Land North Of Babraham Park And Ride Cherry Hinton Road Cambridgeshire
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Installation of a 132-33kV substation including 2 grid transformers and raised switch house, incorporating all works ancillary to the development of a substation.
As published by the council, reference 24/02948/FUL
Application record
- Reference
- 24/02948/FUL
- Type
- Full Application
- Status
- Decided
- Decision
- Granted As published: Granted Permission
- Received
- 6 Aug 2024
- Validated
- 6 Aug 2024
- Decided
- 12 Dec 2024
- Ward
- Shelford
- Decision by
- Committee Decision (Area/Main)
Timeline
Dates from the published record
-
6 Aug 2024
Received by Cambridge
-
12 Dec 2024
Decision issued: Granted Permission
-
27 Aug 2026
Added to PlanIndex
Who's behind it
Company information only, from the register and Companies House
Bidwells LLP Agent, registered in Cambridge
Active · incorporated 2009 · Cambridge
983 applications on PlanIndex · across 107 councils · 91% granted
Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.
See their track recordDocuments
Plans, drawings, consultee responses and the officer's report
54 documents on file for this application
- OFFICER REPORT
- DECISION NOTICE
- AGENT/APPLICANT PUBLIC SPEAKING LETTER
- EXTENSION OF TIME REQUEST
- AMENDED LANDSCAPE SPEC
- BNE LANDSCAPE
- REVISED LANDSCAPE PLAN
- FIELD BOUNDARY PLAN
- LOCAL HIGHWAY AUTHORITY
- ENVIRONMENTAL QUALITY AND GROWTH
- BNE LANDSCAPE
- ATC DATA REPORT
- VISIBILITY SPLAY PLAN
- LLFA
- LOCAL HIGHWAY AUTHORITY
- CADENT GAS
- CADENT GAS
- CAMBRIDGE CITY AIRPORT COMMENTS
- ARCHAEOLOGY COMMENTS
- ACKNOWLEDGEMENT LETTER
- BIODIVERSITY METRIC CALCULATION
- FEE CALCULATION
- APPLICATION FORM - NO PERSONAL INFO
- ATTACHMENT SUMMARY FROM PORTAL
- FRA WITH APPENDIX
- CONSTRUCTION TRAFFIC MANAGEMENT PLAN
- DRAINAGE STRATEGY
- BIODIVERSITY NET GAIN REPORT
- PRELIMINARY ECOLOGICAL APPRAISAL
- TRANSPORT STATEMENT
- ARBORICULTURAL METHOD STATEMENT
- COVERING LETTER
- ALTERNATIVE SITES ASSESSMENT
- LANDSCAPE MAINTENANCE PLAN
- LANDSCAPE PLAN
- LANDSCAPING SPECIFICATION
- LVA AND GREEN BELT STUDY APDX1
- LVA AND GREEN BELT STUDY APDX2
- LVA AND GREEN BELT STUDY APDX3
- LVA AND GREEN BELT STUDY APDX4
- LVA AND GREEN BELT STUDY APDX5
- LVA AND GREEN BELT STUDY APDX6
- LVA AND GREEN BELT STUDY
- ARCHAEOLOGICAL TRIAL TRENCHING EVAL REPORT
- PLANNING STATEMENT
- SUBSTATION NOISE ASSESSMENT
- SITE LOCATION PLAN
- STATUTORY BIODIVERSITY METRIC CONDITION ASSESSMENTS
- TECHNICAL VISUALISATIONS
- SUBSTATION COMPOUND GENERAL ARRANGEMENT PLAN
- RAISED CLADDED SUBSTATION 33 KV SWITCH AND CONTROL ROOM PLAN AND ELEVATIONS
- CAMBRIDGE EAST 132-33 KV COMPOUND SITE PLAN
- 1 OF 2 CAMBRIDGE EAST 132-33 KV COMPOUND ELEVATIONS
- 2 OF 2 CAMBRIDGE EAST 132-33 KV COMPOUND ELEVATIONS
Watch members (£5 a month) open the document list from here.
Open the documentsWhat this grant of permission means
Cambridge granted permission on 12 December 2024, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About full applications
A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
Land North Of Babraham Park And Ride Cherry Hinton Road Great Shelford Cambridgeshire
Installation of a 132-33kV substation including 2 grid transformers and raised switch house, incorporating all works ancillary to the development of a substation.
Granted Full applications 45 docs -
Land North Of Babraham Park And Ride Cherry Hinton Road Great Shelford Cambridgeshire
Submission of details required by condition 10 (Traffic Management Plan) of planning permission 24/02949/FUL
Granted Conditions 23 docs -
Netherhall Farm Worts Causeway Cambridge Cambridgeshire CB1 8RJ
Creation of a new farm access
Granted Full applications 33 docs -
Brethren Meeting House Shelford Bottom Great Shelford Cambridge Cambridge CB22 3FB
Extension to car park and associated lighting.
Granted Full applications Extension 21 docs
Other full applications
In Cambridge
-
26/02377/FUL Granted
5 Davy Road Cambridge Cambridgeshire CB1 3QW
Two storey front extension, a single storey rear extension (following the removal of the existing side and single storey rear extensions). Conversion of existing roof space following the reconstruction with a raised ridge height, to create 1no 3bed dwelling adjacent to the existing house.
-
26/03042/FUL Granted
Botanical Gardens, Plant Growth Facility Department Of Plant Science Bateman Street Cambridge Cambridgeshire CB2 1LR
Installation of a new stand-by Generator and acoustic enclosure at the Sainsbury Laboratory to serve Building B in mains fail conditions.
-
26/03008/FUL Granted
24 Luard Road Cambridge Cambridgeshire CB2 8PJ
Demolition of existing dwelling and construction of new 2.5 storey dwelling and associated landscaping
-
26/03002/FUL Granted
The Pickerel Inn 30 Magdalene Street Cambridge Cambridgeshire CB3 0AF
Remove existing jumbrellas 2 no. and replace with a new Mirador Pergola to the rear courtyard
-
26/03729/FUL Awaiting decision
27-28 Bridge Street Cambridge Cambridgeshire CB2 1UJ
Installation of new shopfront and seating at the rear external court yard with proposed conservatory glass roof.