Existing Beinn Ghlas Wind Farm Taynuilt Argyll And Bute PA35 1HY

Granted Argyll and Bute 25/01240/PP

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Erection of 7 turbines (up to 149.9m to tip) and ancillary development and decommissioning of existing Beinn Ghlas wind farm.

As published by the council, reference 25/01240/PP

Application record

Reference
25/01240/PP
Status
Decided
Decision
Granted As published: Application Approved
Received
25 Jul 2025
Validated
27 Aug 2025
Decided
16 Sep 2026
Ward
Oban North And Lorn
Parish
Taynuilt Community Council
Postcode
PA35 1HY

Timeline

Dates from the published record

  1. 25 Jul 2025

    Received by Argyll and Bute

  2. 27 Aug 2025

    Validated

    Checked as complete and ready for consideration.

  3. 5 Aug 2026

    Added to PlanIndex

  4. 16 Sep 2026

    Decision issued: Application Approved

  5. 16 Sep 2026

    Status changed to Decided

    Previously Awaiting decision.

Documents

Plans, drawings, consultee responses and the officer's report

Documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Watch members (£5 a month) open the document list from here.

Open the documents

What this grant of permission means

Argyll and Bute granted permission on 16 September 2026, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About this record

The published feed does not state which type of application this is; the register entry on Argyll and Bute's portal will say. Our guide explains the common types.