Planning application
Land From North Of Peterhead To South Of New Deer Green Volt Offshore Windfarm Aberdeenshire
Relates to APP/2023/1454
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Discharge of Conditions 2(ii) (Decommissioning, Restoration and Aftercare Strategy) and 19 (Archaeological Scheme of Investigation) for Previously Approved APP/2023/1454 for National for Formation of Onshore Landfall Point, Laying of Underground Cable and Erection of Substation
As published by the council, reference APP/2025/1791
Application record
- Reference
- APP/2025/1791
- Type
- Discharge of Conditions - Std
- Status
- Decided
- Decision
- Granted As published: Approved
- Received
- 31 Oct 2025
- Validated
- 20 Nov 2025
- Decided
- 19 Jan 2026
- Ward
- Central Buchan
- Parish
- Peterhead
- Decision by
- Delegated
Site history
Applications at this address on the Aberdeenshire register
This site has had 2 applications since 2023: 2 approved, 0 refused.
-
APP/2023/1454 Granted
Land From North Of Peterhead To South Of New Deer Green Volt Offshore Windfarm Aberdeenshire
National for Formation of Onshore Landfall Point, Laying of Underground Cable and Erection of Substation
Timeline
Dates from the published record
-
31 Oct 2025
Received by Aberdeenshire
-
20 Nov 2025
Validated
Checked as complete and ready for consideration.
-
19 Jan 2026
Decision issued: Approved
-
28 Jul 2026
Added to PlanIndex
Related applications
Cases linked to this one on the register
-
APP/2023/1454 Granted
Land From North Of Peterhead To South Of New Deer Green Volt Offshore Windfarm Aberdeenshire
National for Formation of Onshore Landfall Point, Laying of Underground Cable and Erection of Substation
What this grant of permission means
Aberdeenshire granted permission on 19 January 2026, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About condition discharge and variation applications
This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
Land From North Of Peterhead To South Of New Deer Green Volt Offshore Windfarm Aberdeenshire
National for Formation of Onshore Landfall Point, Laying of Underground Cable and Erection of Substation
Granted Full applications 220 docs
Other condition discharge and variation applications
In Aberdeenshire
-
APP/2026/1059 Granted
Plots 26 & 27 Queen Elizabeth Drive South Of Pheppie Burn Chapelton Stonehaven
Condition 3J (Layout, Siting, Design and Finish) of Planning Permission in Principle Reference APP/2011/3100 for New Settlement Comprising Residential (Up to 4045 Dwellinghouses), Commercial, Retail and Community Facilities with Associated Landscaping, Open Space, Drainage and Roads Infrastructure and Services
-
APP/2026/0959 Granted
Land At Backhill Lenabo Kinknockie Mintlaw Aberdeenshire AB42 5BA
Condition 2(a) Layout, Siting, (b) External Appearance, Finishing Materials, (c) Landscaping, (d) Levels, Cross Sections, Finished Floor Levels, (e) Drainage, (f) Means of Access, Visibility Splays, (g) Car Parking, Vehicle Turning Area, (h) Biodiversity Enhancement Plan of Planning Permission Reference APP/2024/0870 for Erection of Dwellinghouse
-
APP/2026/1097 Granted
Stables At Glencommon Farm Bridge Of Canny Banchory AB31 4FN
Condition 2a (Layout & Siting), 2b (External Appearance), 2c (Levels), 2d (Disposal of Foul & Surface Water), 2e (Visibility Splays), 2f (Parking/Vehicle Turning Area/Lay-by), 2g (Refuse Uplift), 2h (Biodiversity & Habitat Enhancement) of Planning Permission in Principle Reference APP/2024/1247 for Erection of Dwellinghouse
-
APP/2026/1341 Awaiting decision
Kirkton Heights Phase 2 Development Boothby Road Fraserburgh Aberdeenshire
Discharge of Planning Obligation (Waste and Recylcing) of APP/2025/1683 for Erection of 175 Dwellinghouses and Associated Infrastructure
-
APP/2026/1340 Awaiting decision
Kirkton Heights Phase 2 Development Boothby Road Fraserburgh Aberdeenshire
Discharge of Planning Obligation (Sports and Recreation) of APP/2025/1683 for Erection of 175 Dwellinghouses and Associated Infrastructure