The East Anglia 3 Offshore Wind Farm Order 2017

Granted Babergh DC/26/00630 Discharge of Requirement

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Approval of Details reserved by Requirement 14 Provision of Landscaping pursuant to The East Anglia 3 Offshore Wind Farm Order 2017

As published by the council, reference DC/26/00630

Application record

Reference
DC/26/00630
Type
Discharge of Requirement
Status
Granted
Decision
Granted
Received
13 Feb 2026
Validated
13 Feb 2026
Decided
10 Mar 2026
Ward
Bramford
Parish
Bramford
Decision by
Delegated Decision

Timeline

Dates from the published record

  1. 13 Feb 2026

    Received by Babergh

  2. 10 Mar 2026

    Decision issued: Granted

  3. 9 Aug 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

2 documents on file for this application

  • 090969-102 10-20MM GRANITE EN12620 EN933 PSD & FLAKI Additional Information · 01 Jan 1900
  • FINAL STONE PROPOSAL Additional Information · 01 Jan 1900

Watch members (£5 a month) open the document list from here.

Open the documents

What this grant of permission means

Babergh granted permission on 10 March 2026, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About condition discharge and variation applications

This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.

Nearby applications

Within 0.3 miles

  • East Anglia Three Offshore Windfarm Tye Lane Bramford Suffolk

    DC/26/02120 Submitted 19 May 2026 50 yards away

    East Anglia 3 Onshore Converter Station - Application pursuant to discharge of requirements 24 and 25(2)(f). to agree out of hours working (a request for out of hours working on the following dates May: 24th, 25th & 31st (07:00 hrs to 17:00hrs) and June: 7th, 14th, 21st & 28th (07:00 hrs to 17:00hrs)

    Granted Conditions 3 docs
  • East Anglia Three Offshore Windfarm Tye Lane Bramford Suffolk

    DC/26/02120 Submitted 19 May 2026 50 yards away

    East Anglia 3 Onshore Converter Station - Application pursuant to discharge of requirements 24 and 25(2)(f). to agree out of hours working (a request for out of hours working on the following dates May: 24th, 25th & 31st (07:00 hrs to 17:00hrs) and June: 7th, 14th, 21st & 28th (07:00 hrs to 17:00hrs)

    Granted Conditions 3 docs
  • East Anglia Three Offshore Windfarm Tye Lane Bramford Suffolk

    DC/26/02487 Submitted 10 Jun 2026 50 yards away

    East Anglia Three - Onshore Cable Route: Out of hours working request for the following dates June: 21st, 28th, July: 05th, 12th 19th and 26th (10:00 - 16:00).

    Granted Conditions 3 docs
  • East Anglia 3-Converter Station

    DC/25/04525 Submitted 11 Oct 2025 50 yards away

    Out of Hours Working request - 7am-7pm on 19/10/25, 26/10/25 and 02/11/25

    Granted Conditions 2 docs
  • East Anglia Three Offshore Windfarm Tye Lane Bramford Suffolk

    DC/21/00067 Submitted 21 Dec 2020 50 yards away

    Approval of details reserved by Requirement 24 (Control of noise during operational phase (Part 2)) pursuant to The East Anglia ONE Offshore Wind Farm Order 2014

    Granted Conditions 6 docs
  • East Anglia Three Offshore Windfarm

    DC/21/00065 Submitted 18 Dec 2020 50 yards away

    Approval of details reserved by Requirement 23 (External Lighting and Control of Artificial Light Emissions (Parts 1 and 2)) pursuant to The East Anglia THREE Offshore Wind Farm Order 2017

    Granted Conditions 9 docs

In Babergh

  • DC/26/00236 Granted

    Chilton Woods Mixed Development To North Of Woodhall Business Park Sudbury Suffolk

    Discharge of Conditions Application for B/15/01718 - Part discharge of Conditions 38 (Landscaping) and 43 (Open Space) for phase 4 only.

    Received 21 Jan, published by the council 24 Jul 2026 Conditions
  • DC/26/00355 Refused

    Land To The Rear Of 30 Market Hill Sudbury Suffolk

    Application under Section 73 of The Town and Country Planning Act 1990 - Variation of Condition 2 (Approved Plans and Documents) and Condition 12 (Provision of Access Prior to Any Other Works Commencing) of Planning Permission DC/25/05227 dated 23/01/2026 - Erection of 4No. (terraced) dwellings and alterations/improvement to: (1) outbuilding to form cycle store, (2) boundary wall and (3) existing access.

    Received 28 Jan, published by the council 24 Jul 2026 Conditions
  • DC/26/04408 Awaiting decision

    The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Submission of Details reserved by Requirement 6 Detailed Written Scheme of Investigation for Stage 3 of the authorised development pursuant to The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Received 9 Oct, published by the council 11 Oct 2026 Conditions
  • DC/26/04407 Awaiting decision

    High Elm Bungalow Crowfield Road Stonham Aspal Suffolk

    Discharge of Conditions Application for DC/24/01026 - Condition 3 (Biodiversity Net Gain)

    Received 9 Oct, published by the council 11 Oct 2026 Conditions
  • DC/26/04395 Awaiting decision

    Little Wenham Hall Hall Lane Wenham Parva Colchester Suffolk CO7 6PZ

    Discharge of Conditions for DC/24/02709 - Condition 14 (Historic Floor Finishes- Building D)

    Received 8 Oct, published by the council 11 Oct 2026 Conditions