Granted Basildon 21/01452/FULL Full Application

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Installation of renewable led energy generation station, comprising ground-mounted photovoltaic solar arrays and battery-based electricity storage containers together with substation, inverter/transformers stations, site access, internal access tracks, security measures, access gates, other ancillary infrastructure, grid connection cable, landscaping and biodiversity enhancements.

As published by the council, reference 21/01452/FULL

Application record

Reference
21/01452/FULL
Type
Full Application
Status
Decided
Decision
Granted
Received
23 Sep 2021
Validated
23 Sep 2021
Decided
8 Sep 2023
Ward
Nethermayne
Decision by
Committee Decision

Timeline

Dates from the published record

  1. 23 Sep 2021

    Received by Basildon

  2. 8 Sep 2023

    Decision issued: Granted

  3. 11 Sep 2026

    Added to PlanIndex

Cases linked to this one on the register

  • Appeal: 23/00065/NONDET (Appeal Withdrawn)

Who's behind it

Company information only, from the register and Companies House

Enso Energy Limited Agent, registered in Cirencester

Active · incorporated 2015 · Cirencester

27 applications on PlanIndex · across 12 councils · 88% granted

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Documents

Plans, drawings, consultee responses and the officer's report

76 documents on file for this application

  • SITE PLAN - THURROCK Drawing · 23 Dec 2022
  • SITE PLAN - THURROCK FENCE AREA Drawing · 23 Dec 2022
  • NON-BREEDING WATERBIRD MITIGATION TECHNICAL NOTE Drawing · 23 Dec 2022
  • LANDSCAPING AND ECOLOGY PLAN Drawing · 23 Dec 2022
  • SUBMISSION LETTER BackGround Papers - Redacted · 23 Sep 2021
  • THE LOCATION PLAN Drawing · 23 Sep 2021
  • THE LOCATION PLAN Drawing · 23 Sep 2021
  • THE LOCATION PLAN Drawing · 23 Sep 2021
  • THE LOCATION PLAN Drawing · 23 Sep 2021
  • THE LOCATION PLAN Drawing · 23 Sep 2021
  • THE LOCATION PLAN Drawing · 23 Sep 2021
  • HIGH ROAD JUNCTION ARRANGEMENT Drawing · 23 Sep 2021
  • WEATHER STATION Drawing · 23 Sep 2021
  • SUBSTATION ELEVATIONS Drawing · 23 Sep 2021
  • PV ELEVATIONS Drawing · 23 Sep 2021
  • INTERNAL ACCESS ROAD Drawing · 23 Sep 2021
  • DETAILED SOFT LANDSCAPE PLAN Drawing · 23 Sep 2021
  • PLANTING SCHEDULE Drawing · 23 Sep 2021
  • PROPOSED SITE PLAN Drawing · 23 Sep 2021
  • INVERTER/TRANSFORMER STATION Drawing · 23 Sep 2021
  • FENCE AND GATE ELEVATION Drawing · 23 Sep 2021
  • LANDSCAPE AND ECOLOGY ENHANCEMENT PLAN Drawing · 23 Sep 2021
  • PV ELEVATION BALLAST FOUNDATION Drawing · 23 Sep 2021
  • DETAILED SOFT LANDSCAPING PLAN Drawing · 23 Sep 2021
  • DETAIED SOFT LANDSCAPING PLAN Drawing · 23 Sep 2021
  • STORAGE CONTAINER ELEVATIONS Drawing · 23 Sep 2021
  • BATTERY FENCE AND GATE ELEVATION Drawing · 23 Sep 2021
  • CCTV ELEVATIONS Drawing · 23 Sep 2021
  • BATTERY CONTAINER ELEVATIONS Drawing · 23 Sep 2021
  • AUXILARY TRANSFORMER Drawing · 23 Sep 2021
  • CABLE TROUGH Drawing · 23 Sep 2021
  • CONTROL ROOM ELEVATIONS Drawing · 23 Sep 2021
  • SUBMISSION DRAWINGS Drawing · 23 Sep 2021
  • PLANNING STATEMENT BackGround Papers - Redacted · 23 Sep 2021
  • DESIGN AND ACCESS STATEMENT BackGround Papers - Redacted · 23 Sep 2021
  • NON-TECHINICIAL SUMMARY OF THE ENVIRONMENTAL STATEMENT BackGround Papers - Redacted · 23 Sep 2021
  • APPENDIX 2 PROPOSED SITE LAYOUT PLAN BackGround Papers - Redacted · 23 Sep 2021
  • PROJECT QUALITY CONTROL SHEET BackGround Papers - Redacted · 23 Sep 2021
  • ENVIRONMENTAL STATION CHAPTER 2 BackGround Papers - Redacted · 23 Sep 2021
  • ENVIRONMENTAL STATION CHAPTER 3 BackGround Papers - Redacted · 23 Sep 2021
  • ENVIRONMENTAL STATION CHAPTER 4 BackGround Papers - Redacted · 23 Sep 2021
  • ENVIRONMENTAL STATION CHAPTER 5 BackGround Papers - Redacted · 23 Sep 2021
  • ENVIRONMENTAL STATION CHAPTER 6 BackGround Papers - Redacted · 23 Sep 2021
  • ENVIRONMENTAL STATION CHAPTER 9 BackGround Papers - Redacted · 23 Sep 2021
  • ENVIORNMENTAL STATION CHAPTER 10 BackGround Papers - Redacted · 23 Sep 2021
  • ENVIRONMENTAL STATEMENT - CONTENT PAGE BackGround Papers - Redacted · 23 Sep 2021
  • ARCHAEOLOGY REPORT BackGround Papers - Redacted · 23 Sep 2021
  • ENVIRONMENTAL STATEMENT - APPENDIX 7.2 BackGround Papers - Redacted · 23 Sep 2021
  • DETAILED GRADIOMETER BackGround Papers - Redacted · 23 Sep 2021
  • ENVIRONMENTAL STATEMENT BackGround Papers - Redacted · 23 Sep 2021
  • ENVIRONMENTAL STATEMENT BackGround Papers - Redacted · 23 Sep 2021
  • APPENDICES LVIA BackGround Papers - Redacted · 23 Sep 2021
  • ENVIRONMENTAL STATEMENT BackGround Papers - Redacted · 23 Sep 2021
  • REQUEST FOR SCOPING BackGround Papers - Redacted · 23 Sep 2021
  • SCOPING OPINION BackGround Papers - Redacted · 23 Sep 2021
  • BIODIVERSITY NET GAIN REPORT BackGround Papers - Redacted · 23 Sep 2021
  • EIA PROJECT TEAM QUALIFICATION AND EXPERIENCE BackGround Papers - Redacted · 23 Sep 2021
  • VIEWPOINT 2 BackGround Papers - Redacted · 23 Sep 2021
  • FINDINGS OF THE ECOLOGICAL SURVEY BackGround Papers - Redacted · 23 Sep 2021
  • ENVIRONMENTAL STATEMENT - APPENDIX 6.1 - 6.6 BackGround Papers - Redacted · 23 Sep 2021
  • ENVIRONMENTAL STATEMENT BackGround Papers - Redacted · 23 Sep 2021
  • ENVIRONMENTAL STATEMENT BackGround Papers - Redacted · 23 Sep 2021
  • ENVIRONMENTAL STATEMENT - LANDSCAPE VISUALS BackGround Papers - Redacted · 23 Sep 2021
  • FLOOD RISK ASSESSMENT BackGround Papers - Redacted · 23 Sep 2021
  • FLOOD RISK ASSESSMENT BackGround Papers - Redacted · 23 Sep 2021
  • NOISE IMPACT ASSESSMENT BackGround Papers - Redacted · 23 Sep 2021
  • GLINT AND GLARE ASSESSMENT BackGround Papers - Redacted · 23 Sep 2021
  • STATEMENT OF COMMUNITY INVOLVEMENT BackGround Papers - Redacted · 23 Sep 2021
  • GROUND INVESTIGATION REPORT BackGround Papers - Redacted · 23 Sep 2021
  • AGRICULTURAL LAND CLASSIFICATION BackGround Papers - Redacted · 23 Sep 2021
  • DETAILED SOFT LANDSCAPING PLAN Drawing · 23 Sep 2021
  • DETAILED SOFT LANDSCAPING PLAN Drawing · 23 Sep 2021
  • DETAILED SOFT LANDSCAPING PLAN Drawing · 23 Sep 2021
  • DETAILED SOFT LANDSCAPING PLAN Drawing · 23 Sep 2021
  • DETAILED SOFT LANDSCAPING PLAN Drawing · 23 Sep 2021
  • APPLICATION FORM - WITHOUT PERSONAL DATA Application Form · 23 Sep 2021

Watch members (£5 a month) open the document list from here.

Open the documents

What this grant of permission means

Basildon granted permission on 8 September 2023, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About full applications

A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.

In Basildon

  • 26/01011/FULL Granted

    27 Tyler Avenue Laindon Basildon Essex SS15 5UR

    Proposed garage conversion and porch

    18 Sep 2026 Full applications
  • 26/00957/FULL Granted

    10 Leysings Lee Chapel South Basildon Essex SS16 5SL

    Proposed first floor extension over existing garage and dining area.

    Received 28 Aug, published by the council 1 Sep 2026 Full applications
  • 26/01196/FULL Awaiting decision

    TEXACO 327 Whitmore Way Basildon Essex SS14 2NL

    Redevelopment and Reconfiguration of the Existing Forecourt, including the Removal of the Existing Car Wash; The Installation of Three Jet Wash Bays, Revised Parking Arrangements and Associated Ancillary Works

    Received 3 Nov, published by the council 4 Nov 2026 Full applications
  • 26/01199/FULL Awaiting decision

    Unit Number 5 Radford Way Billericay Essex CM12 0DX

    Replacement of an existing external staircase with a new galvanised steel staircase, including associated landings, handrails and balustrades.

    Received 3 Nov, published by the council 4 Nov 2026 Full applications
  • 26/01198/FULL Awaiting decision

    10 Chestwood Close Billericay Essex CM12 0PB

    Amended application to previously approved application 26/00953/FULL - Proposed first floor extension to rear, alteration to fenestration, removal of chimney sttacks and oak framed storm porch to front.

    3 Nov 2026 Full applications