Planning application
MERMAID BUILDINDS, PENTRE ROAD, ST CLEARS, CARMARTHEN, SA33 4AA
Works: New dwelling Several homes
Read from the description, not a valuation. How we read the register
Permission granted. Work must normally begin within five years of the decision or the permission lapses.
Proposal
CONVERSION OF THE UPPER FLOORS OF THE EXISTING BUILDINGS AND REAR OUTBUILDING TO FORM 6 APARTMENTS, GROUND FLOOR TO REMAIN AS SHOP UNITS
As published by the council, reference W/33877
Application record
- Reference
- W/33877
- Type
- Full planning permission
- Status
- Decision Made
- Decision
- Full Granted
- Received
- 3 May 2016
- Validated
- 27 May 2016
- Decided
- 24 Jun 2016
- Ward
- St. Clears (Historical)
- Parish
- St. Clears
- Decision by
- Delegated
- Postcode
- SA33 4AA
Timeline
Dates from the published record
-
3 May 2016
Received by Carmarthenshire
-
27 May 2016
Validated
Checked as complete and ready for consideration.
-
24 Jun 2016
Decision issued: Full Granted
-
2 Sep 2026
Added to PlanIndex
Documents
Plans, drawings, consultee responses and the officer's report
13 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Trade members open them from here.
Open the documentsWhat a grant of permission means
The process from here
Permission has been granted, usually subject to conditions listed on the decision notice, some of which must be discharged before work starts. The decision notice on the council portal sets out exactly what was approved.
Work must normally begin within five years of the decision or the permission lapses. Neighbours cannot appeal a grant; challenging one means judicial review of how the decision was made, within tight time limits.
About full applications applications
How this application type works
A full application seeks permission for a complete, detailed proposal in one go: siting, design, access and landscaping are all fixed at this stage. It is the standard route for new buildings, conversions and changes of use. The statutory target is eight weeks for smaller schemes and thirteen weeks for major development, though complex cases often take longer by agreement.
Nearby applications
Within 500 metres
-
MERMAID BUILDINGS, PENTRE ROAD, ST CLEARS, CARMARTHEN, SA33 4AA
DISCHARGE OF CONDITION 4 ON W/33877 (DUST MITIGATION SCHEME)
Granted Conditions 1 doc -
THE MEWS COTTAGE, PENTRE ROAD, ST CLEARS, CARMARTHEN, SA33 4AA
CHANGE OF USE FROM ONE BEDROOM FLAT TO OFFICE AND STORE
Granted Full applications 3 docs -
FORMER PUBLIC LIBRARY, PENTRE ROAD, ST CLEARS, CARMARTHEN, SA33 4AA
CHANGE OF USE OF REDUNDANT LIBRARY TO 2 DWELLING UNITS
Refused Full applications 4 docsSeveral homes -
FORMER PUBLIC LIBRARY, PENTRE ROAD, ST CLEARS, CARMARTHEN, SA33 4AA
CHANGE OF USE OF REDUNDANT LIBRARY TO 2 DWELLING UNITS
Refused Full applications 9 docsSeveral homes -
LAND OFF PENTRE ROAD, ST CLEARS, CARMARTHEN, SA33 4AA
INFORMATIONAL SIGNS FOR ST CLEARS HERITAGE TRAIL
Granted Advertising 7 docs -
Y GAT, PENTRE ROAD, ST CLEARS, CARMARTHEN, SA33 4AA
INFORMATIONAL SIGNS (PARTLY IN RETROSPECT)
Granted Advertising 3 docs
Other full applications applications
In Carmarthenshire
-
PL/11198 Granted
Towy Retail Park, Old Llangunnor Road, Carmarthen
Installation of solar panels on the building’s low-pitched, barrel-shaped
-
PL/11000 Granted
Pantymaen, Gellywen, Carmarthen, SA33 6DR
Erection of a portal framed agricultural building for cattle housing and associated works
-
PL/10493 Granted
Capel Farm, Carmarthen, SA33 5ED
Construction of concrete silage store and effluent tank built to SSAFO regs and associated works
-
PL/10577 Withdrawn
Bryngwyn, Talley, Llandeilo, SA19 7DQ
Change of use of land for the siting of a static caravan for farm workers accommodation and associated works (retrospective)
-
PL/10989 Granted
Land adjacent to the Tywi Valley Path, Nantgaredig, SA32 7LG
A mobility hub comprising 19 car parking spaces, including for 8 spaces designated for EV charging, cycle parking and associated infrastructure including a canopy over the EV chargers