Planning application
P/25/740/DOC
Former Ford Engine Plant Waterton Industrial Estate Bridgend CF31 3PJ
Proposal
Approval of details for condition 5 (Ground Gas Protection) in relation to Substation 1 of P/25/37/FUL
As published by the council, reference P/25/740/DOC
Timeline
Dates from the published record
-
3 Dec 2025
Received by Bridgend
-
5 Dec 2025
Validated
Checked as complete and ready for consideration.
-
18 Dec 2025
Decision issued: DOC agree
-
28 Jul 2026
Added to PlanIndex
After the decision
The process from here
The council has decided this application; the published outcome sits in the record above and the decision notice on the council portal carries the detail, including any conditions.
If permission was granted, work must normally begin within five years of the decision. If it was refused, the applicant can appeal within the statutory time limit or submit a revised scheme.
About conditions applications
How this application type works
This type of application deals with conditions attached to an existing permission, either by supplying the details a condition requires, called discharging it, or by asking to vary or remove one. It does not reopen the principle of the permission itself. Building often cannot lawfully start, or continue past a set stage, until the named conditions are discharged.
Nearby applications
Within 500 metres
-
P/26/319/FUL Awaiting decision
CGI, Brocastle Avenue, Waterton, Bridgend, CF31 3TR
Proposed new entrance way, replacing roof coverings and minor external works/alterations to boundary treatments
-
P/26/325/DOC Decided
Former Bridgend Engine Plant Waterton Industrial Estate Waterton CF31 3BF
Approval of details for condition 20 (O) (written scheme of historic environment mitigation) of P/25/247/HYB
-
P/25/739/DOC Decided
Former Ford Engine Plant Waterton Industrial Estate Bridgend CF31 3PJ
Approval of details for conditions 27 (O) Ground Gas Protection) and 29 (F) Ground Gas Protection of P/25/247/HYB
-
P/25/643/RES Granted
Former Ford Engine Plant Waterton Industrial Estate Bridgend CF31 3PJ
Reserved matters for construction of the Interim Power Solution - a temporary new pylon and a substation - and the permanent Substation 2 (advance infrastructure), comprising transformers, switchgears and electrical equipment and the electrical earthing mesh, together with new buildings and the surf...
-
P/26/7/FUL Awaiting decision
TBD UK Ltd Brocastle Avenue Waterton Bridgend CF31 3US
Proposed extension to existing building and ancillary amended site access arrangements
-
P/25/725/FUL Awaiting decision
Land off Waterton Lane Bridgend
22no. affordable dwellings (10no. of 4P2B houses, 4no. of 2P1B walk up flats and 8no. of 5P3B houses) with associated landscape and infrastructure
Other conditions applications
In Bridgend
-
P/26/276/DOC Decided
HMP Parc Heol Hopcyn John Coity CF35 6AP
Approval of details for condition 4 (drainage) of P/25/417/FUL
-
P/26/325/DOC Decided
Former Bridgend Engine Plant Waterton Industrial Estate Waterton CF31 3BF
Approval of details for condition 20 (O) (written scheme of historic environment mitigation) of P/25/247/HYB
-
P/26/245/DOC Decided
Land east of Cwm Felin & south of Graig Terrace/Ebenezer Terrace Blackmill CF35 6EJ
Approval of details for condition 3 (Construction Environmental Management Plan) of P/14/838/FUL
-
P/26/263/RLX Granted
Anwen Care Home, Pant-Yr-Awel, Ogmore Vale, CF32 7LA
Variation of standard time condition to extend the planning permission of P/21/208/FUL (Extensions to provide 14 additional complex nursing care bedrooms; lifts and associated lounge space; replacement stretcher lift to main home and additional lounge/ancillary space)
-
P/26/391/DOC Awaiting decision
Unit 13 Kingsway Bridgend Industrial Estate CF31 3UT
Approval of details for conditions 8 (surface water drainage) and 13 (waste management plan) of P/25/278/FUL