Planning application
Land To The North Of Smiddyhill Strichen Fraserburgh
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Application for Installation of 25MW Energy Storage Compound and CCTV, Formation of Access Road and Erection of 3m High Fencing Without Compliance with Condition 1 (Cessation Date) of Full Planning Permission Reference APP/2018/0526
As published by the council, reference APP/2022/2112
Application record
- Reference
- APP/2022/2112
- Type
- Application under Section 42
- Status
- Decided
- Decision
- Approved
- Received
- 4 Oct 2022
- Validated
- 11 Oct 2022
- Decided
- 16 Feb 2023
- Ward
- Central Buchan
- Parish
- Strichen & District
- Decision by
- Delegated
Timeline
Dates from the published record
-
4 Oct 2022
Received by Aberdeenshire
-
11 Oct 2022
Validated
Checked as complete and ready for consideration.
-
16 Feb 2023
Decision issued: Approved
-
22 Aug 2026
Added to PlanIndex
Documents
Plans, drawings, consultee responses and the officer's report
14 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Trade members open them from here.
Open the documentsWhat this grant of permission means
Aberdeenshire granted permission on 16 February 2023, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About this record
The published feed does not state which type of application this is; the register entry on Aberdeenshire's portal will say. Our guide explains the common types.
Nearby applications
Within 500 metres
-
Site To North Of Smiddyhill Strichen Fraserburgh
Installation of a 49.9MWh Battery Energy Storage System (BESS) and Associated Infrastructure
Decided -
Site To North Of Smiddyhill Strichen Fraserburgh Aberdeenshire
Installation of a Battery Energy Storage System and Associated Infrastructure
Decided 2 docs -
North East Of Smiddyhill Strichen Fraserburgh
Installation of 49.9MWh Battery Energy Storage System (BESS), Substation and Associated Works
Decided Outline