Site Adjacent To Greenbank Caravan And Trailers Hillhead Of Phingask Fraserburgh

Granted Aberdeenshire APP/2022/1988 Full Planning Permission

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Formation of Grid Battery Energy Storage Facility (up to 50MW) Siting of Substations, Welfare Facility, Erection of Security Fencing, CCTV, Floodlighting, Formation of Access, SUDS Basin and Associated Infrastructure

As published by the council, reference APP/2022/1988

Application record

Reference
APP/2022/1988
Type
Full Planning Permission
Status
Decided
Decision
Granted As published: Approved
Received
16 Sep 2022
Validated
30 Sep 2022
Decided
30 Jan 2023
Ward
Fraserburgh And District
Parish
Rathen, Memsie & District
Decision by
Committee

Timeline

Dates from the published record

  1. 16 Sep 2022

    Received by Aberdeenshire

  2. 30 Sep 2022

    Validated

    Checked as complete and ready for consideration.

  3. 30 Jan 2023

    Decision issued: Approved

  4. 22 Aug 2026

    Added to PlanIndex

Cases linked to this one on the register

2 later applications on the register refer to this one:

  • APP/2025/1767 Granted

    Site Adjacent To Greenbank Caravan And Trailers Hillhead Of Phingask Fraserburgh Aberdeenshire

    Formation of Grid Battery Energy Storage Facility (up to 50MW) Siting of Substations, Welfare Facility, Erection of Security Fencing, CCTV, Floodlighting, Formation of Access, SUDS Basin and Associated Infrastructure without Compliance with Condition 1 (Time Condition) of Planning Permission Reference APP/2022/1988

    Decided 19 Feb 2026
  • APP/2025/1717 Withdrawn

    Site Adjacent To Greenbank Caravan And Trailers Hillhead Of Phingask Fraserburgh Aberdeenshire

    Formation of Grid Battery Energy Storage Facility (up to 50MW) Siting of Substations, Welfare Facility, Erection of Security Fencing, CCTV, Floodlighting, Formation of Access, SUDS Basin and Associated Infrastructure without Compliance with Conditions 5 (Restoration Liabilities), 6 (Visibility Splays), 10 (Acoustic Specification) and 12 (Floodlighting) of Planning Permission Reference APP/2022/1988

    Decided 11 Dec 2025

Documents

Plans, drawings, consultee responses and the officer's report

50 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Watch members (£5 a month) open the document list from here.

Open the documents

What this grant of permission means

Aberdeenshire granted permission on 30 January 2023, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About full applications

A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.

Nearby applications

Within 0.3 miles

In Aberdeenshire

  • APP/2026/1621 Awaiting decision

    Base Station Tullich Invercauld Estate Pass Of Ballater Aberdeenshire

    Installation Of Generator

    Received 25 Sep, published by the council 2 Oct 2026 Full applications
  • APP/2026/1506 Awaiting decision

    Surfside Caravan Park Harbour Road Fraserburgh AB43 9TB

    Extension to Caravan Site Operating Times (March to January)

    Received 2 Sep, published by the council 3 Sep 2026 Full applications
  • APP/2026/1489 Awaiting decision

    3 Gean Court Balmedie AB23 8ST

    Extension to Dwellinghouse and Installation of Flue

    Received 31 Aug, published by the council 2 Sep 2026 Full applications
  • APP/2026/1494 Awaiting decision

    18 David Mclean Drive Alford Aberdeenshire AB33 8PW

    Erection of Garden Room (Retrospective)

    Received 31 Aug, published by the council 3 Sep 2026 Full applications
  • APP/2026/1476 Awaiting decision

    Huntly Hotel 18 The Square Huntly Aberdeenshire AB54 8BR

    Alterations to Hotel Including Replacement Doors

    Received 28 Aug, published by the council 3 Sep 2026 Full applications