Planning application
Pavilion Leisure Centre, Kentish Way, Bromley, BR1 3EF
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Installation of solar panels on western side of roof of the Pavilion Leisure Centre fronting Kentish Way (56 DAY APPLICATION UNDER CLASS J, PART 14, SCHEDULE 2 OF THE GENERAL PERMITTED DEVELOPMENT ORDER TO DETERMINE WHETHER PRIOR APPROVAL IS REQUIRED IN RELATION TO THE DESIGN AND EXTERNAL APPEARANCE OF SOLAR EQUIPMENT ON NON-DOMESTIC PREMISES.
As published by the council, reference 23/00809/SOLAR
Application record
- Reference
- 23/00809/SOLAR
- Type
- Prior approval Part 14 Class J: Installation or alteration etc of solar equipment on non-domestic premises
- Status
- Decision Made
- Decision
- PRIOR APPROVAL IS REQUIRED AND GRANTED
- Received
- 1 Mar 2023
- Validated
- 1 Mar 2023
- Decided
- 24 Apr 2023
- Ward
- Bromley Town
- Decision by
- Delegated Decision
- Postcode
- BR1 3EF
Timeline
Dates from the published record
-
1 Mar 2023
Received by Bromley
-
24 Apr 2023
Decision issued: PRIOR APPROVAL IS REQUIRED AND GRANTED
-
29 Aug 2026
Added to PlanIndex
Who's behind it
Company information only, from the register and Companies House
Agent on file, registered in Burton-On-Trent
5 applications on PlanIndex · across 3 councils
Trade members see who it is, their full track record, and every application they have filed.
See who's behind itDocuments
Plans, drawings, consultee responses and the officer's report
11 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Trade members open them from here.
Open the documentsWhat this grant of permission means
Bromley granted permission on 24 April 2023, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About prior approval applications
Prior approval applies where permitted development rights already grant the principle of the work, leaving the council only the specific matters the rules name, commonly within 56 days. More in our guide to planning application types.
Nearby applications
Within 500 metres
-
93 The Glades Shopping Centre, High Street, Bromley, BR1 1DD
Details submitted to discharge conditions in relation to planning permission ref 21/03354/FULL1 (Amended by 21/03354/AMD):Condition 3 - Scheme showing the specification and performance of the kitchen extract system
Decided Conditions 12 docs -
101 THE GLADES SHOPPING CENTRE, HIGH STREET, BROMLEY, BR1 1DD
Replacement of existing bi-folding door to service hatch for takeaway use.
Granted Full applications Windows or glazing 10 docs -
The Glades Shopping Centre, High Street, Bromley, BR1 1DN
Non-material amendment application under S96a of the Town and Country Planning Act to planning permission reference 25/04028/FPA to allow for relocation of substation.
Granted Amendments 12 docs -
260 THE GLADES SHOPPING CENTRE, HIGH STREET, BROMLEY, BR1 1DN
Installation of two external louvres at first floor rear elevation of Unit 260.
Granted Full applications 13 docs -
The Glades Shopping Centre, High Street, Bromley, BR1 1DN
Redevelopment of Units 262, 65, 66 and 67 (former Debenhams, Superdry, Superdrug and basement levels) at The Glades Shopping Centre to comprise the subdivision of the existing unit into separate units (including street level unit accessed from Elmfield Road with pedestrian ramp and lower and upper mall levels accessed from The Glades ), infilling of the existing atrium, alterations to the roofscape, alterations to the shopfronts, amended pedestrian access to site, installation of seating and planters to Elmfield Road frontage and installation of replacement rooftop plant (car park Level 02), reconfiguration of car parking spaces and new electricity substation fronting Elmfield Road.
Granted Full applications 66 docs -
SMOKY BOYS, 3-5 QUEENS GARDENS, THE GLADES, BROMLEY, BR1 1DN
Continued display of 3 x illuminated fascia signs
Granted Advertising 8 docs
Other prior approval applications
In Bromley
-
26/02926/NOT Refused
Grass Verge, Chipperfield Road, Bromley, London, BR5 2HA
Removal of existing 8m high streetworks pole and 2no. cabinets, and replacement with 15m high Phase 7 Mk2 streetworks pole with 9no. radio antennas and ancillary apparatus including wraparound cabinet and 2no. additional equipment cabinets. (56 DAY CONSULTATION BY EE Ltd REGARDING THE NEED FOR APPROVAL OF SITING AND APPEARANCE OF TELECOMMUNICATIONS DEVELOPMENT)
-
26/02972/NOT Granted
3 SANDHURST ROAD, ORPINGTON, BR6 9HN
Single storey rear extension, extending beyond the rear wall of the original house by 4.9m, for which the maximum height would be 3.17m, and for which the height of the eaves would be 3m (42 Day Notification for Householder Permitted Development Prior Approval
-
26/03425/NOT Awaiting decision
33 THE AVENUE, WEST WICKHAM, BR4 0DX
Single storey rear extension, extending beyond the rear wall of the original house by 4.69m, for which the maximum height would be 3.19m, and for which the height of the eaves would be 3m (42 Day Notification for Householder Permitted Development Prior Approval)
-
26/02802/NOT Refused
PEILLS COURTYARD, BOURNE ROAD, BROMLEY, BR2 9NS
Change of use of commercial building (Use Class E) to 7 dwellinghouses (Use Class C3) under Schedule 2, Part 3, Class MA of The Town and Country Planning (General Permitted Development) (England) Order 2015 (as amended) (56 day application for prior approval in respect of transport and highways impacts, contamination risks, flood risk, noise impacts, impact on character or sustainability of a conservation area, provision of natural light to habitable rooms, impact on an area of general or heavy industry, impact of loss of services provided by a registered nursery or a health centre, and fire safety impacts)
-
26/02858/NOT Granted
3 MANNING ROAD, ORPINGTON, BR5 4DD
Single storey rear extension, extending beyond the rear wall of the original house by 3.50m, for which the maximum height would be 3.25m, and for which the height of the eaves would be 2.95m (42 Day Notification for Householder Permitted Development Prior Approval)