Planning application
Hornsea Project Three Offshore Wind Farm
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Partial discharge of requirements (conditions) for Provision of Ecological Management Plan (10), Construction Traffic Management Plan (18), Onshore Written Scheme of Investigation (16), Landscape Plan (8) & Code of Construction Practice (17): for Pre-construction Environmental Surveys and Pre-construction Land Drainage Surveys
As published by the council, reference 2021/2573
Application record
- Reference
- 2021/2573
- Type
- Approval of Details Required by DCO
- Status
- Decided
- Decision
- Granted As published: Approval of details - Approved
- Received
- 25 Nov 2021
- Validated
- 25 Nov 2021
- Decided
- 17 Mar 2022
- Ward
- Mulbarton And Stoke Holy Cross
- Parish
- Swardeston
- Decision by
- Delegated
Site history
Applications at this address on the Broadland register
This site has had 4 applications since 2021: 4 approved, 0 refused.
-
20212144 Granted
Hornsea Project Three Offshore Wind Farm
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Partial discharge of requirements (conditions) for Provision of Ecological Management Plan (10), Construction Traffic Management Plan (18), Onshore Written Scheme of Investigation (16), Landscape Plan (8) & Code of Construction Practice (17) : for Pre-construction Environmental Surveys and Pre-construction Land Drainage Surveys
-
2021/2223 Granted
Hornsea Project Three Offshore Wind Farm
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Partial discharge of requirements (conditions) for Provision of Landscaping (8), Ecological Management Plan (10), Onshore Archaeology (16), Code of Construction Practice (17) and Construction Traffic Management Plan (18) - For pre-construction Archaeological Investigations
-
20211803 Granted
Hornsea Project Three Offshore Wind Farm
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Partial discharge of requirements (conditions) for Provision of Landscaping (8), Ecological Management Plan (10), Onshore Archaeology (16), Code of Construction Practice (17) and Construction Traffic Management Plan (18) - For pre-construction Archaeological Investigations
Timeline
Dates from the published record
-
25 Nov 2021
Received by Broadland
-
17 Mar 2022
Decision issued: Approval of details - Approved
-
24 Jul 2026
Added to PlanIndex
Documents
Plans, drawings, consultee responses and the officer's report
13 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat this grant of permission means
Broadland granted permission on 17 March 2022, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About condition discharge and variation applications
This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
Hornsea Project Three Offshore Wind Farm
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Partial discharge of requirements (conditions) for Provision of Landscaping (8), Ecological Management Plan (10), Onshore Archaeology (16), Code of Construction Practice (17) and Construction Traffic Management Plan (18) - For pre-construction Archaeological Investigations
Granted Conditions 15 docs -
Hornsea Project Three Offshore Wind Farm
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Partial discharge of requirements (conditions) for Provision of Landscaping (8), Ecological Management Plan (10), Onshore Archaeology (16), Code of Construction Practice (17) and Construction Traffic Management Plan (18) - For pre-construction Archaeological Investigations
Granted Conditions 15 docs -
Hornsea Project Three Offshore Wind Farm
National Infrastructure Development Consent Order for Hornsea Project Three Offshore Wind Farm (Planning Inspectorate Reference: EN010080) Partial discharge of requirements (conditions) for Provision of Ecological Management Plan (10), Construction Traffic Management Plan (18), Onshore Written Scheme of Investigation (16), Landscape Plan (8) & Code of Construction Practice (17): for Pre-construction Environmental Surveys and Pre-construction Land Drainage Surveys
Granted Conditions 13 docs -
Wymeswold Chapel Road Roughton Norwich Norfolk NR11 8QP
Scots Pine - remove all the lower branches that are getting lower over on to the pathway and road way to balance up the said tree - TPO/21/0003
Granted Trees 3 docs -
Sereynis Back Lane Roughton Norwich Norfolk NR11 8QR
Single storey rear extension
Refused Householder Extension 12 docsSmall domestic -
Rose Cottage 65A Chapel Road Roughton Norwich Norfolk NR11 8QP
Erection of detached double car port in front garden/driveway with EV charger
Granted 10 docs
Other condition discharge and variation applications
In Broadland
-
2026/2058 Granted
Church Of St Remigius Norwich Road Hethersett Norfolk
Details of condition 3 (March) of original planning application 2025/2839 (Installation of 6 x 4m tall black lighting columns and 2 x car charging points)
-
2026/2295 Granted
Old Hall Farm Fakenham Road Attlebridge Norfolk NR9 5TQ
Details of conditions 5A and 5B (Archaeological Written Scheme of Investigation) of 2026/0771
-
2026/2195 Granted
Land North East Of Hackford Road Wicklewood Norfolk
Details reserved by condition 3 of 2026/0412 - highways vehicular access
-
2026/2247 Granted
The Chestnuts 4 Beccles Road Loddon Norfolk NR14 6JQ
Details reserved by condition 4c of 2025/3981 - material details
-
2026/2139 Granted
Market Farm Market Lane Burston Norfolk IP22 5TR
Details of conditions 3 (external boarding) & 4 (window and door details) of application 2026/1028 (Upgrade conservatory/boot room entrance) dated 07/07/2026