Saunderton Data Centre Campus Haw Lane Saunderton Buckinghamshire HP14 4JD

Awaiting decision Buckinghamshire PL/26/06118/UA

Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.

Proposal

Consultation on an environmental permit application EPR/SP3429LN/A001

As published by the council, reference PL/26/06118/UA

Application record

Reference
PL/26/06118/UA
Status
Registered
Validated
28 Jul 2026
Postcode
HP14 4JD

Timeline

Dates from the published record

  1. 28 Jul 2026

    Validated

    Checked as complete and ready for consideration.

  2. 3 Aug 2026

    Added to PlanIndex

  3. Decision

    Awaiting decision

    Decision expected by 22 September 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    Buckinghamshire took a median of 58 days over the applications it decided in the last year.

What happens while it is decided

This application is with Buckinghamshire for determination, against a statutory target of eight weeks. Over the last year Buckinghamshire's median decision took 58 days. More in our guide to how long planning decisions take.

About this record

The published feed does not state which type of application this is; the register entry on Buckinghamshire's portal will say. Our guide explains the common types.

Nearby applications

Within 0.3 miles

  • Former Molins Site Haw Lane Saunderton Buckinghamshire

    PL/25/6761/VRC Submitted 23 Dec 2025 150 yards away

    88% historically approved · decision due ~17 Feb

    Variation of conditions 2 (approved plans), 3 (detailed phasing plan), 4 (drainage), 10 (Noise), 13 (materials), 19 (site levels), 22 (hard and soft landscaping scheme), 23 (Landscape management plan), 24 (Landscaping implementation programme) and 25 (Ecological management plan) of planning permission 22/06872/VCDN relating to variations to the original permission 08/05740/FULEA (Erection of 4 no. Data centre buildings (sui generis use) together with associated groundworks, plant, electricity sub-station, security fence, gates and piers, landscaping, amendment to existing vehicular access(es), internal roads, service areas and provision of 150 car parking spaces with retention of the existing office building and "Ballroom" building fronting Haw Lane for ancillary operational uses and demolition of all other buildings and structures) to allow for relocation of substation enclosure

    Awaiting decision Conditions Demolition 186 docs
    Small domestic
  • Former Molins Site Haw Lane Saunderton Buckinghamshire HP14 4JE

    PL/26/01615/CONDA Submitted 26 Feb 2026 150 yards away

    88% historically approved · decision due ~23 Apr

    Application for approval of details subject to condition 26 (Code of Practice for Construction) of planning approval 22/06872/VCDN

    Awaiting decision Conditions 13 docs
  • Former Molins Site Haw Lane Saunderton Buckinghamshire

    PL/25/2380/CONDA Submitted 24 Jul 2025 200 yards away

    88% historically approved · decision due ~18 Sep

    Approval of condition 4 (drainage details) of planning permission 22/06872/VCDN - Variation of Conditions 2 and 3 (plan numbers and development phasing) attached to 08/05740/FULEA [Erection of 4 no. Data centre buildings (sui generis use) together with associated groundworks, plant, electricity sub-station, security fence, gates and piers, landscaping, amendment to existing vehicular access(es), internal roads, service areas and provision of 150 car parking spaces with retention of the existing office building and "Ballroom" building fronting Haw Lane for ancillary operational uses and demolition of all other buildings and structures] to allow for relocation of substation enclosure

    Awaiting decision Conditions Demolition 52 docs
    Small domestic