Creag Dhubh Windfarm Creag Dubh North East Of Strachur Village Argyll And Bute

Refused Argyll and Bute 19/02544/PP Planning Permission

Refused. Only the applicant can appeal, within the statutory time limit, and a revised scheme can be submitted instead.

Proposal

Construction of wind farm comprising of 9 wind turbines (maximum blade tip height 145m), formation of 5.6km new access track, erection of substation building, welfare building, temporary construction compound and 2 borrow pits

As published by the council, reference 19/02544/PP

Application record

Reference
19/02544/PP
Type
Planning Permission
Status
Decided
Decision
Refused As published: Refuse
Received
5 Dec 2019
Validated
22 Jan 2020
Decided
1 Mar 2022
Ward
Cowal
Parish
Strachur Community Council
Decision by
Major Committee Decision

Site history

Applications at this address on the Argyll and Bute register

This site has had 3 applications since 2019: 1 approved, 1 refused.

  • 19/02544/DOC01 Granted

    Creag Dhubh Windfarm Creag Dubh North East Of Strachur Village Argyll And Bute

    Request to discharge conditions relative to application 19/02544/PP. Specifically conditions 7,9,16,17 and 19

    Decided 6 Nov 2025 Conditions
  • 24/01869/PP Withdrawn

    Creag Dhubh Windfarm Creag Dubh North East Of Strachur Village Argyll And Bute

    Section 42 application to planning permission 19/02544/PP (Construction of wind farm comprising of 9 wind turbines (maximum blade tip height 145m), formation of 5.6km new access track, erection of substation building, welfare building, temporary construction compound and 2 borrow pits) to vary condition 2 of appeal decision (case reference PPA-130-2084) to extend the commencement of development deadline by 3 years to 07/11/2028

    Decided 13 Mar 2025 Full applications

Timeline

Dates from the published record

  1. 5 Dec 2019

    Received by Argyll and Bute

  2. 22 Jan 2020

    Validated

    Checked as complete and ready for consideration.

  3. 1 Mar 2022

    Decision issued: Refuse

  4. 19 Sep 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

257 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Watch members (£5 a month) open the document list from here.

Open the documents

What this refusal means

Argyll and Bute refused this application for the reasons on the decision notice; only the applicant can appeal, and refused schemes often return in revised form. More in our guide to what happens after a planning decision.

About full applications

A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.

Nearby applications

Within 0.3 miles

  • Creag Dhubh Windfarm Creag Dubh North East Of Strachur Village Argyll And Bute

    24/01869/PP Submitted 14 Oct 2024 400 yards away

    Section 42 application to planning permission 19/02544/PP (Construction of wind farm comprising of 9 wind turbines (maximum blade tip height 145m), formation of 5.6km new access track, erection of substation building, welfare building, temporary construction compound and 2 borrow pits) to vary condition 2 of appeal decision (case reference PPA-130-2084) to extend the commencement of development deadline by 3 years to 07/11/2028

    Withdrawn Full applications 52 docs
  • Creag Dhubh Windfarm Creag Dubh North East Of Strachur Village Argyll And Bute

    19/02544/DOC01 Submitted 28 Oct 2025 0.3 miles away

    Request to discharge conditions relative to application 19/02544/PP. Specifically conditions 7,9,16,17 and 19

    Granted Conditions

In Argyll and Bute

  • 26/01578/PP Awaiting decision

    Achavit Dunmore Argyll And Bute PA29 6XZ

    Erection of extension to dwellinghouse

    9 Sep 2026 Full applications
  • 26/00695/PP Granted

    Land At Alt An T-Seilich The Oa Isle Of Islay Argyll And Bute

    Installation of 4 glamping pods, new borehole and installation of package sewage treatment plant

    Received 27 Apr, published by the council 28 Jul 2026 Full applications
  • 26/01551/PP Awaiting decision

    Land Approx 640 Metres West Of Dererach Pennyghael Isle Of Mull Argyll And Bute

    Formation of hardstanding for timber stacking and relocation of rock to form small causeway and interface with floating linkspan and barge

    Received 3 Sep, published by the council 8 Sep 2026 Full applications
  • 26/01548/PP Awaiting decision

    Ashfield Bungalow Achnamara Argyll And Bute PA31 8PT

    Erection of annexe for underground cellar and bar area, double garage and storage buildings and connecting pergola

    Received 3 Sep, published by the council 9 Sep 2026 Full applications
  • 25/01665/PP Withdrawn

    Land East Of Former Gunpowder Store Kames Argyll And Bute

    Erection of dwellinghouse and shed. Installation of septic tank and soakaway and formation of access track

    Received 7 Oct, published by the council 28 Jul 2026 Full applications