Cruachan Power Station Lochawe Dalmally Argyll And Bute PA33 1AN
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Alterations to turbine hall (subterranean level) relating to the replacement of Units 3 and 4
As published by the council, reference 23/00090/LIB
Application record
- Reference
- 23/00090/LIB
- Type
- Application for Listed Building Consent
- Status
- Decided
- Decision
- Granted As published: Application Approved
- Received
- 24 Jan 2023
- Validated
- 8 Mar 2023
- Decided
- 27 Apr 2023
- Ward
- Oban North And Lorn
- Parish
- Glenorchy And Inishail Community Council
- Decision by
- Local Delegated Decision
- Postcode
- PA33 1AN
Site history
Applications at this address on the Argyll and Bute register
This site has had 5 applications since 2022: 3 approved, 1 refused.
-
23/00353/S36 Granted
Cruachan Power Station Lochawe Dalmally Argyll And Bute PA33 1AN
Section 36 for upgrading works at Cruachan Power Station
-
22/02598/LIB Granted
Cruachan Power Station Lochawe Dalmally Argyll And Bute PA33 1AN
Proposed alterations to hydro-electric power station turbine hall including formation of two new access tunnels, connecting the existing turbine hall and access tunnel to the proposed new turbine hall and access tunnel at Cruachan 2
-
22/01221/S36 Refused
Cruachan Power Station Lochawe Dalmally Argyll And Bute PA33 1AN
Construction and operation of the Cruachan expansion project
-
22/00531/SCOPE Decided
Cruachan Power Station Lochawe Dalmally Argyll And Bute PA33 1AN
Scoping Opinion for development of new underground power station and associated infrastructure
Timeline
Dates from the published record
-
24 Jan 2023
Received by Argyll and Bute
-
8 Mar 2023
Validated
Checked as complete and ready for consideration.
-
27 Apr 2023
Decision issued: Application Approved
-
6 Sep 2026
Added to PlanIndex
Documents
Plans, drawings, consultee responses and the officer's report
24 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat this grant of permission means
Argyll and Bute granted permission on 27 April 2023, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About heritage and listed building applications
Listed building consent is needed for works that affect the special interest of a listed building, and carrying out such works without it is a criminal offence. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
Cruachan Power Station Lochawe Dalmally Argyll And Bute PA33 1AN
Proposed alterations to hydro-electric power station turbine hall including formation of two new access tunnels, connecting the existing turbine hall and access tunnel to the proposed new turbine hall and access tunnel at Cruachan 2
Granted Heritage and listed buildings 31 docs -
Cruachan Power Station Lochawe Argyll And Bute PA33 1AN
Alterations to existing control block access to form new upgraded security doors at the west, central and east stairs. Replacement/upgrade of all existing fire doors. Alterations to replace existing protective barriers in machine hall and at lighting gantry to meet current safety requirements
Granted Heritage and listed buildings
Other heritage and listed building applications
In Argyll and Bute
-
26/01533/LIB Awaiting decision
41 Colquhoun Street Helensburgh Argyll And Bute G84 9JW
Installation of replacement windows and back door
-
26/01477/LIB Awaiting decision
Bloomhill House Carman Road Cardross Argyll And Bute G82 5LA
Alterations to listed building consent application reference 25/00285/LIB (Demolition of sections of care home and erection of extension to form 2 duplex apartments and associated works) comprising reduction of overall height, marginal increase in external wall width, slight reduction in roof pitch to ensure the finished ridge height is no higher than unit 5 and increase in size of new apartments by 1200mmm to the rear
-
25/01691/LIB Granted
Trinity Church 26 Castle Street Rothesay Isle Of Bute Argyll And Bute PA20 9HA
Conversion of existing church and church hall to form family entertainment activity centre including erection of single storey link extension
-
26/00158/LIB Withdrawn
Barcaldine Castle Benderloch Argyll And Bute PA37 1SA
Installation of standing stones and associated works including engineering operations (part retrospective)
-
26/01405/LIB Awaiting decision
Woodcote Pier Road Rhu Argyll And Bute G84 8LJ
Renewal of listed building consent reference 23/01260/LIB (Replacement of existing windows, doors, and rooflights; alterations to kitchen window to form door; replacement of slate roof tiling, rainwater goods and formation of plat and steps)