Planning application
Anemometer Mast Capull Cloiche Land South West Of Lochan Anama And North East Of A'Cruach Windfarm 6km East Of Kilmartin Argyll And Bute
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Erection of temporary wind monitoring meteorological mast of up to 100m in height for a period of 24 months (2 years)
As published by the council, reference 21/00093/PP
Application record
- Reference
- 21/00093/PP
- Type
- Planning Permission
- Status
- Decided
- Decision
- Granted As published: Application Approved
- Received
- 19 Jan 2021
- Validated
- 19 Feb 2021
- Decided
- 25 Jun 2021
- Ward
- Mid Argyll
- Parish
- Dunadd Community Council
- Decision by
- Local Delegated Decision
Timeline
Dates from the published record
-
19 Jan 2021
Received by Argyll and Bute
-
19 Feb 2021
Validated
Checked as complete and ready for consideration.
-
25 Jun 2021
Decision issued: Application Approved
-
5 Aug 2026
Added to PlanIndex
Documents
Plans, drawings, consultee responses and the officer's report
20 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat this grant of permission means
Argyll and Bute granted permission on 25 June 2021, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About full applications
A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
Glasvaar Anemometer Mast Ford Argyll And Bute
Erection of temporary meteorological mast of up to 100m in height for a period of 5 years
Granted Full applications -
Land East Of Kilmartin And North East Of Lochgilphead Argyll And Bute
Application under Section 42 of the Town and Country Planning (Scotland) Act 1997 to vary the Standard Time Condition Limit of application reference 22/01380/PP from three years to ten years to allow for completion of grid connection works to connect the wind farm
Granted Full applications
Other full applications
In Argyll and Bute
-
26/01070/PP Granted
MacLeod Construction Kilmory Industrial Estate Lochgilphead Argyll And Bute PA31 8RR
Formation of accessible access to existing offices, removal of existing stepped entrance and internal alterations to form accessible toilet, kitchen, and private office space
-
26/01578/PP Awaiting decision
Achavit Dunmore Argyll And Bute PA29 6XZ
Erection of extension to dwellinghouse
-
26/00695/PP Granted
Land At Alt An T-Seilich The Oa Isle Of Islay Argyll And Bute
Installation of 4 glamping pods, new borehole and installation of package sewage treatment plant
-
26/01551/PP Awaiting decision
Land Approx 640 Metres West Of Dererach Pennyghael Isle Of Mull Argyll And Bute
Formation of hardstanding for timber stacking and relocation of rock to form small causeway and interface with floating linkspan and barge
-
26/01548/PP Awaiting decision
Ashfield Bungalow Achnamara Argyll And Bute PA31 8PT
Erection of annexe for underground cellar and bar area, double garage and storage buildings and connecting pergola