Planning application
Land At Shielhill St Fergus Aberdeenshire AB42 3HQ
Decided. The decision notice on the council portal carries the outcome in full, including any conditions.
Proposal
Grid Connected Battery Energy Storage Facility by St Fergus Grid Substation Including Array of Containerised Batteries, Power Converters and Transformers, Access Track, Transmission Compound, Switchgear, Control Building, Stores, Fencing, Security, Landscaping, Water Tanks, Parking and Ancillary Structures
As published by the council, reference ENQ/2022/0396
Application record
- Reference
- ENQ/2022/0396
- Type
- Proposal of Application Notice
- Status
- Decided
- Decision
- PAC Agreed as Specified in Notice
- Received
- 17 Mar 2022
- Validated
- 17 Mar 2022
- Decided
- 21 Mar 2025
- Ward
- Peterhead North And Rattray
- Parish
- Buchan East
- Decision by
- Delegated
- Postcode
- AB42 3HQ
Timeline
Dates from the published record
-
17 Mar 2022
Received by Aberdeenshire
-
21 Mar 2025
Decision issued: PAC Agreed as Specified in Notice
-
15 Sep 2026
Added to PlanIndex
Documents
Plans, drawings, consultee responses and the officer's report
2 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsAfter the decision
Aberdeenshire has decided this application; the outcome above is the register's own wording and the decision notice on the council portal carries the detail. More in our guide to what happens after a planning decision.
About this record
The published feed does not state which type of application this is; the register entry on Aberdeenshire's portal will say. Our guide explains the common types.
Nearby applications
Within 0.3 miles
-
Tamanaru Shielhill Pitbirn St Fergus Peterhead Aberdeenshire AB42 3HQ
Extensions to Dwellinghouse
Granted Full applications Extension 15 docsDomestic