Planning application
Aspen Offshore Wind Farm (Onshore Infrastructure) Land At Craig Stirling North, North East And North West Of Newtonhill Connecting To Fetteresso Forest Aberdeenshire
Decided. The decision notice on the council portal carries the outcome in full, including any conditions.
Proposal
Onshore Transmission Infrastructure for Aspen Offshore Wind Farm Including Installation of Electrical Cables, Erection of Substation and Associated Infrastructure to Connect to the National Electricity Transmission System
As published by the council, reference ENQ/2026/0739
Application record
- Reference
- ENQ/2026/0739
- Type
- Proposal of Application Notice
- Status
- Decided
- Decision
- PAC Agreed as Specified in Notice
- Received
- 30 Apr 2026
- Validated
- 30 Apr 2026
- Decided
- 28 May 2026
- Ward
- Stonehaven And Lower Deeside
- Parish
- Newtonhill, Muchalls & Cammachmore
- Decision by
- Delegated
Timeline
Dates from the published record
-
30 Apr 2026
Received by Aberdeenshire
-
28 May 2026
Decision issued: PAC Agreed as Specified in Notice
-
28 Jul 2026
Added to PlanIndex
Documents
Plans, drawings, consultee responses and the officer's report
4 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Trade members open them from here.
Open the documentsAfter the decision
Aberdeenshire has decided this application; the outcome above is the register's own wording and the decision notice on the council portal carries the detail. More in our guide to what happens after a planning decision.
About this record