Proposal
Internal and external alterations associated with the conversion of existing garage area to office space including removal of mesh cladding and installation of curtain wall, glazing, louvre panels and double door and internal layout changes
As published by the council, reference 2019/3900/L
Application record
- Reference
- 2019/3900/L
- Type
- Listed Building Consent
- Status
- Granted As published: FINAL DECISION
- Decision
- Granted
- Received
- 16 Jul 2019
- Validated
- 31 Jul 2019
- Decided
- 23 Oct 2019
- Ward
- Bloomsbury (Pre May 2022)
- Decision by
- Delegated
- Postcode
- WC1H 0AL
Site history
Applications at this address on the Camden register
This site has had 42 applications since 2012: 36 approved, 2 refused.
-
2026/3533/P Awaiting decision
Institute Of Education 20 Bedford Way London WC1H 0AL
Variation of condition 2 (approved plans) of planning permission 2024/3198/P dated 02/10/2024 (for: Upgrading of the existing Bloomsbury District Heat network through the installation of roof mounted air source heat pumps and supporting equipment within an acoustic enclosure, and associated external works.) NAMELY, the reconfiguration of plant, amendment of the steelwork structure distributing the load of the new plant areas through the existing building, and the amendment of the louvred plant screens to satisfy the opposing requirements of ventilation to plant and sound attenuation.
-
2026/3505/L Awaiting decision
Institute Of Education 20 Bedford Way London WC1H 0AL
Variation of condition 2 (approved plans) of Listed Building Consent 2024/3245/L dated 02/10/2024 (for: Upgrading of the existing Bloomsbury District Heat network through the installation of roof mounted air source heat pumps and supporting equipment within an acoustic enclosure, and associated external works.) NAMELY, the reconfiguration of plant, amendment of the steelwork structure distributing the load of the new plant areas through the existing building, and the amendment of the louvred plant screens to satisfy the opposing requirements of ventilation to plant and sound attenuation.
-
2024/3644/L Granted
Institute of Education 20 Bedford Way London WC1H 0AL
Internal works comprising reconfiguration and refurbishment of Levels 5-9 Core A nib and wing, Level 6 wing A Lawton Room, Level 1 plantroom, Level 4 Room 426, Level 5 Zone C and Levels 1, 3 and 4 foyers; replacement mezzanine levels to selected rooms at Levels 2 and 3 in Core C and Levels 4 and 5; creation of new plant room at Level 8 wing A; new post room to Level 4; installation of platform lifts at Level 3 and 4 foyers; installation of fixed furniture and security gates in foyers; replacement of doors to the IALs building at Levels 4-9; infill of Level 1 drama hall window; replacement of existing halls signage with new digital signage at Levels 1-9 Cores A and B, Level 3 and 4 Zone B and Level 5 Zone C; and other associated internal works. External works comprising a new extended entrance at Bedford Way; a reconfigured entrance at Thornhaugh Mews; alterations to roof plant enclosure and new chiller unit; repairs and installation of insulation to external Levels 6-9 terraces; installation of secondary glazing to selected panels; new louvres at Level 8 wing A; smoke ventilation panels along Bedford Way elevation; refurbishment and repairs to Level 4 and 10 roof; new external gate at Level 5 wing A; replacement rooflights at Level 4; external beacons at Level 6 and 10 roof; and other associated external works
-
2024/3607/P Granted
Institute of Education 20 Bedford Way London WC1H 0AL
Installation of new extended entrance at Bedford Way; a reconfigured entrance at Thornhaugh Mews; alterations to roof plant enclosure and new chiller unit; repairs and installation of insulation to external Levels 6-9 terraces; installation of secondary glazing to selected panels; new louvres at Level 8 wing A; smoke ventilation panels along Bedford Way elevation; refurbishment and repairs to Level 4 and 10 roof; new external gate at Level 5 wing A; replacement rooflights at Level 4; external beacons at Level 6 and 10 roof; and other associated external works.
-
2024/3245/L Granted
Institute Of Education 20 Bedford Way London WC1H 0AL
Upgrading of the existing Bloomsbury District Heat network through the installation of roof mounted air source heat pumps and supporting equipment within an acoustic enclosure, and associated external and internal works
-
2024/3198/P Granted
Institute Of Education 20 Bedford Way London WC1H 0AL
Upgrading of the existing Bloomsbury District Heat network through the installation of roof mounted air source heat pumps and supporting equipment within an acoustic enclosure, and associated external works
-
2021/6235/P Granted
Institute Of Education 20 Bedford Way London WC1H 0AL
Refurbishment and reconfiguration of selected areas comprising: a new extended entrance at Bedford Way, a reconfigured entrance at Thornhaugh Mews; and other associated works.
-
2021/6242/L Granted
Institute Of Education 20 Bedford Way London WC1H 0AL
Refurbishment and reconfiguration of selected areas comprising: a new extended entrance at Bedford Way, a reconfigured entrance at Thornhaugh Mews; insertion of a new platform lift at Level 3 and a platform lift serving Level 3 and 4; refurbishment of the foyers at Levels 1, 3 and 4 including the installation of fixed furniture and security gates; replacement of doors to the IALS building at Levels 4-9; and other associated works.
-
2020/1787/L Granted
Institute Of Education 20 Bedford Way London WC1H 0AL
Refurbishment of the lifts within the Cores B and C including the upgrade of landing indicators, evacuations intercoms, landing stations, fire control switches, landing doors, service stations, header/overgate panels and other associated works.
-
2020/1567/L Granted
Institute Of Education 20 Bedford Way London WC1H 0AL
Refurbishment and reconfiguration of selected areas of the Institute of Education comprising: repairs and installation of insulation to the external terraces; creation of a new plant room at Level 8 Wing A and installation of new louvres to serve this plant room; refurbishment and repairs to the lobby roof on level 4 and the roof at Level 10; installation of new external gate at Level 5 of Wing A; and associated works.
Timeline
Dates from the published record
-
16 Jul 2019
Received by Camden
-
31 Jul 2019
Validated
Checked as complete and ready for consideration.
-
23 Oct 2019
Decision issued: Granted
-
22 Jul 2026
Added to PlanIndex
-
5 Sep 2026
Status changed to FINAL DECISION
Previously Final Decision.
Documents
Plans, drawings, consultee responses and the officer's report
4 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat this grant of permission means
Camden granted permission on 23 October 2019, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About heritage and listed building applications
Listed building consent is needed for works that affect the special interest of a listed building, and carrying out such works without it is a criminal offence. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
University of London Institute of Education 20 Bedford Way LONDON WC1H 0AL
Work to erect lighting columns to the rear of the building over the exit courtyard and additional lighting on the upper walkway.
Withdrawn Heritage and listed buildings 4 docs -
Institute of Education 20 Bedford Way LONDON WC1H 0AL
Discharge of Condition 6 (ref:2017/2543/L) granted 30/10/2017.
Granted Heritage and listed buildings 1 doc -
Levels 2-5 of Wing A Institute of Education (IoE) University College London 20 Bedford Way London WC1H 0AL
Refurbishment of Levels 2, 4 and 5 of Wing A to provide a replacement students bar to lv.4 (Use Class A4) as well as new teaching and study spaces, staff offices and associated facilities (Use Class D1). External alterations incl. to additions/ relocation of external doors to terraces; replacement terrace rooflight; raising level of terraces to allow for added insulation; and to raise height of existing terrace balustrades. Replacement HVAC system involving the removal of existing plant to lv.4 terrace and relocation to new plant room with associated installation of external louvres.
Granted Full applications Loft or dormer 77 docs -
Institute of Education 20 Bedford Way London WC1H 0AL
The reconfiguration and refurbishment of the Level 1 washrooms.
Granted Heritage and listed buildings 14 docs -
Institute of Education 20 Bedford Way London WC1H 0AL
Removal of no.3 existing and installation of no.7 new lamp posts around rear forecourt of University building (Use Class D1)
Granted Full applications 11 docs -
Levels 2-5 of Wing A University of London Institute of Education 20 Bedford Way London WC1H 0AL
Submission of external ventilation grill and door details, to partially discharge condition 4 of listed building consent 2018/3322/L (dated 14/11/2018) for 'Refurbishment involving internal and external changes to Levels 2, 4 and 5 of Wing A'
Granted Heritage and listed buildings 15 docs
Other heritage and listed building applications
In Camden
-
2026/1141/L Granted
25 John Street London WC1N 2BS
Internal and external alterations to partition layout at basement, supporting structures and external ground level, and alterations to design of conservatory, windows and doors granted under listed building consent 2024/0338/L dated 06/08/2024.
-
2025/1781/L Granted
Frognal Rise House Lower Terrace London NW3 6RE
Demolition of existing garage and interlinking gallery and replacement with new garage and garden room with link, new basement floor below garden, alterations to main house including replacement windows including reinstated oriel window and new French doors to entrance elevation, new roofing to side wing, new portico and replacement door to front elevation, enlargement of existing lightwell, replacement gates and canopy over entrance gate, restorations of boundary treatments, associated internal alterations including partial underpinning works and other minor alterations.
-
2026/4129/L Awaiting decision
6 Leverton Street London NW5 2PJ
Strip out kitchen including floor tiles and replace; replace plumbing and flooring in rear ensuite; replace plumbing in front ensuite and WC; replace internal doors; replace garden wall with metal railing; replace 3 rear windows, 3 rear elevation side windows, 1 rear door and 1 rear elevation side door with double-glazed crittal windows and doors; remove 2 rear windows; render rear elevation brickwork; and associated works.
-
2026/1686/L Granted
Flat Ground and 1st Floor and Flat 2nd and 3rd Floor 14 Downshire Hill London NW3 1NR
External and internal alterations in connection with conversion of two self-contained flats into a single-family dwellinghouse, including new doors at rear ground and second floor level, replacement windows at rear second and third floors level, removal of internal partitions, extending the stair handrail, and replacement internal doors, parquet flooring, skirting, architraves, cornicing, and fittings.
-
2026/2202/L Refused
4 Hampstead Square London NW3 1AB
Erection of conservatory to front elevation.