Northern Shetland 220kV To Kergord 132kV
Decided. The decision notice on the council portal carries the outcome in full, including any conditions.
Proposal
To run overhead line between North of Kergord Converter Station running generally parallel to the A970 before passing Voe and running alongside the A968 towards the Toft / Scatsta area.
As published by the council, reference 2025/279/ECUCON
Application record
- Reference
- 2025/279/ECUCON
- Type
- Energy Consents Unit
- Status
- Pending Consideration
- Decision
- Offer observations
- Received
- 27 Oct 2025
- Validated
- 27 Oct 2025
- Decided
- 30 Oct 2025
Site history
Applications at this address on the Shetland Islands register
This site has had 2 applications since 2025.
-
2025/252/ECUCON Decided
Northern Shetland 220kV To Kergord 132kV
To run overhead line from the existing Kergord 132kV substation past Voe and onto a proposed 220kV northern substation near to Sullom Voe Terminal.
Timeline
Dates from the published record
-
27 Oct 2025
Received by Shetland Islands
-
30 Oct 2025
Decision issued: Offer observations
-
28 Jul 2026
Added to PlanIndex
Related applications
Cases linked to this one on the register
- Application: 2025/252/ECUCON
Documents
Plans, drawings, consultee responses and the officer's report
2 documents on file for this application
- ROUTE OPTIONS
- PRE-APPLICATION CONSULTATION NOTICE FORM
Watch members (£5 a month) open the document list from here.
Open the documentsAfter the decision
Shetland Islands has decided this application; the outcome above is the register's own wording and the decision notice on the council portal carries the detail. More in our guide to what happens after a planning decision.
About this record
The published feed does not state which type of application this is; the register entry on Shetland Islands's portal will say. Our guide explains the common types.