Planning application
LA08/2025/1305/DC
Lands at and to the south and north-west of Gosford Services Station, 145a Gosford Road, Loughgilly, Armagh, BT60 2DE
Proposal
Discharge of condition number 20 of planning approval ref: LA08/2023/3087/F which states: Prior to the construction of the drainage network, the applicant shall submit a final Drainage Assessment, to be agreed in writing with the Council which demonstrates the safe management of any out of sewer flooding emanating from the surface water drainage network, in a 1 in 100-year event with an additional allowance for climate change. Reason: To safeguard against flood risk to the development and from the development to elsewhere.
As published by the council, reference LA08/2025/1305/DC
Timeline
Dates from the published record
-
21 Oct 2025
Received by Armagh City, Banbridge and Craigavon
-
27 Oct 2025
Validated
Checked as complete and ready for consideration.
-
15 Dec 2025
Decision issued: Condition Discharged
-
29 Jul 2026
Added to PlanIndex
After the decision
The process from here
The council has decided this application; the published outcome sits in the record above and the decision notice on the council portal carries the detail, including any conditions.
If permission was granted, work must normally begin within three years of the decision. If it was refused, the applicant can appeal within the statutory time limit or submit a revised scheme.
About conditions applications
How this application type works
This type of application deals with conditions attached to an existing permission, either by supplying the details a condition requires, called discharging it, or by asking to vary or remove one. It does not reopen the principle of the permission itself. Building often cannot lawfully start, or continue past a set stage, until the named conditions are discharged.
Nearby applications
Within 500 metres
-
LA08/2025/1133/DC Awaiting decision
Lands at and to the south and north-west of Gosford Services Station, 145a Gosford Road, Loughgilly, Armagh, BT60 2DE
Proposed discharge of conditions 26 & 27 of Planning Approval LA08/2023/3087/F. Condition 26 states: No development shall commence at this site until the applicant has submitted evidence in writing to the Planning Authority for its agreement demonstrating that the risks to environmental receptors due to on-site contamination have been effectively assessed. This evidence shall include: • Groundwater and surface water quality monitoring data and a quantitative risk assessment to investigate the risks to water from contamination identified at the site. • If unacceptable risks to water are identified, provision of remedial criteria as soil and groundwater concentrations that would not pose an unacceptable risk to receptors. The remedial criteria are required to be derived through Detailed Quantitative Risk Assessment based on the conceptual site model and applying the Environment Agency’s Hydrogeological Risk Assessment for Land Contamination, Remedial Targets Worksheet v3.2 (P20). If unacceptable risks to receptors are identified a detailed remediation strategy will be required in writing for agreement with the Planning Authority to address those risks. Reason: Protection of environmental receptors to ensure the site is suitable for use. Condition 27 states: No development shall commence at this site until a Detailed Remediation Strategy to address all unacceptable risks to receptors has been submitted in writing and agreed with the Planning Authority. This strategy shall be completed by competent persons in accordance with the Land Contamination: Risk Management (LCRM) guidance available at: https://www.gov.uk/guidance/land-contamination-how-to-manage-the-risks. This strategy should identify all unacceptable risks on the site, the remedial objectives/criteria and the measures which are proposed to mitigate them (including maps/plans showing the remediation design, implementation plan detailing timetable of works, remedial criteria, monitoring program, etc). Reason: Protection of environmental receptors to ensure the site is suitable for use.
-
LA08/2025/1131/DC Awaiting decision
Lands at and to the south and north-west of Gosford Services Station, 145a Gosford Road, Loughgilly, Armagh, BT60 2DE
Proposed Partial Discharge of condition 19 of planning approval LA08/2023/3087/F. Condition 19 states: No development should take place on-site until the method of sewage disposal has been submitted to and agreed in writing with the Council. The works shall be carried out as approved. Reason: To ensure protection to the aquatic environment and to help the applicant avoid incurring unnecessary expense before it can be ascertained that a feasible method of sewage disposal is available.
Other conditions applications
In Armagh City, Banbridge and Craigavon
-
LA08/2026/0566/DC Decided
Lands at No. 9 Derrinraw Road, Portadown, BT62 1UX
Discharge of condition 8 of LA08/2024/1525/F which reads: A final Construction Environmental Management Plan (fCEMP) must be submitted within 8 weeks following the grant of planning permission. This shall include all necessary mitigation measures for the construction phase of the development as outlined in the oCEMP (Taggarts, May 2025) to avoid the egress of any polluting discharges to Lough Neagh and Lough Beg Ramsar site and Lough Neagh and Lough Beg SPA.
-
LA08/2026/0510/DC Decided
Lands at 41 Mullavilly Road adjacent to and East of 38 and 39 Laurel heights East of 39 and 48 Laurel Drive West of 1-11 Rose Gardens and to the South of 5 14 and 16 Mullavilly Green Access is to be between No's 5 and 16 Mullavilly Green Laurelvale/Mullavilly, Tandragee BT62 2NT
Discharge of condition 14 of LA08/2022/1173/O. Condition 14 states "No site works of any nature or development shall take place until a programme of archaeological work (POW) has been prepared by a qualified archaeologist, submitted by the applicant and approved in writing by the Council in consultation with Historic Environment Division, Department for Communities. The POW shall provide for: The identification and evaluation of archaeological remains within the site; Mitigation of the impacts of development through licensed excavation recording or by preservation of remains in-situ; Post-excavation analysis sufficient to prepare an archaeological report, to publication standard if necessary; and Preparation of the digital, documentary and material archive for deposition. Reason: to ensure that archaeological remains within the application site are properly identified, and protected or appropriately recorded."
-
LA08/2026/0610/DC Decided
45 High Street, Lurgan, BT66 8AH
Discharge of condition 04 of LA08/2022/0819/LBC which reads: No work shall commence on the works until samples of all finish materials have been submitted to and agreed in writing with the Council in conjunction with HED and all works shall conform to the agreed samples. This includes, glazing, frames, roof finishes, rain water goods. Samples to be retained on site until completion of the works.
-
LA08/2026/0535/DC Decided
Lands 52m north-west of nos. 48-50 Killycomain Road, 40m sout-east of nos. 26-32 Bachelors Avenue, 44m south of 16 and 18 Bachelors Avenue, Portadown (with access onto Killycomain Road)
Discharge of condition 34 of LA08/2023/2031/F which reads: No development shall take place until a Wastewater Impact Assessment has been submitted to and approved in writing by the Council, in consultation with NI Water, with the Wastewater Impact Assessment demonstrating that the development can be served by the public sewerage system or that acceptable alternative provision for disposal of sewerage has been made. Any mitigation measures contained therein shall be implemented prior to the commencement of the development herby permitted, or in accordance with a programme to be submitted to and agreed in writing with the Council.
-
LA08/2026/0504/DC Decided
90 Collegelands Road, Charlemont, Dungannon BT71 6SW and lands to the Southeast
Discharge of Condition number: 10 of LA08/2021/1346/F which reads: No development shall take place on-site until final details of the method of sewage disposal has been submitted to and agreed in writing by the Council and any mitigation measures contained therein shall be implemented prior to the occupation of any part of the development.