Skip to content
PlanIndex Get alerts
Menu

Planning application

Houghton Regis Substation, Porz Avenue, LU5 4SB

Decided Central Bedfordshire CB/24/02829/EPD Electricity works -Permitted Development

Decided. The decision notice on the council portal carries the outcome in full, including any conditions.

Proposal

Electricity Works Permitted Development: It is proposed to install a 3x3m GRP substation within the operational boundary of UK Power Networks' Houghton Regis Substation site on Porz Avenue, Houghton Regis, Dunstable, as shown on the attached plans. The GRP and equipment contained within will facilitate a customer connection to the network

As published by the council, reference CB/24/02829/EPD

Application record

Reference
CB/24/02829/EPD
Type
Electricity works -Permitted Development
Status
Decided
Decision
Comments Released
Received
26 Sep 2024
Validated
26 Sep 2024
Decided
3 Dec 2024
Parish
Houghton Regis
Postcode
LU5 4SB

Timeline

Dates from the published record

  1. 26 Sep 2024

    Received by Central Bedfordshire

  2. 3 Dec 2024

    Decision issued: Comments Released

  3. 14 Aug 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

Documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Watch members (£5 a month) open the document list from here.

Open the documents

After the decision

Central Bedfordshire has decided this application; the outcome above is the register's own wording and the decision notice on the council portal carries the detail. More in our guide to what happens after a planning decision.

About prior approval applications

Prior approval applies where permitted development rights already grant the principle of the work, leaving the council only the specific matters the rules name, commonly within 56 days. More in our guide to planning application types.

Nearby applications

Within 0.3 miles

  • Unit 29, Verey Road, Dunstable, LU5 4TT

    CB/22/04922/FULL Submitted 22 Dec 2022 250 yards away

    Proposed change of use: to Unit 29 to secure a flexible range of uses (within Classes E(g)(iii), B2 and / or B8) together with refurbishment works and physical alterations including reducing the building's overall footprint to increase its servicing yard and to provide a new access road to its rear car park, and all other associated works.

    Granted Full applications 44 docs
  • Unit 30, Verey Road, Dunstable, LU5 4TT

    CB/25/02759/FULL Submitted 29 Aug 2025 250 yards away

    Demolition of the existing building and erection of a new building within a flexible range of uses (Classes E(g)(iii) Light Industrial, B2 General Industrial and / or B8 Storage and Distribution) with ancillary offices, together with all other associated works

    Granted Full applications Demolition 84 docs
  • Unit 30, Verey Road, Dunstable, LU5 4TT

    CB/26/02697/DOC Submitted 28 Aug 2026 250 yards away

    100% historically approved · decision due ~27 Oct

    Discharge of Conditions 2,4,5,7,8,9,12,13 and 18 against planning permission ref CB/25/02759/FULL

    Awaiting decision Conditions 3 docs
  • Unit 29, Verey Road, Dunstable, LU5 4TT

    CB/23/01430/DOC Submitted 27 Apr 2023 250 yards away

    Discharge of Condition 9 against planning permission CB/22/04922/FULL (Proposed change of use: to Unit 29 to secure a flexible range of uses (within Classes E(g)(iii), B2 and / or B8) together with refurbishment works and physical alterations including reducing the building's overall footprint to increase its servicing yard and to provide a new access road to its rear car park, and all other associated works.)

    Granted Conditions 6 docs
  • Unit 30, Verey Road, Dunstable, LU5 4TT

    CB/26/02828/DOC Submitted 11 Sep 2026 250 yards away

    100% historically approved · decision due ~9 Nov

    Discharge of Condition 8 against planning permission ref. CB/25/02425/PADM

    Awaiting decision Conditions 4 docs
  • Unit 1, Foster Avenue, Dunstable, LU5 5TA

    CB/23/00281/ADV Submitted 27 Jan 2023 350 yards away

    Advertisement: 2 No. building mounted, colour coated metal signs and logo and 1 No. free standing internally illuminated colour coated metal entrance sign.

    Granted Advertising 10 docs

In Central Bedfordshire

  • CB/26/02527/EPD Decided

    Land at Oakwell Park, LU5 6GU

    Electricity Works Permitted Development: To relocate an existing substation

    Received 12 Aug, published by the council 18 Aug 2026 Prior approval
  • CB/26/02449/EPD Decided

    Biggleswade Eastern ELC Sub Station, Holme Crescent, Biggleswade, Bedfordshire. SG18 8DF

    Electricity Works Permitted Development (Install a new 10kVA generator on new concrete foundation. Install power duct from source to genny. Install wide cable trunking on concrete base. Install AMF panel on a new pole fixed to concrete base. Retain the Eltek PSU cabinet)

    Received 5 Aug, published by the council 7 Aug 2026 Prior approval
  • CB/26/02429/EPD Withdrawn

    Four Fields, Tebworth Road, Tebworth, Leighton Buzzard, LU7 9PZ

    Electricity Works Permitted Development related to an overhead line.

    Received 22 Jul, published by the council 7 Aug 2026 Prior approval
  • CB/26/02317/EPD Awaiting decision

    Four Fields, Tebworth Road, Tebworth, Leighton Buzzard, LU7 9PZ

    Electricity Works Permitted Development, disconnection of existing O/H to U/G single phase service and connection of a new three phase O/H service with a new pole installation.

    Received 22 Jul, published by the council 23 Jul 2026 Prior approval
  • CB/26/01178/EPD Granted

    7 Water End, Wrestlingworth, Sandy, SG19 2HA

    Electricity Board Notification: To rectify an existing safety compliance issue with the current low voltage overhead service to the property No 7 Water End, SG19 2HA. The proposal is to install a new intermediate pole and install new underground cable. The existing low voltage overhead service will then be removed.

    Received 10 Apr, published by the council 9 Sep 2026 Prior approval