Skip to content
PlanIndex Get alerts
Menu

Planning application

Land North Of Babraham Park And Ride Cherry Hinton Road Cambridgeshire

Granted Cambridge 24/02948/FUL Full Application

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Installation of a 132-33kV substation including 2 grid transformers and raised switch house, incorporating all works ancillary to the development of a substation.

As published by the council, reference 24/02948/FUL

Application record

Reference
24/02948/FUL
Type
Full Application
Status
Decided
Decision
Granted As published: Granted Permission
Received
6 Aug 2024
Validated
6 Aug 2024
Decided
12 Dec 2024
Ward
Shelford
Decision by
Committee Decision (Area/Main)

Timeline

Dates from the published record

  1. 6 Aug 2024

    Received by Cambridge

  2. 12 Dec 2024

    Decision issued: Granted Permission

  3. 27 Aug 2026

    Added to PlanIndex

Who's behind it

Company information only, from the register and Companies House

Bidwells LLP Agent, registered in Cambridge

Active · incorporated 2009 · Cambridge

983 applications on PlanIndex · across 107 councils · 91% granted

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Documents

Plans, drawings, consultee responses and the officer's report

54 documents on file for this application

  • OFFICER REPORT Application Committee / Delegated Report · 13 Dec 2024
  • DECISION NOTICE Application Decision Notice · 12 Dec 2024
  • AGENT/APPLICANT PUBLIC SPEAKING LETTER Application Officer Correspondence · 25 Nov 2024
  • EXTENSION OF TIME REQUEST Extension of Time Request · 14 Nov 2024
  • AMENDED LANDSCAPE SPEC Drawings · 31 Oct 2024
  • BNE LANDSCAPE Consultee Comments · 23 Oct 2024
  • REVISED LANDSCAPE PLAN Drawings · 10 Oct 2024
  • FIELD BOUNDARY PLAN Drawings · 10 Oct 2024
  • LOCAL HIGHWAY AUTHORITY Consultee Comments · 17 Sep 2024
  • ENVIRONMENTAL QUALITY AND GROWTH Consultee Comments · 12 Sep 2024
  • BNE LANDSCAPE Consultee Comments · 12 Sep 2024
  • ATC DATA REPORT Application Survey / Assessment / Statement · 06 Sep 2024
  • VISIBILITY SPLAY PLAN Drawings · 06 Sep 2024
  • LLFA Consultee Comments · 02 Sep 2024
  • LOCAL HIGHWAY AUTHORITY Consultee Comments · 20 Aug 2024
  • CADENT GAS Consultee Comments · 15 Aug 2024
  • CADENT GAS Consultee Comments · 15 Aug 2024
  • CAMBRIDGE CITY AIRPORT COMMENTS Consultee Comments · 15 Aug 2024
  • ARCHAEOLOGY COMMENTS Consultee Comments · 13 Aug 2024
  • ACKNOWLEDGEMENT LETTER Application Officer Correspondence · 12 Aug 2024
  • BIODIVERSITY METRIC CALCULATION Application Information · 07 Aug 2024
  • FEE CALCULATION Application Information · 06 Aug 2024
  • APPLICATION FORM - NO PERSONAL INFO Application Information · 06 Aug 2024
  • ATTACHMENT SUMMARY FROM PORTAL Attachment Summary · 06 Aug 2024
  • FRA WITH APPENDIX Application Information · 06 Aug 2024
  • CONSTRUCTION TRAFFIC MANAGEMENT PLAN Application Information · 06 Aug 2024
  • DRAINAGE STRATEGY Application Survey / Assessment / Statement · 06 Aug 2024
  • BIODIVERSITY NET GAIN REPORT Application Information · 06 Aug 2024
  • PRELIMINARY ECOLOGICAL APPRAISAL Application Information · 06 Aug 2024
  • TRANSPORT STATEMENT Application Survey / Assessment / Statement · 06 Aug 2024
  • ARBORICULTURAL METHOD STATEMENT Application Survey / Assessment / Statement · 06 Aug 2024
  • COVERING LETTER Application Information · 06 Aug 2024
  • ALTERNATIVE SITES ASSESSMENT Application Survey / Assessment / Statement · 06 Aug 2024
  • LANDSCAPE MAINTENANCE PLAN Application Information · 06 Aug 2024
  • LANDSCAPE PLAN Drawings · 06 Aug 2024
  • LANDSCAPING SPECIFICATION Drawings · 06 Aug 2024
  • LVA AND GREEN BELT STUDY APDX1 Application Information · 06 Aug 2024
  • LVA AND GREEN BELT STUDY APDX2 Application Information · 06 Aug 2024
  • LVA AND GREEN BELT STUDY APDX3 Application Information · 06 Aug 2024
  • LVA AND GREEN BELT STUDY APDX4 Application Information · 06 Aug 2024
  • LVA AND GREEN BELT STUDY APDX5 Application Information · 06 Aug 2024
  • LVA AND GREEN BELT STUDY APDX6 Application Information · 06 Aug 2024
  • LVA AND GREEN BELT STUDY Application Information · 06 Aug 2024
  • ARCHAEOLOGICAL TRIAL TRENCHING EVAL REPORT Application Information · 06 Aug 2024
  • PLANNING STATEMENT Application Survey / Assessment / Statement · 06 Aug 2024
  • SUBSTATION NOISE ASSESSMENT Application Survey / Assessment / Statement · 06 Aug 2024
  • SITE LOCATION PLAN Drawings · 06 Aug 2024
  • STATUTORY BIODIVERSITY METRIC CONDITION ASSESSMENTS Application Survey / Assessment / Statement · 06 Aug 2024
  • TECHNICAL VISUALISATIONS Application Information · 06 Aug 2024
  • SUBSTATION COMPOUND GENERAL ARRANGEMENT PLAN Drawings · 06 Aug 2024
  • RAISED CLADDED SUBSTATION 33 KV SWITCH AND CONTROL ROOM PLAN AND ELEVATIONS Drawings · 06 Aug 2024
  • CAMBRIDGE EAST 132-33 KV COMPOUND SITE PLAN Drawings · 06 Aug 2024
  • 1 OF 2 CAMBRIDGE EAST 132-33 KV COMPOUND ELEVATIONS Drawings · 06 Aug 2024
  • 2 OF 2 CAMBRIDGE EAST 132-33 KV COMPOUND ELEVATIONS Drawings · 06 Aug 2024

Watch members (£5 a month) open the document list from here.

Open the documents

What this grant of permission means

Cambridge granted permission on 12 December 2024, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About full applications

A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.

Nearby applications

Within 0.3 miles

In Cambridge

  • 26/02377/FUL Granted

    5 Davy Road Cambridge Cambridgeshire CB1 3QW

    Two storey front extension, a single storey rear extension (following the removal of the existing side and single storey rear extensions). Conversion of existing roof space following the reconstruction with a raised ridge height, to create 1no 3bed dwelling adjacent to the existing house.

    Received 23 Jun, published by the council 23 Jul 2026 Full applications
  • 26/03042/FUL Granted

    Botanical Gardens, Plant Growth Facility Department Of Plant Science Bateman Street Cambridge Cambridgeshire CB2 1LR

    Installation of a new stand-by Generator and acoustic enclosure at the Sainsbury Laboratory to serve Building B in mains fail conditions.

    Received 11 Aug, published by the council 14 Aug 2026 Full applications
  • 26/03008/FUL Granted

    24 Luard Road Cambridge Cambridgeshire CB2 8PJ

    Demolition of existing dwelling and construction of new 2.5 storey dwelling and associated landscaping

    Received 10 Aug, published by the council 14 Aug 2026 Full applications
  • 26/03002/FUL Granted

    The Pickerel Inn 30 Magdalene Street Cambridge Cambridgeshire CB3 0AF

    Remove existing jumbrellas 2 no. and replace with a new Mirador Pergola to the rear courtyard

    Received 7 Aug, published by the council 14 Aug 2026 Full applications
  • 26/03729/FUL Awaiting decision

    27-28 Bridge Street Cambridge Cambridgeshire CB2 1UJ

    Installation of new shopfront and seating at the rear external court yard with proposed conservatory glass roof.

    Received 2 Oct, published by the council 9 Oct 2026 Full applications