Planning application
Land at Ford Airfield Ford
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Application to approve details required under the Section 106 dated 13.07.23 (as amended) linked to F/4/20/OUT in relation to Clauses 1.2 and 2.2 of the Fifth Schedule (Open Space Scheme and Play Areas Scheme) for Phases IRM, RM1 and RM4.
As published by the council, reference F/32/26/AOO
Application record
- Reference
- F/32/26/AOO
- Status
- Approve
- Decision
- Permitted
- Received
- 26 May 2026
- Validated
- 26 May 2026
- Decided
- 24 Jul 2026
- Parish
- Ford
Site history
Applications at this address on the Arun register
This site has had 28 applications since 2024: 15 approved, 0 refused.
-
F/41/26/DOC Awaiting decision
Land at Ford Airfield Ford
Approval of details reserved by condition imposed under F/4/20/OUT relating to condition 10-Construction Management Plan.
-
F/39/26/DOC Awaiting decision
Land at Ford Airfield Ford
Approval of details reserved by condition under F/4/20/OUT relating to conditions 28- Foul Drainage 29- Surface Water Drainage 30- Discharge Flows to Watercourses 31- Maintenance & Management of Surface Water Drainage System. (Phase RM1)
-
F/34/26/DOC Decided
Land at Ford Airfield Ford
Partial approval of details reserved by condition under F/15/24/RES relating to condition 11- External Dwelling Materials (excluding dark red multi red brick and flint blocks)
-
F/28/26/DOC Decided
Land at Ford Airfield Ford
Approval of details reserved by condition under F/14/24/RES relating to Condition 5- Tree Pit Details.
-
F/25/26/DOC Withdrawn
Land at Ford Airfield Ford
Approval of details reserved by condition under F/4/20/OUT relating to conditions 28- Foul Drainage, 29- Surface Water Drainage, 30- Discharge to Watercourses and 31- Maintenance & Management.
-
F/22/26/DOC Awaiting decision
Land at Ford Airfield Ford
Approval of details reserved by condition under F/4/20/OUT relating to conditions 28- Proposed foul drainage system, 29- Proposed surface water drainage scheme, 30- Discharges to watercourses and 31-Maintenance & management of surface water drainage system.
-
F/18/26/DOC Decided
Land at Ford Airfield Ford
Approval of details reserved by condition imposed under F/4/20/OUT relating to condition 14-copy of asbestos register and remedial strategy.
-
F/14/26/DOC Decided
Land at Ford Airfield Ford
Approval of details reserved by condition under F/15/24/RES relating to condition 3- Tree Pit Details.
-
F/15/26/DOC Granted
Land at Ford Airfield Ford
Approval of details reserved by condition under F/4/20/OUT (Phase IRM) relating to condition 10- Construction Management Plan.
-
F/16/26/DOC Granted
Land at Ford Airfield Ford
Approval of details reserved by condition under F/4/20/OUT (Phase RM1) relating to condition 10- Construction Management Plan.
Timeline
Dates from the published record
-
26 May 2026
Received by Arun
-
24 Jul 2026
Decision issued: Permitted
-
31 Jul 2026
Added to PlanIndex
Documents
Plans, drawings, consultee responses and the officer's report
Documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Trade members open them from here.
Open the documentsWhat this grant of permission means
Arun granted permission on 24 July 2026, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About this record
The published feed does not state which type of application this is; the register entry on Arun's portal will say. Our guide explains the common types.