Planning application
Approximately 4 Km South West Of Inveraray, 300M West Of Douglas Water And Upslope Of The Existing An Suidhe Substation Inveraray Argyll And Bute
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Erection of high voltage electricity substation and formation of associated access, landscaping, drainage and means of enclosure
As published by the council, reference 22/02479/PP
Application record
- Reference
- 22/02479/PP
- Type
- Planning Permission
- Status
- Decided
- Decision
- Granted As published: Application Approved
- Received
- 7 Dec 2022
- Validated
- 13 Jan 2023
- Decided
- 24 May 2023
- Ward
- Mid Argyll
- Parish
- Inveraray Community Council
- Decision by
- Major Committee Decision
Timeline
Dates from the published record
-
7 Dec 2022
Received by Argyll and Bute
-
13 Jan 2023
Validated
Checked as complete and ready for consideration.
-
24 May 2023
Decision issued: Application Approved
-
2 Oct 2026
Added to PlanIndex
Documents
Plans, drawings, consultee responses and the officer's report
97 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat this grant of permission means
Argyll and Bute granted permission on 24 May 2023, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About full applications
A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
An Suidhe Windfarm Inveraray Argyll And Bute
Install and keep installed approximately 1.34km of realigned 275kV overhead line supported on 6 new steel towers to connect the proposed An Suidhe Substation via downleads to the existing 275kV Inveraray to Crossaig overhead line
Granted Outline 63 docs -
-
Woodland North East Of Auchindrain Furnace Argyll And Bute
Amendment to Land Management Plan
Decided Outline 7 docs
Other full applications
In Argyll and Bute
-
26/01070/PP Granted
MacLeod Construction Kilmory Industrial Estate Lochgilphead Argyll And Bute PA31 8RR
Formation of accessible access to existing offices, removal of existing stepped entrance and internal alterations to form accessible toilet, kitchen, and private office space
-
26/01578/PP Awaiting decision
Achavit Dunmore Argyll And Bute PA29 6XZ
Erection of extension to dwellinghouse
-
26/00695/PP Granted
Land At Alt An T-Seilich The Oa Isle Of Islay Argyll And Bute
Installation of 4 glamping pods, new borehole and installation of package sewage treatment plant
-
26/01551/PP Awaiting decision
Land Approx 640 Metres West Of Dererach Pennyghael Isle Of Mull Argyll And Bute
Formation of hardstanding for timber stacking and relocation of rock to form small causeway and interface with floating linkspan and barge
-
26/01548/PP Awaiting decision
Ashfield Bungalow Achnamara Argyll And Bute PA31 8PT
Erection of annexe for underground cellar and bar area, double garage and storage buildings and connecting pergola