Granted Aberdeenshire APP/2026/0804 Certificate of Lawful Use

Relates to APP/2023/0193

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Confirmation Existing Planning Permission APP/2023/0193 Formation of 45MW Battery Energy Storage System Compound, Siting of Substations, Erection of Security Fencing, CCTV, Formation of Vehicular Access and Associated Infrastructure

As published by the council, reference APP/2026/0804

Application record

Reference
APP/2026/0804
Type
Certificate of Lawful Use
Status
Decided
Decision
Granted As published: Approved
Received
13 May 2026
Validated
19 May 2026
Decided
15 Jun 2026
Ward
Fraserburgh And District
Parish
Rathen, Memsie & District
Decision by
Delegated

Site history

Applications at this address on the Aberdeenshire register

This site has had 4 applications since 2022: 2 approved, 0 refused.

  • APP/2026/1589 Awaiting decision

    Land East Of A981 Fraserburgh Aberdeenshire

    Erection of Welfare Building, Switch Gear Building and Installation of 7 Kiosks and Associated Drainage Infrastructure

    Submitted 21 Sep 2026
  • APP/2023/0193 Granted

    Land East Of A981 Fraserburgh Aberdeenshire

    Formation of 45MW Battery Energy Storage System Compound, Siting of Substations, Erection of Security Fencing, CCTV, Formation of Vehicular Access and Associated Infrastructure

    Decided 13 Apr 2023 Full applications
  • ENQ/2022/1698 Decided

    Land East Of A981 Fraserburgh Aberdeenshire

    Formation of 45MW Battery Energy Storage Compound and Associated Infrastructure

    Decided 25 Nov 2022

Timeline

Dates from the published record

  1. 13 May 2026

    Received by Aberdeenshire

  2. 19 May 2026

    Validated

    Checked as complete and ready for consideration.

  3. 15 Jun 2026

    Decision issued: Approved

  4. 28 Jul 2026

    Added to PlanIndex

Cases linked to this one on the register

  • APP/2023/0193 Granted

    Land East Of A981 Fraserburgh Aberdeenshire

    Formation of 45MW Battery Energy Storage System Compound, Siting of Substations, Erection of Security Fencing, CCTV, Formation of Vehicular Access and Associated Infrastructure

    Decided 13 Apr 2023 Full applications

Documents

Plans, drawings, consultee responses and the officer's report

7 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Watch members (£5 a month) open the document list from here.

Open the documents

What this grant of permission means

Aberdeenshire granted permission on 15 June 2026, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About lawful development applications

A lawful development certificate is a legal determination that existing or proposed works do not need planning permission; the merits of the scheme are not considered. More in our guide to planning application types.

In Aberdeenshire

  • APP/2026/1316 Granted

    Jockston House Ardoe Aberdeenshire AB12 5XT

    Use as Domestic Garden Ground

    Received 30 Jul, published by the council 5 Aug 2026 Lawful development
  • APP/2026/0844 Granted

    13 Irvinemuir Park Drumoak AB31 5BF

    Alterations And Extension To Dwellinghouse

    Received 18 May, published by the council 28 Jul 2026 Lawful development
  • APP/2026/0698 Refused

    Greenheads Hatton AB42 0RE

    Existing - Increase in Number of Stances and Change of Layout of Caravan Site

    Received 24 Apr, published by the council 28 Jul 2026 Lawful development
  • APP/2026/0865 Granted

    37 St Machar Avenue Aboyne Aberdeenshire AB34 5FH

    Alterations and Extension to Dwellinghouse

    Received 20 May, published by the council 28 Jul 2026 Lawful development
  • APP/2026/0621 Granted

    Lower Drumbulg Gartly Huntly AB54 4SB

    Erection of Ancillary Accommodation