Planning application
Carreg Wen Wind Farm St Gwynno Forest Aberdare
Permission granted. Work must normally begin within five years of the decision or the permission lapses.
Proposal
Request for comment - Planning and Environment Decisions Wales Scoping Opinon for Up to 18 wind turbines with associated battery storage, sub-station, access, and infrastructure works
As published by the council, reference 26/00573/RFO
Application record
- Reference
- 26/00573/RFO
- Type
- Request for observations
- Status
- Decided
- Decision
- Granted As published: Raise No Objection
- Received
- 10 Mar 2026
- Validated
- 10 Mar 2026
- Decided
- 8 Apr 2026
- Ward
- Outside Cardiff Boundary
- Decision by
- Delegated to Group Leader
Timeline
Dates from the published record
-
10 Mar 2026
Received by Cardiff
-
8 Apr 2026
Decision issued: Raise No Objection
-
22 Jul 2026
Added to PlanIndex
Documents
Plans, drawings, consultee responses and the officer's report
3 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat this grant of permission means
Cardiff granted permission on 8 April 2026, subject to any conditions on the decision notice. Work must normally begin within five years or the permission lapses. More in our guide to what happens after a planning decision.
About this record
The published feed does not state which type of application this is; the register entry on Cardiff's portal will say. Our guide explains the common types.