Proposal
Condition 1 a) Layout, Siting and Design, b) External Appearance and Finishing Materials, c) Landscaping Scheme, d) Levels Survey and Cross Sections, e) Means of Disposal of Foul and Surface Water, f) Access, g) Car Parking/Vehicle Turning Area and h) Refuse Bin Uplift Store of Planning Permission in Principle Reference APP/2017/2319 for Erection of Dwellinghouse
As published by the council, reference APP/2020/2175
Application record
- Reference
- APP/2020/2175
- Type
- Approval of Matters Specified in Conds
- Status
- Decided
- Decision
- Approved
- Received
- 3 Nov 2020
- Validated
- 5 Nov 2020
- Decided
- 1 Mar 2021
- Ward
- Aboyne, Upper Deeside And Donside
- Parish
- Torphins
- Decision by
- Delegated
Timeline
Dates from the published record
-
3 Nov 2020
Received by Aberdeenshire
-
5 Nov 2020
Validated
Checked as complete and ready for consideration.
-
1 Mar 2021
Decision issued: Approved
-
5 Aug 2026
Added to PlanIndex
Documents
Plans, drawings, consultee responses and the officer's report
17 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Trade members open them from here.
Open the documentsWhat a grant of permission means
The process from here
Permission has been granted, usually subject to conditions listed on the decision notice, some of which must be discharged before work starts. The decision notice on the council portal sets out exactly what was approved.
Work must normally begin within three years of the decision or the permission lapses. Neighbours cannot appeal a grant; challenging one means judicial review of how the decision was made, within tight time limits.
About conditions applications
How this application type works
This type of application deals with conditions attached to an existing permission, either by supplying the details a condition requires, called discharging it, or by asking to vary or remove one. It does not reopen the principle of the permission itself. Building often cannot lawfully start, or continue past a set stage, until the named conditions are discharged.
Nearby applications
Within 500 metres
-
Haugh Head Torphins Aberdeenshire AB31 4NN
95% historically approved · decision due ~25 Sep
Alterations and Extension to Dwellinghouse Including Erection of Fence
Awaiting decision ExtensionSmall domestic
Other conditions applications
In Aberdeenshire
-
APP/2026/0311 Granted
Land At Mains Of Greens Cuminestown Aberdeenshire AB53 5YQ
Discharge of Conditions 7 (Habitat Management Plan), 21 (Site Investigation/Remediation Strategy) and 28 (Landscaping Scheme) of Planning Permission Reference APP/2024/1927 for National for Erection of 400kV AC Substation and Associated Infrastructure
-
APP/2026/0463 Granted
Land At Mains Of Greens Cuminestown Aberdeenshire AB53 5YQ
Discharge of Condition 23 (Private Water Supply) of Application Reference APP/2024/1927 for National for Erection of 400kV AC Substation and Associated Infrastructure
-
APP/2025/2024 Granted
Netherton Hub Land West Of Parkhills Farm Blackhills Peterhead
Discharge of Planning Conditions 3 (Demolition), 4 (Private Water), 7 (CTMP), 8 (CEMP) 12 (Schedule of Mitigation) and 13 (Socio-economic strategy) of Planning Permission Reference APP/2024/1714 for National for Erection of a Strategic Electricity Transmission Hub Including 400kV AC Substation, 132kV AC Substation, 2 HVDC Converter Stations, Transmission Hall, Spares Warehouse, Operations Base and Associated Works
-
APP/2026/0071 Granted
Netherton Hub Land West Of Parkhills Farm Blackhills Peterhead
Discharge of Planning Conditions 5 (Offsite Landscaping), 6 (PMO), 9 (ECoW), 10 (BEMP) and 11 (Archaeology) of Planning Permission Reference APP/2024/1714 for National for Erection of a Strategic Electricity Transmission Hub Including 400kV AC Substation, 132kV AC Substation, 2 HVDC Converter Stations, Transmission Hall, Spares Warehouse, Operations Base and Associated Works
-
APP/2025/1754 Granted
Netherton Hub Land West Of Parkhills Farm Blackhills Peterhead
Approval of Matters Specified in Conditions 2a)i, 2a)ii, 2a)iii, 2a)iv, 2a)v, 2a)vi, 2a)vii, 2a)viii, 2a)ix, 2a)x, 2a)xi, 2a)xii, 2a)xiii, 2a)xiv, 2a)xv and 2a)xvi (Lot 1 Civils) of Planning Permission ref: APP/2024/1714 for Erection of a Strategic Electricity Transmission Hub Including 400kV AC Substation, 132kV AC Substation, 2 HVDC Converter Stations, Transmission Hall, Spares Warehouse, Operations Base and Associated Works