Planning application
Offices Scottish Association For Marine Science Dunbeg Oban Argyll And Bute PA37 1QA
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Installation of solar PV array on south facing roof
As published by the council, reference 21/00463/PP
Application record
- Reference
- 21/00463/PP
- Type
- Planning Permission
- Status
- Decided
- Decision
- Granted As published: Application Approved
- Received
- 4 Mar 2021
- Validated
- 4 May 2021
- Decided
- 30 Jun 2021
- Ward
- Oban North And Lorn
- Parish
- Dunbeg Community Council
- Decision by
- Local Delegated Decision
- Postcode
- PA37 1QA
Timeline
Dates from the published record
-
4 Mar 2021
Received by Argyll and Bute
-
4 May 2021
Validated
Checked as complete and ready for consideration.
-
30 Jun 2021
Decision issued: Application Approved
-
2 Oct 2026
Added to PlanIndex
Documents
Plans, drawings, consultee responses and the officer's report
19 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat this grant of permission means
Argyll and Bute granted permission on 30 June 2021, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About full applications
A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
Offices Scottish Association For Marine Science Dunbeg Argyll And Bute PA37 1QA
Erection of small louvred external plant enclosure to house replacement plant room chillers, with power connection from plant equipment within the closure to the existing internal plant room utilising the existing service routes
Decided -
Sheina Marshall Building Scottish Marine Institute Dunstaffnage Dunbeg Oban Argyll And Bute PA37 1QA
Installation of roof mounted solar panels
Granted Full applications 13 docs -
European Marine Science Park Dunstaffnage By Oban PA37 1QA
Erection of 2 non illuminated pole mounted signs
Granted Advertising 18 docs -
Kirk Road Dunbeg Argyll And Bute
Install fixed line broadband electronic communications apparatus under Regulation 5
Withdrawn Telecoms -
Dunstaffnage Castle Dunbeg Oban Argyll And Bute PA37 1PZ
Removal of existing septic tank and soakaway and replacement with biodisc treatment plant with UV disinfection unit
Granted Full applications 15 docs -
Dunstaffnage Castle Dunbeg Oban Argyll And Bute PA37 1PZ
Provision of 2 freestanding temporary toilet cubicles (retrospective)
Granted Full applications 10 docs
Other full applications
In Argyll and Bute
-
26/01070/PP Granted
MacLeod Construction Kilmory Industrial Estate Lochgilphead Argyll And Bute PA31 8RR
Formation of accessible access to existing offices, removal of existing stepped entrance and internal alterations to form accessible toilet, kitchen, and private office space
-
26/01578/PP Awaiting decision
Achavit Dunmore Argyll And Bute PA29 6XZ
Erection of extension to dwellinghouse
-
26/00695/PP Granted
Land At Alt An T-Seilich The Oa Isle Of Islay Argyll And Bute
Installation of 4 glamping pods, new borehole and installation of package sewage treatment plant
-
26/01551/PP Awaiting decision
Land Approx 640 Metres West Of Dererach Pennyghael Isle Of Mull Argyll And Bute
Formation of hardstanding for timber stacking and relocation of rock to form small causeway and interface with floating linkspan and barge
-
26/01548/PP Awaiting decision
Ashfield Bungalow Achnamara Argyll And Bute PA31 8PT
Erection of annexe for underground cellar and bar area, double garage and storage buildings and connecting pergola