Skip to content
PlanIndex Get alerts
Menu

Planning application

8 Denhead Crescent Potterton Aberdeenshire AB23 8UA

Granted Aberdeenshire APP/2020/1973 Full Planning Permission

Works: Extension Domestic

Read from the description, not a valuation. How we read the register

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Alterations and Extension to Dwellinghouse

As published by the council, reference APP/2020/1973

Application record

Reference
APP/2020/1973
Type
Full Planning Permission
Status
Decided
Decision
Granted As published: Approved
Received
8 Oct 2020
Validated
12 Oct 2020
Decided
27 Nov 2020
Ward
Mid-Formartine
Parish
Belhelvie
Decision by
Delegated
Postcode
AB23 8UA

Timeline

Dates from the published record

  1. 8 Oct 2020

    Received by Aberdeenshire

  2. 12 Oct 2020

    Validated

    Checked as complete and ready for consideration.

  3. 27 Nov 2020

    Decision issued: Approved

  4. 5 Oct 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

8 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Watch members (£5 a month) open the document list from here.

Open the documents

What this grant of permission means

Aberdeenshire granted permission on 27 November 2020, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About full applications

A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.

Nearby applications

Within 0.3 miles

In Aberdeenshire

  • APP/2026/1621 Awaiting decision

    Base Station Tullich Invercauld Estate Pass Of Ballater Aberdeenshire

    Installation Of Generator

    Received 25 Sep, published by the council 2 Oct 2026 Full applications
  • APP/2026/1506 Awaiting decision

    Surfside Caravan Park Harbour Road Fraserburgh AB43 9TB

    Extension to Caravan Site Operating Times (March to January)

    Received 2 Sep, published by the council 3 Sep 2026 Full applications
  • APP/2026/1489 Awaiting decision

    3 Gean Court Balmedie AB23 8ST

    Extension to Dwellinghouse and Installation of Flue

    Received 31 Aug, published by the council 2 Sep 2026 Full applications
  • APP/2026/1494 Awaiting decision

    18 David Mclean Drive Alford Aberdeenshire AB33 8PW

    Erection of Garden Room (Retrospective)

    Received 31 Aug, published by the council 3 Sep 2026 Full applications
  • APP/2026/1476 Awaiting decision

    Huntly Hotel 18 The Square Huntly Aberdeenshire AB54 8BR

    Alterations to Hotel Including Replacement Doors

    Received 28 Aug, published by the council 3 Sep 2026 Full applications