Land To The South Of Bogfern Farm Cushnie Alford

Granted Aberdeenshire APP/2024/0201 Application under Section 42

Relates to APP/2021/0936

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Variation of Condition 11 (Noise) of Planning Permisison APP/2021/0936 Erection of Battery Storage Units, Inverters and Transformers, DNO Substation, Client Switchgear Container, Security Columns including Landscaping (Renewal of Planning Permission APP/2018/2702)

As published by the council, reference APP/2024/0201

Application record

Reference
APP/2024/0201
Type
Application under Section 42
Status
Decided
Decision
Granted As published: Approved
Received
12 Feb 2024
Validated
12 Feb 2024
Decided
26 Nov 2025
Ward
Huntly, Strathbogie And Howe Of Alford
Parish
Donside
Decision by
Local Member Delegated

Site history

Applications at this address on the Aberdeenshire register

This site has had 2 applications since 2021: 2 approved, 0 refused.

  • APP/2021/0936 Granted

    Land To The South Of Bogfern Farm Cushnie Alford

    Erection of Battery Storage Units, Inverters and Transformers, DNO Substation, Client Switchgear Container, Security Columns including Landscaping (Renewal of Planning Permission APP/2018/2702)

    Decided 29 Jun 2021 Full applications

Timeline

Dates from the published record

  1. 12 Feb 2024

    Received by Aberdeenshire

  2. 26 Nov 2025

    Decision issued: Approved

  3. 1 Sep 2026

    Added to PlanIndex

Cases linked to this one on the register

  • APP/2021/0936 Granted

    Land To The South Of Bogfern Farm Cushnie Alford

    Erection of Battery Storage Units, Inverters and Transformers, DNO Substation, Client Switchgear Container, Security Columns including Landscaping (Renewal of Planning Permission APP/2018/2702)

    Decided 29 Jun 2021 Full applications

Documents

Plans, drawings, consultee responses and the officer's report

27 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Watch members (£5 a month) open the document list from here.

Open the documents

What this grant of permission means

Aberdeenshire granted permission on 26 November 2025, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About this record

The published feed does not state which type of application this is; the register entry on Aberdeenshire's portal will say. Our guide explains the common types.

Nearby applications

Within 0.3 miles

  • Land To The South Of Bogfern Farm Cushnie Alford

    APP/2021/0936 Submitted 23 Apr 2021 50 yards away

    Erection of Battery Storage Units, Inverters and Transformers, DNO Substation, Client Switchgear Container, Security Columns including Landscaping (Renewal of Planning Permission APP/2018/2702)

    Granted Full applications 16 docs
  • Westfield Cushnie Alford Aberdeenshire AB33 8LP

    APP/2022/1460 Submitted 1 Jul 2022 150 yards away

    Alterations and Extension to Steading to form Dwellinghouse (Holiday Let)

    Granted Full applications Extension 20 docs
    Domestic
  • Cauldhame Cushnie Alford Aberdeenshire AB33 8LP

    APP/2022/1530 Submitted 11 Jul 2022 200 yards away

    Erection of Agricultural Building

    Granted Prior approval 7 docs