drawing · 23 Jul 2026
  • Revised land use plan rev a Revised Drawing · 23 Jul 2026
  • Revised housing mix plan rev a Revised Drawing · 23 Jul 2026
  • Revised affordable housing plan rev a Revised Drawing · 23 Jul 2026
  • Revised building heights plan rev a Revised Drawing · 23 Jul 2026
  • Revised parking strategy plan rev a Revised Drawing · 23 Jul 2026
  • Revised bin & cycle storage plan rev a Revised Drawing · 23 Jul 2026
  • Revised external finishes plan rev a. Revised Drawing · 23 Jul 2026
  • Revised external enclosures plan rev a Revised Drawing · 23 Jul 2026
  • Revised house type plan rev a Revised Drawing · 23 Jul 2026
  • Revised ev charging plan rev a. Revised Drawing · 23 Jul 2026
  • Revised street scene Revised Drawing · 23 Jul 2026
  • Revised street scene Revised Drawing · 23 Jul 2026
  • Revised street scene Revised Drawing · 23 Jul 2026
  • Revised summary of amendments document_high res Report · 23 Jul 2026
  • Revised summary of amendments document_low res Report · 23 Jul 2026
  • Revised arboricultural impact assessment Report · 23 Jul 2026
  • Revised biodiversity net gain statement - v3 - 20.07.26 Report · 23 Jul 2026
  • Revised ecological impact assessment - v3 - 20.07.26 Report · 23 Jul 2026
  • Revised statutory biodiveristy metric - v3 - 20.07.26 Report · 23 Jul 2026
  • Revised planning statement revised - badgeworth road affordable housing - 21-07- Report · 23 Jul 2026
  • Revised phase 1 desk study and phase 2 ground investigation report update part 1 Report · 23 Jul 2026
  • Revised phase 1 desk study and phase 2 ground investigation report update part 2 Report · 23 Jul 2026
  • Revised phase 1 desk study and phase 2 ground investigation report update part 3 Report · 23 Jul 2026
  • Revised phase 1 desk study and phase 2 ground investigation report update part 4 Report · 23 Jul 2026
  • Revised phase 1 desk study and phase 2 ground investigation report update part 5 Report · 23 Jul 2026
  • Revised phase 1 desk study and phase 2 ground investigation report update part 6 Report · 23 Jul 2026
  • Revised phase 1 desk study and phase 2 ground investigation report update part 7 Report · 23 Jul 2026
  • Revised phase 1 desk study and phase 2 ground investigation report update part 8 Report · 23 Jul 2026
  • Revised phase 1 desk study and phase 2 ground investigation report update part 9 Report · 23 Jul 2026
  • Revised phase 1 desk study and phase 2 ground investigation report update part 1 Report · 23 Jul 2026
  • Revised phase 1 desk study and phase 2 ground investigation report update part 1 Report · 23 Jul 2026
  • Revised phase 1 desk study and phase 2 ground investigation report update part 1 Report · 23 Jul 2026
  • Revised historic environment assessment Report · 23 Jul 2026
  • Revised sustainability statement rev c Report · 23 Jul 2026
  • Revised proposed level strategy Revised Drawing · 23 Jul 2026
  • Revised flood risk assessment Report · 23 Jul 2026
  • Revised site sections Revised Drawing · 23 Jul 2026
  • Revised noise impact assessment Report · 23 Jul 2026
  • Revised northern site access arrangement Revised Drawing · 23 Jul 2026
  • Revised transport assessment Report · 23 Jul 2026
  • Revised framework travel plan Report · 23 Jul 2026
  • Revised site contribution to green belt purposes Report · 23 Jul 2026
  • Revised hard landscape Revised Drawing · 23 Jul 2026
  • Revised hard landscape Revised Drawing · 23 Jul 2026
  • Revised hard landscape Revised Drawing · 23 Jul 2026
  • Revised soft landscape Revised Drawing · 23 Jul 2026
  • Revised soft landscape Revised Drawing · 23 Jul 2026
  • Revised soft landscape Revised Drawing · 23 Jul 2026
  • Revised tree pit details Revised Drawing · 23 Jul 2026
  • Revised illustrative landscape masterplan Revised Drawing · 23 Jul 2026
  • Revised landscape and visual impact assessment including open space assessment Report · 23 Jul 2026
  • Revised sustainable_construction_checklist - 200726 Report · 23 Jul 2026
  • Revised existing site plan topo Revised Drawing · 23 Jul 2026
  • Sunny brae, badgeworth road Public Comment · 30 Mar 2026
  • Updated revised gcc highways response Consultee Comment · 19 Mar 2026
  • Gcc highways response Consultee Comment · 19 Mar 2026
  • Gloucestershire airport response Consultee Comment · 17 Mar 2026
  • Gcc education & libraries response Consultee Comment · 16 Mar 2026
  • Gcc education & libraries response Consultee Comment · 16 Mar 2026
  • Urban design officer response Consultee Comment · 13 Mar 2026
  • Landscape architect response Consultee Comment · 12 Mar 2026
  • Civic society Consultee Comment · 06 Mar 2026
  • Parks & landscape response Consultee Comment · 04 Mar 2026
  • Gcc minerals & waste response Consultee Comment · 26 Feb 2026
  • National highways response Consultee Comment · 26 Feb 2026
  • Sunny brae, badgeworth road Public Comment · 25 Feb 2026
  • Sunny brae, badgeworth road Public Comment · 25 Feb 2026
  • Sunny brae, badgeworth road Public Comment · 25 Feb 2026
  • Llfa response Consultee Comment · 24 Feb 2026
  • Ppa - planning performance agreement Other · 23 Feb 2026
  • Sunny brae, badgeworth road Public Comment · 20 Feb 2026
  • Natural england response Consultee Comment · 17 Feb 2026
  • Natural england response Consultee Comment · 17 Feb 2026
  • Gwt response Consultee Comment · 13 Feb 2026
  • Updated ecology response Consultee Comment · 13 Feb 2026
  • Ecology officer response Consultee Comment · 11 Feb 2026
  • Cbc's hra Other · 11 Feb 2026
  • Application form Application Form · 04 Feb 2026
  • Arboricultural impact assessment Superseded Documents · 04 Feb 2026
  • Biodiversity net gain statement and assessment Superseded Documents · 04 Feb 2026
  • Ecological impact assessment Superseded Documents · 04 Feb 2026
  • Biodiversity metric calculation tool Superseded Documents · 04 Feb 2026
  • Design and access statement BackGround Papers · 04 Feb 2026
  • Design and access statement BackGround Papers · 04 Feb 2026
  • Design and access statement BackGround Papers · 04 Feb 2026
  • Sustainable construction checklist Superseded Documents · 04 Feb 2026
  • Site location plan Superseded Documents · 04 Feb 2026
  • Existing site plan Superseded Documents · 04 Feb 2026
  • Proposed site plan Superseded Documents · 04 Feb 2026
  • Proposed boundary plan Superseded Documents · 04 Feb 2026
  • Proposed materials plan Superseded Documents · 04 Feb 2026
  • Proposed affordable housing plan Superseded Documents · 04 Feb 2026
  • Proposed heights plan Superseded Documents · 04 Feb 2026
  • Proposed unit mix plan Superseded Documents · 04 Feb 2026
  • Proposed site plan coloured Superseded Documents · 04 Feb 2026
  • Proposed street elevations Superseded Documents · 04 Feb 2026
  • Proposed site sections Superseded Documents · 04 Feb 2026
  • Proposed bin & cycle storage detail for apartments Superseded Documents · 04 Feb 2026
  • Housetype vyne plans and elevations Superseded Documents · 04 Feb 2026
  • Housetype hertford plans and elevations Superseded Documents · 04 Feb 2026
  • Housetype charleston plans and elevations Superseded Documents · 04 Feb 2026
  • Housetype gosford v1 plans and elevations Superseded Documents · 04 Feb 2026
  • Housetype gosford v2 plans and elevations Superseded Documents · 04 Feb 2026
  • Housetype maidstone plans and elevations Superseded Documents · 04 Feb 2026
  • Housetype frogmore plans and elevations Superseded Documents · 04 Feb 2026
  • Housetype parham plans and elevations Superseded Documents · 04 Feb 2026
  • Housetype penhurst v1 plans and elevations Superseded Documents · 04 Feb 2026
  • Housetype penhurst v2 plans and elevations Superseded Documents · 04 Feb 2026
  • Housetype maisonette plans and elevations Superseded Documents · 04 Feb 2026
  • Proposed waste management plan Superseded Documents · 04 Feb 2026
  • Proposed car parking plan Superseded Documents · 04 Feb 2026
  • Phase 1 desk study and phase 2 ground investigation report Superseded Documents · 04 Feb 2026
  • Plan view & section a-a Superseded Documents · 04 Feb 2026
  • Site zonation plan Superseded Documents · 04 Feb 2026
  • Site investigation photograph Photo · 04 Feb 2026
  • Site grounds investigations plans Superseded Documents · 04 Feb 2026
  • 3 waste and landfill BackGround Papers · 04 Feb 2026
  • Trial pit information BackGround Papers · 04 Feb 2026
  • Phase 1 desk study and phase 2 ground investigation report photos Superseded Documents · 04 Feb 2026
  • Assessment of chemicals of potential concern to human health BackGround Papers · 04 Feb 2026
  • Hazwaste online information BackGround Papers · 04 Feb 2026
  • Non hazardous waste BackGround Papers · 04 Feb 2026
  • Non hazardous waste BackGround Papers · 04 Feb 2026
  • Noise impact assessment Superseded Documents · 04 Feb 2026
  • Historic environmental statement Superseded Documents · 04 Feb 2026
  • Flood risk assessment and drainage startegy Superseded Documents · 04 Feb 2026
  • Flood risk assessment map Superseded Documents · 04 Feb 2026
  • Flood risk assessment - appendix c Superseded Documents · 04 Feb 2026
  • Flood risk assessment - map flood zones Superseded Documents · 04 Feb 2026
  • Flood risk assessment - appendix g Superseded Documents · 04 Feb 2026
  • Site sections Superseded Documents · 04 Feb 2026
  • Northern site access arrangement Superseded Documents · 04 Feb 2026
  • Transport assessment Superseded Documents · 04 Feb 2026
  • Transport assessment Superseded Documents · 04 Feb 2026
  • Travel plan Superseded Documents · 04 Feb 2026
  • Site contribution to green belt purposes dla-2317-gbpurposes-rpt-02-v4 Superseded Documents · 04 Feb 2026
  • Proposed level strategy Superseded Documents · 04 Feb 2026
  • Hard landscape proposals 1 of 3 Superseded Documents · 04 Feb 2026
  • Hard landscape proposals - sheet 2 of 3 Superseded Documents · 04 Feb 2026
  • Hard landscape proposal Superseded Documents · 04 Feb 2026
  • Soft landscape proposals - sheet 1 of 3 Superseded Documents · 04 Feb 2026
  • Soft landscape proposals - sheet 2 of 3 Superseded Documents · 04 Feb 2026
  • Soft landscape proposals - sheet 3 of Superseded Documents · 04 Feb 2026
  • Illustrative landscape materplan Superseded Documents · 04 Feb 2026
  • Landscape and visual impact assessment (including open space statement) dla-2317 Superseded Documents · 04 Feb 2026
  • Community infrastructure levy - completed form BackGround Papers · 04 Feb 2026
  • Covering letter BackGround Papers · 04 Feb 2026
  • Planning statement Superseded Documents · 04 Feb 2026
  • Energy strategy dandara BackGround Papers · 04 Feb 2026

Trade members open them from here.

Open the documents

Checking the current position

The published feed does not show a live status for this application; the register on Cheltenham's own portal holds the authoritative version.

About full applications

A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.

Nearby applications

Within 500 metres

  • Euroclydon Badgeworth Road Cheltenham Gloucestershire GL51 6SJ

    19/01239/FUL Submitted 24 Jun 2019 77m away

    Extend existing dwelling to both sides, front and rear at ground and first floor level, together with remodelling

    Granted Full applications 12 docs
    Domestic
  • Euroclydon Badgeworth Road Cheltenham Gloucestershire GL51 6SJ

    21/01650/AMEND Submitted 19 Jul 2021 80m away

    Non-material amendment to planning permission to ref. 20/01666/FUL seeking material change to external wall facing materials

    Decided Amendments 3 docs
  • Michael Dene Badgeworth Road Cheltenham Gloucestershire GL51 6SJ

    26/00862/FUL Submitted 28 May 2026 118m away

    96% historically approved · decision due ~1 Sep

    Proposed new 4-bed dwelling.

    Awaiting decision Full applications 29 docs
    Domestic
  • BMW Showroom And Workshop Unit 1 Corinthian Park Corinthian Way Cheltenham Gloucestershire GL51 6UP

    19/01132/FUL Submitted 10 Jun 2019 224m away

    Use of land for temporary car parking for BMW car dealership. Eastern car park to provide 82 car parking spaces for a temporary period of up to 2 months. Following cessation of use of eastern car park, western car park to provide 161 car parking spaces for a temporary period of up to 2 years.

    Granted Full applications 19 docs
  • Corinthian Park Corinthian Way Cheltenham Gloucestershire

    19/01191/CLPUD Submitted 18 Jun 2019 230m away

    The Certificate of Lawfulness of Proposed Use or Development is sought to establish that the two temporary car parks granted permission by application ref. 19/01132/FUL] do not relinquish the ability to lawfully implement extant permission [LPA Ref.: 18/01004/FUL] on land to the west of Grovefield Way, Cheltenham. The eastern car park will be established on existing hardstanding, the western car park will require the construction of a new hardstanding. Primary access to the eastern car park will be from Corinthian Way. The western car park will be accessed through Cotswold BMW's existing car park. This will be made available through the removal of two car parking spaces on the existing car park.

    Granted Lawful development 8 docs
  • Land At North Road West And Grovefield Way Cheltenham Gloucestershire

    20/00741/DISCON Submitted 11 May 2020 238m away

    Discharge of conditions 6 and 15 of 16/02208/FUL (appeal decision ref APP/B1605/W/18/3200395) - Construction Traffic Management Plan and Plant Noise Assessment

    Granted Conditions 5 docs

In Cheltenham

  • 26/00962/FUL Decided

    The Yard Exmouth Court 1 Exmouth Street Cheltenham Gloucestershire GL53 7NR

    Erection of a self-build dwelling.

    16 Jun 2026 Full applications
  • 26/01478/FUL Awaiting decision

    3 The Verneys Cheltenham Gloucestershire GL53 7DB

    Removal of a failing wall and replacement with wooden fencing.

    15 Sep 2026 Full applications
  • 26/01233/FUL Granted

    40 Cudnall Street Charlton Kings Cheltenham Gloucestershire GL53 8HG

    Alterations and extension to dwelling, and erection of outbuilding. 

    31 Jul 2026 Full applications
  • 26/01155/FUL Granted

    3 Whitethorn Cottages Dark Lane Cheltenham Gloucestershire GL51 9RW

    Rear single storey extension and first floor bedroom extension.

    17 Jul 2026 Full applications
  • 26/01467/FUL Awaiting decision

    Lancaster House 2 Sovereign View Cheltenham Gloucestershire GL52 6FD

    Erection of a first floor extension, external staircase and an outbuilding within garden curtilage to provide home office and storage space, plus the replacement of existing balustrades.

    14 Sep 2026 Full applications