Planning application
Bradwell B Power Station Bradwell On Sea Essex
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Scoping consultation for an application by Bradwell Power Generation Company Ltd (the Applicant) for an Order granting Development Consent for the Bradwell B New Nuclear Power Station (the Proposed Development)
As published by the council, reference 20/01663/OBS3
Application record
- Reference
- 20/01663/OBS3
- Status
- Comments on Observation Application
- Decision
- Granted As published: Granted subject to conditions
- Received
- 9 Oct 2020
- Validated
- 9 Oct 2020
- Decided
- 6 Nov 2020
Timeline
Dates from the published record
-
9 Oct 2020
Received by Chelmsford
-
6 Nov 2020
Decision issued: Granted subject to conditions
-
10 Sep 2026
Added to PlanIndex
Documents
2 documents on file for this application
A planning file usually holds the application form, the consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWorking a patch? Trade sends you every new job in your area each morning. 14 days free.
What this grant of permission means
Chelmsford granted permission on 6 November 2020, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About this record
The published feed does not state which type of application this is; the register entry on Chelmsford's portal will say. Our guide explains the common types.